9-Mile Pump Station construction

Outcome

Submissions closed on 20 October 2026. No award has been published yet. Open tenders like this one are listed below.

Amendment 0005 (14 October 2026) confirms the bid deadline remains 20 October 2026 at 14:00 Eastern and the bid opening is at 14:30 Eastern; the submission window has ended.

Place
St. Clair Shores, Macomb County, Michigan, United States
Bid submission deadline
06:00 PM · UTC
Contract value
Not stated in the notice
Contract period
An 880-day period of performance; the start date is not stated in the current notice.
Published
October 7, 2026
SAM.gov

Overview

The U.S. Army Corps of Engineers (USACE) Detroit District, in partnership with Macomb County Public Works, seeks a firm-fixed-price construction contractor for a new 9-Mile Pump Station in St. Clair Shores, Michigan. The project separates the 8-1/2 Mile Relief Drain from the 9-Mile Drain and is intended to reduce flood risk and protect Lake St. Clair water quality. Amendment 0005, issued on 14 October 2026, confirms bids remain due on 20 October at 2:00 p.m. Eastern, with opening at 2:30 p.m. Eastern. The bid-submission period has ended. The notice states an 880-day period of performance.

Information based on the public notice

What the buyer needs

Construction of a new 9-Mile Pump Station in St. Clair Shores, Michigan, to separate the 8-1/2 Mile Relief Drain from the 9-Mile Drain.

  • The notice seeks a contractor for a firm-fixed-price construction contract.

Tender details

Buyer
U.S. Army Corps of Engineers (USACE) Detroit District
Country
United States
Procedure
Solicitation
Classification
Construction and civil works · NAICS 237110 · PSC Y1NZ
Notice reference
39366c2cec054289903fead6f65ec934 · W911XK26BA028
Bid deadline
20 October 2026, 2:00 p.m. EDT (UTC−04:00)
Bid opening
20 October 2026, 2:30 p.m. EDT (UTC−04:00)
Period of performance
880 days
Contract type
Firm-fixed-price construction contract
Buyer telephone
3132262767

What to check in the tender documents

  • The estimated value, award status or result, evaluation criteria and detailed construction requirements are not stated in the current notice.
Get started with Ziva

Original notice

Read the original description

9-Mile Pump Station

****Amendment 0005 is being issued on October 14, 2026. The bid due date will remain October 20, 2026 at 2:00pm (Eastern) with corresponding bid opening at 2:30 PM (Eastern) the day bids are due. ****Amendment 0004 is being issued on October 7, 2026. Bid due date is extended to October 20, 2026 at 2:00pm (ET)****Amendment 0003 is being issued on September 24, 2026. The bid inquiry is reopen until October 01, 2026. ***Amendment 0002 is being issued on September 18, 2026. The Bid Inquiry will remain closed at this time, and will be reopened upon the issuance of a forthcoming amendment.**** ***Amendment 0001 is being issued on September 11, 2026. The Bid Inquiry will remain closed at this time, and will be reopened upon the issuance of a forthcoming amendment. *** The U.S. Army Corps of Engineers (USACE) Detroit District, in partnership with the Macomb County Public Works (MCPW), is seeking contractors for a Firm-Fixed-Price (FFP) construction contract for the 9-Mile Pump Station project located in St. Clair Shores, Macomb County, Michigan. The project entails constructing a new 9-Mile Pump Station to separate the 8-1/2 Mile Relief Drain from the 9-Mile Drain. Operating under an 880-day Period of Performance, this effort is designed to significantly reduce flood risks for southeast Michigan residents and better protect the water quality of Lake St. Clair.

Official source: SAM.gov ↗

Notice updates

October 21, 2026 · Version 2

Buyer updated · Classification updated · Contract period updated · Deadline information updated · Summary and analysis updated · Tender facts updated · Original notice updated · Deadline updated · Location updated · Source notice details updated · Source references updated · Status changed · Notice update added

9-Mile Pump Station

****Amendment 0005 is being issued on October 14, 2026. The bid due date will remain October 20, 2026 at 2:00pm (Eastern) with corresponding bid opening at 2:30 PM (Eastern) the day bids are due. ****Amendment 0004 is being issued on October 7, 2026. Bid due date is extended to October 20, 2026 at 2:00pm (ET)****Amendment 0003 is being issued on September 24, 2026. The bid inquiry is reopen until October 01, 2026. ***Amendment 0002 is being issued on September 18, 2026. The Bid Inquiry will remain closed at this time, and will be reopened upon the issuance of a forthcoming amendment.**** ***Amendment 0001 is being issued on September 11, 2026. The Bid Inquiry will remain closed at this time, and will be reopened upon the issuance of a forthcoming amendment. *** The U.S. Army Corps of Engineers (USACE) Detroit District, in partnership with the Macomb County Public Works (MCPW), is seeking contractors for a Firm-Fixed-Price (FFP) construction contract for the 9-Mile Pump Station project located in St. Clair Shores, Macomb County, Michigan. The project entails constructing a new 9-Mile Pump Station to separate the 8-1/2 Mile Relief Drain from the 9-Mile Drain. Operating under an 880-day Period of Performance, this effort is designed to significantly reduce flood risks for southeast Michigan residents and better protect the water quality of Lake St. Clair.

October 14, 2026 · Version 1

Published

9-Mile Pump Station

****Amendment 0004 is being issues on October 7, 2026. Bid due date is extended to October 20, 2026 at 2:00pm (ET)****Amendment 0003 is being issued on September 24, 2026. The bid inquiry is reopen until October 01, 2026. ***Amendment 0002 is being issued on September 18, 2026. The Bid Inquiry will remain closed at this time, and will be reopened upon the issuance of a forthcoming amendment.**** ***Amendment 0001 is being issued on September 11, 2026. The Bid Inquiry will remain closed at this time, and will be reopened upon the issuance of a forthcoming amendment. *** The U.S. Army Corps of Engineers (USACE) Detroit District, in partnership with the Macomb County Public Works (MCPW), is seeking contractors for a Firm-Fixed-Price (FFP) construction contract for the 9-Mile Pump Station project located in St. Clair Shores, Macomb County, Michigan. The project entails constructing a new 9-Mile Pump Station to separate the 8-1/2 Mile Relief Drain from the 9-Mile Drain. Operating under an 880-day Period of Performance, this effort is designed to significantly reduce flood risks for southeast Michigan residents and better protect the water quality of Lake St. Clair.