Track renewal between Mersch and Cruchten on Luxembourg Line 1

Outcome

Submissions closed on 9 November 2026. No award has been published yet. Open tenders like this one are listed below.

Place
Railway Line 1 between Mersch and Cruchten, Luxembourg
Submission deadline: 9 November 2026 at 10:00. TED prints the deadline time with +02:00, its date with +01:00; the canonical snapshot records 09:00 UTC. These source representations are retained without inferring a conversion.
08:00 AM · UTC
Contract value
Not stated in the notice
Contract period
Preparation may begin two weeks before the main closure (22 March–12 April 2027 at 01:00); finishing works must be complete by the end of April 2027.
Published
October 10, 2026
Luxembourg public procurement portal and official TED notice

Overview

Société Nationale des Chemins de Fer Luxembourgeois (CFL) seeks bids for renewal of both main tracks over approximately 8.7 km between Mersch and Cruchten on Line 1. The work includes modernizing track components, installing B 70 W monoblock concrete sleepers with elastic rail fastenings and UIC60 rails, and partially replacing and cleaning blast-furnace ballast with natural-stone ballast. A full line closure is scheduled from 22 March through 12 April 2027 at 01:00. Preparatory work may begin two weeks before the closure; finishing work must be complete by the end of April. This is a European restricted works procedure under special-sector rules, with no variants accepted. The public portal lists submissions through its portal. The deadline is 9 November 2026 at 10:00; TED prints +02:00 for the time and +01:00 for the date, while the available notice information records 09:00 UTC. Buyer contact: gi.planificationressources@cfl.lu; appeal body: Tribunal administratif, Luxembourg.

Information based on the public notice

What the buyer needs

Renewal of approximately 8.7 km of the left and right main tracks between Mersch and Cruchten, including track component modernization, concrete sleepers, UIC60 rails and partial ballast replacement and cleaning.

  • European restricted special-sectors procedure. Submissions are through the public procurement portal; variants are not accepted.

Tender details

Buyer
Société Nationale des Chemins de Fer Luxembourgeois (CFL)
Country
Luxembourg
Procedure
European restricted works procedure, special sectors
Classification
Railway track renewal works
Notice reference
545876
Buyer contact
Service Gestion Infrastructure, Division Planification Ressources; +352 24895730; gi.planificationressources@cfl.lu
Worksite
Line 1 between Mersch and Cruchten, Luxembourg
Scope
Renewal of both main tracks for approximately 8.7 km; B 70 W concrete sleepers, elastic fastenings, UIC60 rails and partial ballast replacement/cleaning
Rail closure
22 March–12 April 2027; end time 01:00
Submission
Through Luxembourg public procurement portal; no variants accepted
Deadline
9 November 2026 at 10:00; TED time offset +02:00 and date offset +01:00; snapshot separately records 09:00 UTC
Appeal body
Tribunal administratif, Luxembourg

What to check in the tender documents

  • No estimated value is stated. The TED time and date fields carry different offsets (+02:00 and +01:00); the available notice information separately records 09:00 UTC.
Get started with Ziva

Original notice

Read the original description

Dans le cadre du projet, il est prévu de réaliser les travaux suivants: renouvellement des voies courantes principales (voie gauche et voie droite) sur une longueur d'environ ± 8.700 m’ avec modernisation des différents composants, comprenant notamment la mise en oeuvre de traverses en béton mono-bloc B 70 W avec fixation élastique des rails, mise en oeuvre de rails UIC60 et , remplacement et nettoyage partiellement du ballast en matériel de haut-fourneau par du ballast en pierre naturelle. La phase principale (période de barrage complet de la ligne ferroviaire) des travaux de renouvellement de voie a lieu du lundi 22.03.2027 jusqu'au lundi 12.04.2027 (01h00). Les travaux préparatoires peuvent débuter 2 semaines avant la période de barrage de voie et les travaux de finition doivent être achevés pour fin avril 2027.

Dans le cadre du projet, il est prévu de réaliser les travaux suivants: renouvellement des voies courantes principales (voie gauche et voie droite) sur une longueur d'environ ± 8.700 m’ avec modernisation des différents composants, comprenant notamment la mise en oeuvre de traverses en béton mono-bloc B 70 W avec fixation élastique des rails, mise en oeuvre de rails UIC60 et , remplacement et nettoyage partiellement du ballast en matériel de haut-fourneau par du ballast en pierre naturelle. La phase principale (période de barrage complet de la ligne ferroviaire) des travaux de renouvellement de voie a lieu du lundi 22.03.2027 jusqu'au lundi 12.04.2027 (01h00). Les travaux préparatoires peuvent débuter 2 semaines avant la période de barrage de voie et les travaux de finition doivent être achevés pour fin avril 2027.

Official source: Luxembourg public procurement portal and official TED notice ↗