Overview

The City of Fayzobod’s water and wastewater project is procuring Package 5, rehabilitation of its existing wastewater treatment plant. The official EBRD ECEPP notice describes design and construction of new facilities on the existing site, demolition, network connections, a treated-effluent outfall and bank protection on the Loyak River. Mandatory capacity is 1,500 m³/day, with separately priced options to reach 3,000 m³/day. Proposals must be submitted electronically through ECEPP by 27 November 2026 at 10:00 UK time. This Swiss-canonical mirrored record is retained under its leased CH classification; ECEPP is the binding source. The notice does not state a contract value.

Information based on the public notice

What the buyer needs

Design and build a new wastewater treatment plant at the existing Fayzobod plant site, demolish existing structures, connect external networks, provide a treated-effluent outfall and Loyak River bank protection. Mandatory capacity is 1,500 m³/day; separately priced optional works raise it to 3,000 m³/day.

  • This Swiss-canonical mirrored record is retained under its leased CH classification; ECEPP is the binding source.

Tender details

Buyer
City of Fayzobod, State Unitary Enterprise Khojagii Manziliyu Kommunali
Country
Switzerland
Procedure
open
Classification
Construction and civil works · CPV 45232420
Notice reference
45703 · 45703-01
Scope
Design and build a new wastewater treatment plant at the existing Fayzobod plant site, demolish existing structures, connect external networks, provide a treated-effluent outfall and Loyak River bank protection. Mandatory capacity is 1,500 m³/day; separately priced optional works raise it to 3,000 m³/day.
Offer deadline
27 November 2026, 10:00 UK time (ECEPP notice time)

What to check in the tender documents

  • The public notice does not state a contract value.
Get started with Ziva

Original notice

Read the original description

Rehabilitation of the Water Supply and Wastewater System in Fayzobod region, Tajikistan

Official EBRD ECEPP notice, “Tajikistan: Package 5 Rehabilitation of existing Wastewater Treatment Plant (WWTP)”. Project: Fayzobod Water and Wastewater Project (EBRD project 52574); client: City of Fayzobod; type: Works; method: Open Tender Single Stage. Publication 15 October 2026; issue 15 October 2026 at 10:00; closing 27 November 2026 at 10:00 UK time. The contract covers design and construction of new wastewater treatment facilities at the existing plant site, demolition of existing structures, connection to external networks, treated-effluent outfall and bank protection on the Loyak River. Mandatory treatment capacity is 1,500 m³/day; optional works, priced separately, increase capacity to 3,000 m³/day. Proposals are submitted electronically using ECEPP. The legally binding notice identifies the City of Fayzobod as client and links this exercise to ECEPP ID 36512955.

Official source: EBRD ECEPP ↗

Notice updates

October 20, 2026 · Version 2

Classification updated

Rehabilitation of the Water Supply and Wastewater System in Fayzobod region, Tajikistan

Official EBRD ECEPP notice, “Tajikistan: Package 5 Rehabilitation of existing Wastewater Treatment Plant (WWTP)”. Project: Fayzobod Water and Wastewater Project (EBRD project 52574); client: City of Fayzobod; type: Works; method: Open Tender Single Stage. Publication 15 October 2026; issue 15 October 2026 at 10:00; closing 27 November 2026 at 10:00 UK time. The contract covers design and construction of new wastewater treatment facilities at the existing plant site, demolition of existing structures, connection to external networks, treated-effluent outfall and bank protection on the Loyak River. Mandatory treatment capacity is 1,500 m³/day; optional works, priced separately, increase capacity to 3,000 m³/day. Proposals are submitted electronically using ECEPP. The legally binding notice identifies the City of Fayzobod as client and links this exercise to ECEPP ID 36512955.

October 15, 2026 · Version 1

Published

Rehabilitation of the Water Supply and Wastewater System in Fayzobod region, Tajikistan

Official EBRD ECEPP notice, “Tajikistan: Package 5 Rehabilitation of existing Wastewater Treatment Plant (WWTP)”. Project: Fayzobod Water and Wastewater Project (EBRD project 52574); client: City of Fayzobod; type: Works; method: Open Tender Single Stage. Publication 15 October 2026; issue 15 October 2026 at 10:00; closing 27 November 2026 at 10:00 UK time. The contract covers design and construction of new wastewater treatment facilities at the existing plant site, demolition of existing structures, connection to external networks, treated-effluent outfall and bank protection on the Loyak River. Mandatory treatment capacity is 1,500 m³/day; optional works, priced separately, increase capacity to 3,000 m³/day. Proposals are submitted electronically using ECEPP. The legally binding notice identifies the City of Fayzobod as client and links this exercise to ECEPP ID 36512955.