Replacement of superheater 3 for the Forsthaus wood-fired combined heat and power plant

Energie Wasser BernSwitzerlandClosed

Outcome

Submissions closed on 6 October 2026. No award has been published yet. Open tenders like this one are listed below.

Place
Switzerland
Submission deadline
09:59 PM · UTC
Contract value
Not stated in the notice
Lots
1 lot
Classification
Boiler installations
Published
August 25, 2026
TED / SIMAP

Overview

Energie Wasser Bern is procuring replacement superheater tubing for units 3 and 2b at its Forsthaus wood-fired combined heat and power plant. The two packages comprise 31 tube coils each, about 7,000 kg of boiler tubes in total, with a 38 mm diameter. The existing tubes are expected to reach their technical service life within about two years. Dismantling is expected to begin on 7 August 2028, with final acceptance expected on 23 August 2028. Offers were due 6 October 2026 at 23:59 +02:00 and remain valid for 180 days. No value is stated.

Information based on the public notice

What the buyer needs

Replace the superheater tubing for units 3 and 2b at the Forsthaus plant, including two packages of 31 coils each; dismantling and final acceptance are expected in August 2028.

  • Submit through DecisionAdvisor; the printed supplier report must also be signed and delivered to the procurement office.

Lots

LOT-0000 ·EBP-671 Ersatz Endüberhitzer 3 für HHKW

Tender details

Buyer
Energie Wasser Bern
Country
Switzerland
Procedure
open
Classification
Boiler installations · CPV 42160000 · CPV 09323000
Notice reference
588405-2026
Submission deadline
2026-10-06T23:59:00+02:00
Planned execution
Voraussichtlich August 2028: - Beginn der Demontage: voraussichtlich 07.08.2028 - Endabnahme: voraussichtlich 23.08.2028

What to check in the tender documents

  • No estimated value is stated in the notices. Detailed technical specifications and evaluation details are referred to the tender documents.
Get started with Ziva

Original notice

Read the original description

EBP-671 Ersatz Endüberhitzer 3 für HHKW

Official TED title: Schweiz – Kesselanlagen – EBP-671 Ersatz Endüberhitzer 3 für HHKW Description of procurement (TED, verbatim): Mit vorliegender Beschaffung des Holzkraftwerks (HHKW) in der Energiezentrale Forsthaus (EZF), beabsichtigt Energie Wasser Bern die bestehenden Überhitzerrohre des Überhitzers 3 und 2b zu ersetzen. Die Überhitzerrohre haben in den nächsten ca. 2 Jahren ihr technisches maximales Lebensalter erreicht und müssen entsprechend ersetzt werden. Bei den Überhitzer 3 und 2b handelt es sich um 2 Pakete mit je 31 Rohrschlangen mit einem Gewicht von total ca. 7000kg Kesselrohren mit einem Durchmesser von 38mm. Project description (SIMAP, verbatim): Mit vorliegender Beschaffung des Holzkraftwerks (HHKW) in der Energiezentrale Forsthaus (EZF), beabsichtigt Energie Wasser Bern die bestehenden Überhitzerrohre des Überhitzers 3 und 2b zu ersetzen. Die Überhitzerrohre haben in den nächsten ca. 2 Jahren ihr technisches maximales Lebensalter erreicht und müssen entsprechend ersetzt werden. Bei den Überhitzer 3 und 2b handelt es sich um 2 Pakete mit je 31 Rohrschlangen mit einem Gewicht von total ca. 7000kg Kesselrohren mit einem Durchmesser von 38mm. Execution note (SIMAP, verbatim): Voraussichtlich August 2028: - Beginn der Demontage: voraussichtlich 07.08.2028 - Endabnahme: voraussichtlich 23.08.2028 Published submission deadline: 6 October 2026, 23:59 +02:00. Offer validity: 180 days.

Official source: TED / SIMAP ↗