Two-storey Fertilizer and Pesticide Authority office construction in Leyte

Outcome

Submissions closed on 19 October 2026. No award has been published yet. Open tenders like this one are listed below.

Place
Philippines
Bid deadline: 19 October 2026 at 09:30, BAC Secretariat time.
Time not stated
Contract value
Not stated in the notice
Lots
1 lot
Contract period
130 calendar days after receipt of the Notice to Proceed.
Published
October 9, 2026
PS-PhilGEPS

Overview

The Department of Agriculture Regional Field Office VIII seeks a contractor to supply labour and materials for a two-storey Fertilizer and Pesticide Authority regional office at the Babatngon Experiment Station in Leyte. The public notice describes a broad building works package, including earthworks, structural concrete and reinforcement, finishes, roofing, plumbing, electrical and mechanical works. The approved contract budget is PHP 25,000,000, not an award. Completion is due within 130 calendar days after notice to proceed. Bids are due by 09:30 on 19 October 2026 at the BAC Secretariat; the notice expressly refers to BAC Secretariat time. It requires a similar completed contract and detailed post-qualification submissions.

Information based on the public notice

What the buyer needs

Construction of a two-storey Fertilizer and Pesticide Authority regional office at the Babatngon Experiment Station, including the listed site works, structure, finishes, utilities and related construction works. Completion is set at 130 calendar days after notice to proceed.

  • Bidders must have completed a similar contract within five years. At bid opening, the notice requires site inspection evidence and a signed/sealed compliance certificate. Post-qualification requires schedules, construction methods, equipment and manpower information, and signed/sealed plans and specifications. The winning contractor must provide the listed insurance, safety, quality and reporting obligations.

Lots

1 ·Two-storey Fertilizer and Pesticide Authority Regional Office VIII

Tender details

Buyer
Department of Agriculture, Regional Field Office VIII
Country
Philippines
Procedure
Competitive Bidding (Public Bidding)
Classification
Public building construction
Notice reference
97504
Approved contract budget
PHP 25,000,000.00
Completion period
130 calendar days after notice to proceed
Similar contract experience
Similar contract completed within the previous five years

What to check in the tender documents

  • The notice refers to bidding documents for full eligibility details and to technical drawings/specifications; those supporting files were not opened. Payment milestones are tied to verified physical accomplishment and project acceptance.
Get started with Ziva

Original notice

Read the original description

Supply Labor and Materials for the Construction of Two (2) Storey fertilizer and Pesticide Authority Regional Office VIII in Babatngon Experiment Station

Invitation to Bid for Supply labor and materials for the Construction of Two (2) Storey Fertilizer and Pesticide Authority Regional Office VIII in Babatngon Experiment Station, Babatngon, Leyte DA8-INFRA-2026-18 (ID No. BT-26-INFRA-FPA-RF08-35727-0001) The D ep a r t m e n t o f A g r i c u l t u r e- R e g i o n a l F i e l d Of f ic e N o. 8 , through the Construction of Fertilizer and Pesticide Authority Regional Field Unit VIII Building (Project) intends to apply the sum of Twenty-five Million Pesos (PhP25,000,000.00) being the Approved Budget for the Contract (ABC) to payments under the contract for Supply labor and materials for the Construction of Two (2) Storey Fertilizer and Pesticide Authority Regional Office VIII in Babatngon Experiment Station, Babatngon, Leyte . Bids received in excess of the ABC shall be automatically rejected at bid opening. The D ep a r t m e n t o f A g r i c u l t u r e- R e g i o n a l F i e l d Of f ic e N o. 8 now invites bids for above Procurement Project .  Completion of the Works is required One Hundred Thirty (130) Calendar days after receipt of Notice to Proceed . Bidders should have completed, within Five (5) years from the date of submission and receipt of bids, a contract similar to the Project. The description of an eligible bidder is contained in the Bidding Documents, particularly, in Section II. Instructions to Bidders (ITB). Quantity UOM Description Total Cost Supply labor and materials for the Construction of Two (2) Storey Fertilizer and Pesticide Authority Regional Office VIII in Babatngon Experiment Station, Babatngon, Leyte 25,000,000.00 SPECIAL ITEMS 1 L.s Generator Set Housing 1 L.s Floor Boards & Wall Boards Installation MISCELLANEOUS STRUCTURES 1 L.s. Roadway Lighting GENERAL REQUIREMENTS 1 L.s Temporary Facility (Barracks & Isolation Facility) 1 L.s Permits and Clearances 1 L.s. Project Billboard/Signboard 1 L.s. Occupational Safety and Health Program 1 L.s. Mobilization and Demobilization 1 L.s. Geotechnical Exploration EARTHWORKS 1000 cu m. Embankment from Borrow, Common Soil 975 cu m. Structural Excavation 800 cu m. Embankment from Structure Excavation 125 cu m. Gravel Bedding STRUCTURAL CONCRETE 262 cu m. Structural Concrete, Class A (Ready Mix Concrete) 36980 kg Reinforcing Steel (Deformed) 734 sq.m Falseworks and Formworks FINISHING AND OTHER CIVIL WORKS Masonry Works 180 sq. m. 150mm CHB Non Load Bearing Fabricated Materials 1 L.s. Finishing Hardware 1 sq.m Steel Doors and Frames 73 sq.m Aluminum Glass Window (Sliding/ Casement/ Awning/ Fixed Type) 1 L.s Wooden Doors and Windows 15 sq.m PVC Doors and Frames 1 L.s Structural Steel 1 L.s Metal Structure Accessories 477 sq.m 4.5mm Fiber Cement Board on Metal Frame Ceiling 16 sqm Tempered Glass, 12mm 113 sqm Waterproofing, Cement-Base 586 sq. m. Glazed Tiles and Trims 117 sq. m. Unglazed Tiles 1 L.s. Railing Painting Works 2211 sqm Painting Works, Masonry/Concrete 37 sqm Painting Works , Wood 26 sqm Painting Works, Steel Roofing Works 21 L.m. Fabricated Metal Roofing Accessory, Gauge 26 (0.551mm), Ridge/Hip Rolls 25 L.m. Fabricated Metal Roofing Accessory, Gauge 26 (0.551mm), Flashing 252 L.m. Prepainted Metal Sheets, Corrugated Type, Long Span, above 0.427mm Plumbing Works 1 L.s. Sewer Line Works 1 L.s. Storm Drainage and Downspout 1 L.s. Septic Vault, Concrete/ CHB 1 L.s. Plumbing Fixtures 1 L.s. Cold Water Lines 1 L.s. Cistern 1 L.s. Plumbing Works Electrical 1 L.s Conduits, Boxes, & Fittings 1 L.s Wires and Wiring Devices 1 L.s Panelboard with Main & Branch Breakers 1 L.s Pole Mounted Distribution Transformer (OISC) with Complete Accessories, Pole Type 1 L.s Generator, Three Phase, Stand-by 1 L.s. Lighting Fixtures 1 L.s CCTV System Mechanical 1 L.s Airconditioning, Package/ Split Type 1 L.s Fire Extinguisher 1 L.s. Fire Alarm System Terms and Conditions: A. During the opening of bids, bidders shall: 1. Submit Certificate of Project Site Inspection issued by Barangay Officials or Affidavit of Site Inspection, and; 2. Submit Certificate of Compliance to the attached drawings duly signed by the bidder’s authorized representative and signed and sealed by a Licensed Civil Engineer. B. All participating bidder must comply with Section B of DPWH D.O. No. 30 series of 2025, particularly in the computation OCM & Profit of the bid amount. C. During Post-Qualification Evaluation 1. In the TWG evaluation/review of bid offer finding any change(s) particularly a decrease of bid amount but found out to be complying with all the requirement of the project, if comformed by the bidder with the lowest calculated bid shall be the basis of recommendation of award of contract after full compliance of post-qualification requirement; 2. Submit PERT/CPM and S-Curve; 3. Construction Methods; 4. Manpower Schedule; 5. Major Equipment Schedule, and 6. Submit Plans, Design, and Specification signed and sealed by a Licensed Civil Engineer. D. Winning bidder shall: 1. Provide Contractor's All Risk Insurance (CARI) 2. Commence construction works within seven (7) days after receipt of Notice to Proceed (NTP); 3. Complete the construction within 130 calendar days; 4. Provide necessary tools/equipment for the satisfactory completion of the project; 5. Assume full responsibility from the time project construction commences up to the final acceptance by DARFO 8 and shall be held responsible for any damage in part or in whole except those occasioned by force majeure; 6. Assign a Project Engineer (either Licensed Agricultural Engineer or Civil Engineer) that will oversee the daily construction activities on site; 7. Comply with the Quality Control Program (QCP) schedule of minimum testing requirements of the end-user; if applicable 8. Submit Material Test Report or its equivalent standard certificate for aggregate (sand & gravel), and cement; 9. Submit material test result from accredited testing laboratory for Concrete, and Reinforcing Bar with geotagged photos if applicable; 10 Attend pre-construction meeting; 11. In case of time extension due to unworkable weather condition, submit the request with PAG-ASA weather report and on-site weather chart within the succeeding month with corresponding geotagged photos using approved DA camera app and time-lapse video; 12. The cameras to be used for time-lapse recording shall preferably be Brinno TLC300 or its equivalent, with a minimum of two (2) cameras installed. The time-lapse videos shall be submitted on a daily basis and shall form part of the documentary requirements prior the release of payment. The cost of procuring the cameras shall be shouldered by the contractor; 13. Secure and Facilitate the necessary permits such as but not limited to building permit required for the project implementation; 14. Strictly observe construction safety rules and health program approved by Department of Labor and Employment (DOLE) during project implementation; and 15. Submit a stake plan in case there are changes in the plans during project staking. E. Any delay in the project completion shall be subjected to Liquidated Damages (LD) equivalent to at least 1/10 of 1% of the cost of the unperformed portion of the works for everyday of delay. LD shall apply even after ninety-five percent (95%) physical acc F. Be paid through partial billing based on validated/verified Statement of Work Accomplishment (SWA) with geo-tagged photos on major works (before, during, and after) and Inspection Report by the DA-RFO8 Inspectorate Team. 1. Atleast 35% of the physical accomplishment; 2. Atleast 60% of the physical accomplishment; 3. Atleast 80% of the physical accomplishment, and; 4. 100% of the physical accomplishment subject to project acceptance. G. Advance payment (maximum of 15%) will be granted upon submission of the following requirements: 1. Advance Payment Bond by the bidder 2. Request for the immediate On-Site Evaluation Report by the DA project engineer H. Winning bidder shall submit a snapshot of a business bank account (preferably Landbank) to effect payment. I. Discount in the bid offer is not allowed. Bidding will be conducted through competitive bidding procedures using a non-discretionary “pass/fail” criterion as specified in the IRR, otherwise known as the “New Government Procurement Act (NGPA)”. Bidding is restricted to Filipino citizens/sole proprietorships, cooperatives, and partnerships or organizations with at least sixty percent (60%) interest or outstanding capital stock belonging to citizens of the Philippines. Interested bidders may obtain further information from [ D ep a r t m e n t o f A g r i c u l t u r e- R e g i o n a l F i e l d Of f ic e N o. 8 and inspect the Bidding Documents at the address given below from 8 :00AM to 5:00 PM . A complete set of Bidding Documents may be acquired by interested bidders on October 10, 2026 to November 03, 2026 from the address given below and websites upon payment of the applicable fee for the Bidding Documents, pursuant to the latest Guidelines issued by the GPPB, in the amount of Twenty-five thousand pesos (P25,000.00) It may also be downloaded free of charge from the website of the Philippine Government Electronic Procurement System (PhilGEPS) and the website of the Procuring Entity , provided that bidders shall pay the applicable fee for the Bidding Documents not later than the submission of their bids. The R e g i o n a l F i e l d Of f ic e N o. 8 will hold a Pre-Bid Conference on October 19, 2026, 9:30 AM (BAC-Secretariat time) at DA8 BAC Office, 4 th floor Green Bldg., Kanhuraw Hill, Tacloban City and/or through video conferencing via googlemeet , which shall be open to prospective bidders. Bids must be duly received by the Bids and Awards Committee (BAC) Secretariat through through manual submission at the office address indicated below on or before November 03, 2026 9:00 AM (BAC-Secretariat time) . Late bids shall not be accepted. 8) All Bids must be accompanied by a Bid Security in any of the acceptable forms and in the amount stated in ITB Clause 1 6 . 9) Bid opening shall be on November 03, 2026, 9:30 AM (BAC-Secretariat time) at DA8 BAC Office, 4 th floor Green Bldg., Kanhuraw Hill, Tacloban City and/or via googlemeet . Bids will be opened in the presence of the Bidders’ representatives who choose to attend the activity. 10) DA DOES NOT CONDONE ANY FORM OF SOLICITATION ON ANY PROSPECTIVE WINNING AND LOSING BIDDERS BY ANY OF OUR STAFF/EMPLOYEES OR ANY OTHER PARTY. ANY SORT OF THIS KIND SHALL BE REPORTED IMMEDIATELY TO THE OFFICE OF THE SECRETARY OR THE NATIONAL BUREAU OF INVESTIGATION (NBI) FOR ENTRAPMENT AND PROPER INVESTIGATION. 11) The D ep a r t m e n t o f A g r i c u l t u r e- R e g i o n a l F i e l d Of f ic e N o. 8 reserves the right to reject any and all bids, declare a failure of bidding, or not award the contract at any time prior to contract award in accordance with Section 70 of R.A. No. 12009, without thereby incurring any liability to the affected bidder or bidders. 12) For further information, please refer to: JUVANNI D. AYASO Head, BAC-Secretariat Department of Agriculture, Regional Field Office-8 Kanhuraw Hill, Tacloban City bacsec@rfo8.da.gov.ph Mobile No. 09368484434 easternvisayas.da.gov.ph You may visit the following websites: For downloading of Bidding Documents: www.philgeps.gov.ph or easternvisayas.da.gov.ph October 10, 2026 (SGD.) LEONARDA A. LONDINA, Ph.D. BAC Chairperson

Official source: PS-PhilGEPS ↗