I/45 Krnov western bypass construction

Outcome

Submissions closed on 9 November 2026. No award has been published yet. Open tenders like this one are listed below.

Place
Czechia
Submission deadline
11:00 PM · UTC
Contract value
CZK 1,150,000,000
estimated value
Lots
1 lot
Contract period
37 months
Published
September 24, 2026
TED

Overview

The Czech Road and Motorway Directorate seeks construction of about 3.4 km of the I/45 western bypass outside built-up Krnov, including its connection to the I/57. The estimated value is CZK 1.15 billion and the planned period is 37 months.

Information based on the public notice

What the buyer needs

The single-lot works deliver a new bypass route outside Krnov and connect it to the I/57. The stated length is approximate; TED gives a 37-month period and estimated total value.

Lots

LOT-0001 ·I/45 Krnov - západní obchvat

Tender details

Buyer
Ředitelství silnic a dálnic s. p.
Country
Czechia
Procedure
open
Classification
Road construction · CPV 45233120
Notice reference
662334-2026
Submission deadline
2026-11-10+01:00 at 08:00:00+01:00
Estimated value
1,150,000,000 CZK
Planned contract period
37 months

Original notice

Read the original description

I/45 Krnov - západní obchvat

I/45 Krnov - západní obchvat Předmětem veřejné zakázky je realizace stavby „I/45 Krnov – západní obchvat“, spočívající ve výstavbě přeložky silnice I/45 mimo zastavěné území města Krnova v délce cca 3,4 km, včetně napojení na silnici I/57.

Official source: TED ↗