Compliance works for fire-detection installations in provincial buildings
Outcome
Submissions closed on 12 November 2026. No award has been published yet. Open tenders like this one are listed below.
The current BOSA record lists 12 November 2026 at 11:00 CET. The TED publication dated 15 October 2026 listed 5 November 2026 at 11:00 CET.
- Place
- Belgium, areas BE331, BE332 and BE335
- 12 November 2026 at 11:00 CET (UTC+01:00)
- 10:00 AM · UTC
- Contract value
- Not stated in the notice
- Lots
- 6 lots
- Contract period
- Estimated duration: 90 days for lot 1; 80 days each for lots 2 and 3; 60 days each for lots 4 and 5; 50 days for lot 6.
- Published
- October 30, 2026
- Belgian BOSA e-Procurement
Overview
The Province de Liège seeks works to bring fire-detection installations into compliance in several provincial buildings, mainly boarding schools. The open procedure has six lots in Verviers, Liège and Huy. The BOSA notice record gives an offer deadline of 12 November 2026 at 11:00 CET; the 15 October TED publication gave 5 November 2026 at 11:00 CET. Detailed technical requirements and selection criteria are in the tender documents.
Information based on the public notice
Ask about this tender
What the buyer needs
Works to bring fire-detection systems into compliance in several provincial buildings, especially boarding schools.
- Offers must be submitted electronically at https://www.publicprocurement.be/supplier/enterprises/0/tendering-workspaces/publication-workspace-detail/3293cca9-13e3-4aa0-834a-567775493dc4/general, in French. An advanced or qualified electronic signature or seal is required. Electronic catalogues are not permitted.
- Offers must remain valid for 240 days. Electronic invoicing is required; electronic orders are not used, and electronic payment is used.
- The notice has six lots. A bidder may bid for and be awarded up to six lots. Participation is not reserved; the notice states that the procurement is not EU-funded and is not covered by the Government Procurement Agreement. It is not a framework agreement or a dynamic purchasing system.
- The notice refers to the procurement documents for exclusion grounds and selection criteria; their detailed thresholds and technical specifications are not stated in the notice.
- Functional contact telephone: +32 42797170. Reference: 90.01-198. Main CPV: 45310000-3; lot CPV: 45312100-8.
- A suspension appeal must be filed with the Conseil d’État within 15 days after notification of the award decision; an annulment appeal must be filed within 60 days after that notification.
Lots
1 ·Internat Verviers
2 ·HEPL Campus Barbou
3 ·DGEF Internat Seraing
4 ·IPES Seraing – Site de Jemeppe
5 ·Internat Herstal
6 ·Internat CRT
Tender details
- Buyer
- Direction générale des Infrastructures et du Développement Durable
- Country
Belgium
- Procedure
- Open procedure
- Classification
- Construction and civil works · CPV 45310000-3 · CPV 45312100-8 · NUTS BE331 · NUTS BE332 · NUTS BE335
- Notice reference
- 3293cca9-13e3-4aa0-834a-567775493dc4 · 90.01-198
- Lots and estimated durations
- Lot 1, Internat Verviers, 90 days; lot 2, HEPL Campus Barbou, 80 days; lot 3, DGEF Internat Seraing, 80 days; lot 4, IPES Seraing, Site de Jemeppe, 60 days; lot 5, Internat Herstal, 60 days; lot 6, Internat CRT, 50 days.
- Maximum lots
- A bidder may submit for up to six lots and may be awarded up to six lots.
- Functional contact telephone
- +32 42797170
- Review periods
- A suspension appeal must be filed with the Conseil d’État within 15 days after notification of the award decision; an annulment appeal must be filed within 60 days after that notification.
- Scope
- Compliance of fire-detection installations in provincial buildings, mainly boarding schools
- Deadline
- 12 November 2026 at 11:00 CET (UTC+01:00); the 15 October TED publication gave 5 November at 11:00 CET
What to check in the tender documents
- The notice does not provide detailed technical specifications.
- The notice refers to procurement documents for selection criteria but does not state their detailed thresholds.
Original notice
Read the original description
Mise en conformité de de diverses installations de détection incendie
Official source: Belgian BOSA e-Procurement ↗
Notice updates
November 5, 2026 · Version 4
Summary and analysis updated · Tender facts updated · Deadline updated · Source notice details updated · Source references updated · Notice update added
Mise en conformité de de diverses installations de détection incendie
Titre: Mise en conformité de de diverses installations de détection incendie Description: Les travaux consistent en la mise en conformité d’installations de détection incendie dans différents bâtiments provinciaux, principalement des internats. Acheteur: Province de Liège; Direction générale des Infrastructures et du Développement Durable Identifiant interne: 90.01-198 Procédure ouverte; non accélérée. Nature principale: Travaux. CPV principal: 45310000 Travaux d’équipement électrique. Pays d’exécution: Belgique. Base juridique: Directive 2014/24/UE. Nombre maximal de lots pour lesquels un soumissionnaire peut présenter une offre: 6. Nombre maximal de lots pouvant être attribués à un soumissionnaire: 6. Sources des motifs d’exclusion: Document de marché. Lot 1: 90.01-198 - 1 Lot 1 « Internat Verviers »; description: mise en conformité d’installations de détection incendie dans différents bâtiments provinciaux, principalement des internats; identifiant interne 1; CPV 45312100 Travaux d'installation de systèmes avertisseurs d'incendie; zone BE335; durée estimée 90 jours. Lot 2: 90.01-198 - 2 Lot 2 « HEPL Campus Barbou »; même description; identifiant interne 2; CPV 45312100; zone BE332; durée estimée 80 jours. Lot 3: 90.01-198 - 3 Lot 3 « DGEF Internat Seraing »; même description; identifiant interne 3; CPV 45312100; zone BE332; durée estimée 80 jours. Lot 4: 90.01-198 - 4 Lot 4 « IPES Seraing – Site de Jemeppe »; même description; identifiant interne 4; CPV 45312100; zone BE332; durée estimée 60 jours. Lot 5: 90.01-198 - 5 Lot 5 « Internat Herstal »; même description; identifiant interne 5; CPV 45312100; zone BE332; durée estimée 60 jours. Lot 6: 90.01-198 - 6 Lot 6 « Internat CRT »; même description; identifiant interne 6; CPV 45312100; zone BE331; durée estimée 50 jours. Pour chaque lot: participation non réservée; non financé par l’UE; non soumis à l’accord sur les marchés publics; critères de sélection et motifs d’exclusion indiqués dans les documents du marché. Soumission électronique requise à https://www.publicprocurement.be/supplier/enterprises/0/tendering-workspaces/publication-workspace-detail/3293cca9-13e3-4aa0-834a-567775493dc4/general. Langue des offres: français. Catalogue électronique non autorisé. Signature ou cachet électronique avancé ou qualifié requis. Durée de validité des offres: 240 jours. Facturation électronique requise. Commande en ligne non utilisée; paiement électronique utilisé. Aucun accord-cadre; aucun système d’acquisition dynamique. Recours: Conseil d’État; recours en suspension dans les 15 jours suivant notification de la décision d’attribution et recours en annulation dans les 60 jours suivant cette notification. Date limite de réception des offres: 5 novembre 2026 à 11:00 +01:00 dans la publication TED du 15 octobre; le dossier BOSA actuel indique le 12 novembre 2026 à 11:00 CET.
October 23, 2026 · Version 3
Buyer updated · Classification updated · Contract period updated · Deadline information updated · Summary and analysis updated · Tender facts updated · Original notice updated · Deadline updated · Source notice details updated · Notice update added
Mise en conformité de de diverses installations de détection incendie
Titre: Mise en conformité de de diverses installations de détection incendie Description: Les travaux consistent en la mise en conformité d’installations de détection incendie dans différents bâtiments provinciaux, principalement des internats. Acheteur: Province de Liège; Direction générale des Infrastructures et du Développement Durable Identifiant interne: 90.01-198 Procédure ouverte; non accélérée. Nature principale: Travaux. CPV principal: 45310000 Travaux d’équipement électrique. Pays d’exécution: Belgique. Base juridique: Directive 2014/24/UE. Nombre maximal de lots pour lesquels un soumissionnaire peut présenter une offre: 6. Nombre maximal de lots pouvant être attribués à un soumissionnaire: 6. Sources des motifs d’exclusion: Document de marché. Lot 1: 90.01-198 - 1 Lot 1 « Internat Verviers »; description: mise en conformité d’installations de détection incendie dans différents bâtiments provinciaux, principalement des internats; identifiant interne 1; CPV 45312100 Travaux d'installation de systèmes avertisseurs d'incendie; zone BE335; durée estimée 90 jours. Lot 2: 90.01-198 - 2 Lot 2 « HEPL Campus Barbou »; même description; identifiant interne 2; CPV 45312100; zone BE332; durée estimée 80 jours. Lot 3: 90.01-198 - 3 Lot 3 « DGEF Internat Seraing »; même description; identifiant interne 3; CPV 45312100; zone BE332; durée estimée 80 jours. Lot 4: 90.01-198 - 4 Lot 4 « IPES Seraing – Site de Jemeppe »; même description; identifiant interne 4; CPV 45312100; zone BE332; durée estimée 60 jours. Lot 5: 90.01-198 - 5 Lot 5 « Internat Herstal »; même description; identifiant interne 5; CPV 45312100; zone BE332; durée estimée 60 jours. Lot 6: 90.01-198 - 6 Lot 6 « Internat CRT »; même description; identifiant interne 6; CPV 45312100; zone BE331; durée estimée 50 jours. Pour chaque lot: participation non réservée; non financé par l’UE; non soumis à l’accord sur les marchés publics; critères de sélection et motifs d’exclusion indiqués dans les documents du marché. Soumission électronique requise à https://www.publicprocurement.be/supplier/enterprises/0/tendering-workspaces/publication-workspace-detail/3293cca9-13e3-4aa0-834a-567775493dc4/general. Langue des offres: français. Catalogue électronique non autorisé. Signature ou cachet électronique avancé ou qualifié requis. Durée de validité des offres: 240 jours. Facturation électronique requise. Commande en ligne non utilisée; paiement électronique utilisé. Aucun accord-cadre; aucun système d’acquisition dynamique. Recours: Conseil d’État; recours en suspension dans les 15 jours suivant notification de la décision d’attribution et recours en annulation dans les 60 jours suivant cette notification. Date limite de réception des offres: 5 novembre 2026 à 11:00 +01:00 dans la publication TED du 15 octobre; le dossier BOSA actuel indique le 12 novembre 2026 à 11:00 CET.
October 16, 2026 · Version 2
Buyer updated · Classification updated · Deadline information updated · Summary and analysis updated · Tender facts updated · Original notice updated · Deadline updated · Location updated · Source updated · Source notice details updated · Source references updated
Mise en conformité de de diverses installations de détection incendie
Mise en conformité de de diverses installations de détection incendie. Les travaux consistent en la mise en conformité d’installations de détection incendie dans différents bâtiments provinciaux, principalement des internats.
October 14, 2026 · Version 1
Published
Mise en conformité de de diverses installations de détection incendie
Mise en conformité de de diverses installations de détection incendie Les travaux consistent en la mise en conformité d’installations de détection incendie dans différents bâtiments provinciaux, principalement des internats.
https://www.publicprocurement.be/publication-workspaces/3293cca9-13e3-4aa0-834a-567775493dc4/general
Source retrieved: 2026-10-23T23:40:00Z