Overhead line and switchyard maintenance at Agus 7

Outcome

Submissions closed on 14 October 2026. No award has been published yet. Open tenders like this one are listed below.

Place
Agus 7 switchyard and overhead line, Lanao del Norte, Philippines
Closed 14 October 2026 at 09:00 as displayed; time zone not stated.
Time not stated
Contract value
₱412,000
Approved budget: PHP 412,000.
Lots
1 lot
Contract period
12 days
Published
October 9, 2026
PhilGEPS

Overview

National Power Corporation’s Mindanao Generation unit sought overhead tie-line and switchyard maintenance at Agus 7. Work includes correcting conductor sag, cleaning tower and switchyard insulators, retightening connectors and removing HVIC compound; Units 1 and 2 must be shut down. The PHP 412,000 small-value procurement allows 12 days for the work. The notice requires relevant experience, site-inspection and cost documentation, safety qualifications and equipment. It closed on 14 October 2026 at 09:00 as displayed; no time zone is stated.

Information based on the public notice

What the buyer needs

Maintenance of overhead tie-line and switchyard equipment at Agus 7, including a planned shutdown, insulator cleaning or replacement, conductor work and connector maintenance.

  • Prepare materials and equipment on site, correct conductor sag, clean suspension tower posts and insulators, and retighten tower connectors.
  • Clean the porcelain suspension insulators at Agus 7 switchyard, including take-off transformers; remove the existing HVIC compound and tighten connectors if thermal scanning identifies hot spots.
  • Agus 7 Units 1 and 2 must be shut down during the work. The contractor supplies safety harnesses and other transmission-line safety equipment and must provide qualified safety staff, PPE and worker training.
  • Provide at least three years of transmission-line maintenance experience, site-inspection evidence, cost estimate and bill of materials, and HVIC technical data.
  • Complete six days of insulator replacement and six days of semi-annual preventive maintenance within 12 days; provide dated work photographs and an accomplishment report.

Lots

1 ·Overhead tie-line and Agus 7 switchyard maintenance

Tender details

Buyer
National Power Corporation – Mindanao Generation
Country
Philippines
Procedure
Not stated in the notice
Classification
Electrical transmission-line maintenance
Notice reference
13280877
Procurement mode
Negotiated Procurement, Small Value Procurement (Sec. 34)
Approved budget
PHP 412,000
Work period
12 days
Experience requirement
At least 3 years in transmission-line maintenance
Closing time
14 October 2026 at 09:00; time zone not stated

What to check in the tender documents

  • The public notice does not state a time zone for the closing clock. Detailed site and material conditions require the site inspection and tender documents.
Get started with Ziva

Original notice

Read the original description

TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE (A7)

Bid Notice Abstract Invitation to Bid (ITB) Reference Number 13280877 Procuring Entity NATIONAL POWER CORPORATION - MINDANAO GENERATION Title TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE (A7) Area of Delivery Lanao Del Norte Solicitation Number: MG-A7M26-141 Trade Agreement: Implementing Rules and Regulations Procurement Mode: Negotiated Procurement - Small Value Procurement (Sec. 34) Classification: Goods Category: General Engineering Services Approved Budget for the Contract: PHP 412,000.00 Delivery Period: 12 Day/s Client Agency: Contact Person: Rey R. Fausto Materials Management Specialist Maria Cristina, Iligan City Lanao Del Norte Philippines 9200 63-63-2219033 63-63-2213988 reyfausto2013@gmail.com Status Closed Associated Components 1 Bid Supplements 0 Document Request List 2 Date Published 10/10/2026 Last Updated / Time 10/10/2026 00:00 AM Closing Date / Time 14/10/2026 09:00 AM Description TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE SCOPE OF WORKS: ACTIVITY 1: 1. PREPARATION FO MATERIALS AND EQUIPMENT ON SITE. 2.CORRECTION OF SAG CONDUCTOR 3. CLEANING OF SUSPENSION TOWER POSTS AND SUSPENSION INSULATORS, PHOTOGRAPHS SHALL BE TAKEN BEFORE AND AFTER CLEANING 4. RETIGHTHENING OF TOWER CONNECTORS 5. AGUS 7 UNITS 1 AND 2 SHALL BE SHUT DOWN DURING THE ACTIVITIES 6. SAFETY HARNESS AND OTHER EQUIPMENT FOR TRANSMISSION LINE ACTIVITIES SHOULD BE PROVIDED BY THE CONTRACTOR. ACTIVITY 2: 1. PREPARATION OF MATERIALS/RESOURCES ON SITE AND SITE EVALUATION. 2. CLEANING OF PORCELAIN SUSPENSION INSULATORS ON THE AGUS 7 SWYD, INCLUDING TAKE-OFF TRANSFORMERS, REMOVE THE EXISTING HVIC COMPOUND 3. CONDUCT TIGHTHENING OF CONNECTORS IF HOTSPOTS ARE IDENTIFIED DURING THERMAL SCANNING FROM AGUS 7 SWYD UP TO THE LAST TOWER. 4. AGUS 7 UNITS 1 AND 2 SHALL BE SHUT DOWN TO CONDUCT THE ACTIVITIES. 5. SAFETY HARNESS AND OTHER EQUIPMENT FOR TRANSMISSION LINE ACTIVITIES SHOULD BE PROVIDED BY THE CONTRACTOR. TERMS AND CONDITIONS: 1. All line works must be completed within TWELVE (12) DAYS, consisting of SIX (6) DAYS for insulator replacement and days (6) days for semi-annual PMS. The line works shall be conducted during the shutdown of Agus 7 Units 1 and 2. 2. The interested bidder shall comply the following: a. Eligibility Requirements * Mayor's Permit (Valid Product line) * Philgeps (Platinum/Red/Blue) Certificate * Omnibus Sworn Statement * Latest Audited Annual Financial Sworn Statement b. Techincal Requirements * Certificate of Site Inspection/Notarized Affidavit of Site Inspection * Cost Estimate and Bill of Materials * Brochure/Technical Data sheet: HVIC Compound * Must have three years experience in T/L maintenance 3. The winning bidder shall comply with the following: a. Technical Requirements: * BOSH and COSH Training Certificate for the designated Safety Officer/s * Certificate of Mandatory 8-hour OSH Seminar for workers * Job Hazard Analysis/ Risk Assessment * Company OSH Program/Emergency Plan * Lineman should have a certificate of lineman's training certificate from a reputable training center such as TESDA & NGCP. b. Administrative Requirements: * Sworn Statement that his/ her worker conforms with the following requirements: - At least 18 years old above - Has not involved from any liability, case, crime or no record covered by PNP/NBI and its affiliates. * Safety and Environmental Orientation to be conducted by the Plant Safety Officer and PCO; * Briefing and Security Check by the Plant Security Officer. * Complete and appropriate PPE's shall be provided and used. * Coordinate first with the End-User for further details of the Job * All materials as stipulated in the submitted bill of materials shall be delivered first to Agus 6&7 Warehouse for inspection prior to start of any work activities. Excess materials after the completion of work activities shall be returned to the said warehouse; * Photographs shall be taken before, during, and after completion of the project, with corresponding dates. * All solid and hazardous wastes shall be properly segregated and disposed * All scrap/waste/junk materials shall be turned-over to Agus 6&7 HPPC Warehouse for documentation purposes; * NPC shall not be held liable to any untoward incident that may happen during the course of the job. * The company's work permitting and HSE procedures and policies shall be strictly observed during the conduct of work. 4. The following shall be provided the following prior to acceptance: * Accomplishment report - 2 copies for warehouse and QA/Safety 5. All works shall be subject for final inspection by End-User and Plant QA prior to issuance of Certificate of Acceptance and Completion. 6. Other requirements may be determined by the End-User but still subject for TWG Evaluation. 7. The number of manpower & corresponding rates reflected in the cost estimate/ bill materials for the labor are fixed. Interested bidders are instructed to follow the said number of manpower and corresponding rates. Offer of bidders below the minimum daily rate will be declared non-complying. However, daily rates above the NPC minimum rates are acceptable. Other Information SITE INSPECTION AND AFFIDAVIT OF SITE INSPECTION COST ESTIMATE AND BILL OF MATERIALS BROCHURE/TECHNICAL DATA SHEET FOR HVIC COMPOUND MUST HAVE AT LEAST THREE(3) YEARS EXPERIENCE IN TRANSMISSION LINE MAINTENANCE Created by Rey R. Fausto Date Created 09/10/2026

Official source: PhilGEPS ↗

Notice updates

October 16, 2026 · Version 3

Buyer updated · Classification updated · Contract period updated · Deadline information updated · Summary and analysis updated · Tender facts updated · Original notice updated · Location updated · Source notice details updated · Source references updated · Status changed · Notice update added

TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE (A7)

Bid Notice Abstract Invitation to Bid (ITB) Reference Number 13280877 Procuring Entity NATIONAL POWER CORPORATION - MINDANAO GENERATION Title TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE (A7) Area of Delivery Lanao Del Norte Solicitation Number: MG-A7M26-141 Trade Agreement: Implementing Rules and Regulations Procurement Mode: Negotiated Procurement - Small Value Procurement (Sec. 34) Classification: Goods Category: General Engineering Services Approved Budget for the Contract: PHP 412,000.00 Delivery Period: 12 Day/s Client Agency: Contact Person: Rey R. Fausto Materials Management Specialist Maria Cristina, Iligan City Lanao Del Norte Philippines 9200 63-63-2219033 63-63-2213988 reyfausto2013@gmail.com Status Closed Associated Components 1 Bid Supplements 0 Document Request List 2 Date Published 10/10/2026 Last Updated / Time 10/10/2026 00:00 AM Closing Date / Time 14/10/2026 09:00 AM Description TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE SCOPE OF WORKS: ACTIVITY 1: 1. PREPARATION FO MATERIALS AND EQUIPMENT ON SITE. 2.CORRECTION OF SAG CONDUCTOR 3. CLEANING OF SUSPENSION TOWER POSTS AND SUSPENSION INSULATORS, PHOTOGRAPHS SHALL BE TAKEN BEFORE AND AFTER CLEANING 4. RETIGHTHENING OF TOWER CONNECTORS 5. AGUS 7 UNITS 1 AND 2 SHALL BE SHUT DOWN DURING THE ACTIVITIES 6. SAFETY HARNESS AND OTHER EQUIPMENT FOR TRANSMISSION LINE ACTIVITIES SHOULD BE PROVIDED BY THE CONTRACTOR. ACTIVITY 2: 1. PREPARATION OF MATERIALS/RESOURCES ON SITE AND SITE EVALUATION. 2. CLEANING OF PORCELAIN SUSPENSION INSULATORS ON THE AGUS 7 SWYD, INCLUDING TAKE-OFF TRANSFORMERS, REMOVE THE EXISTING HVIC COMPOUND 3. CONDUCT TIGHTHENING OF CONNECTORS IF HOTSPOTS ARE IDENTIFIED DURING THERMAL SCANNING FROM AGUS 7 SWYD UP TO THE LAST TOWER. 4. AGUS 7 UNITS 1 AND 2 SHALL BE SHUT DOWN TO CONDUCT THE ACTIVITIES. 5. SAFETY HARNESS AND OTHER EQUIPMENT FOR TRANSMISSION LINE ACTIVITIES SHOULD BE PROVIDED BY THE CONTRACTOR. TERMS AND CONDITIONS: 1. All line works must be completed within TWELVE (12) DAYS, consisting of SIX (6) DAYS for insulator replacement and days (6) days for semi-annual PMS. The line works shall be conducted during the shutdown of Agus 7 Units 1 and 2. 2. The interested bidder shall comply the following: a. Eligibility Requirements * Mayor's Permit (Valid Product line) * Philgeps (Platinum/Red/Blue) Certificate * Omnibus Sworn Statement * Latest Audited Annual Financial Sworn Statement b. Techincal Requirements * Certificate of Site Inspection/Notarized Affidavit of Site Inspection * Cost Estimate and Bill of Materials * Brochure/Technical Data sheet: HVIC Compound * Must have three years experience in T/L maintenance 3. The winning bidder shall comply with the following: a. Technical Requirements: * BOSH and COSH Training Certificate for the designated Safety Officer/s * Certificate of Mandatory 8-hour OSH Seminar for workers * Job Hazard Analysis/ Risk Assessment * Company OSH Program/Emergency Plan * Lineman should have a certificate of lineman's training certificate from a reputable training center such as TESDA & NGCP. b. Administrative Requirements: * Sworn Statement that his/ her worker conforms with the following requirements: - At least 18 years old above - Has not involved from any liability, case, crime or no record covered by PNP/NBI and its affiliates. * Safety and Environmental Orientation to be conducted by the Plant Safety Officer and PCO; * Briefing and Security Check by the Plant Security Officer. * Complete and appropriate PPE's shall be provided and used. * Coordinate first with the End-User for further details of the Job * All materials as stipulated in the submitted bill of materials shall be delivered first to Agus 6&7 Warehouse for inspection prior to start of any work activities. Excess materials after the completion of work activities shall be returned to the said warehouse; * Photographs shall be taken before, during, and after completion of the project, with corresponding dates. * All solid and hazardous wastes shall be properly segregated and disposed * All scrap/waste/junk materials shall be turned-over to Agus 6&7 HPPC Warehouse for documentation purposes; * NPC shall not be held liable to any untoward incident that may happen during the course of the job. * The company's work permitting and HSE procedures and policies shall be strictly observed during the conduct of work. 4. The following shall be provided the following prior to acceptance: * Accomplishment report - 2 copies for warehouse and QA/Safety 5. All works shall be subject for final inspection by End-User and Plant QA prior to issuance of Certificate of Acceptance and Completion. 6. Other requirements may be determined by the End-User but still subject for TWG Evaluation. 7. The number of manpower & corresponding rates reflected in the cost estimate/ bill materials for the labor are fixed. Interested bidders are instructed to follow the said number of manpower and corresponding rates. Offer of bidders below the minimum daily rate will be declared non-complying. However, daily rates above the NPC minimum rates are acceptable. Other Information SITE INSPECTION AND AFFIDAVIT OF SITE INSPECTION COST ESTIMATE AND BILL OF MATERIALS BROCHURE/TECHNICAL DATA SHEET FOR HVIC COMPOUND MUST HAVE AT LEAST THREE(3) YEARS EXPERIENCE IN TRANSMISSION LINE MAINTENANCE Created by Rey R. Fausto Date Created 09/10/2026

October 12, 2026 · Version 2

Summary and analysis updated

TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE (A7)

Bid Notice Abstract Invitation to Bid (ITB) Reference Number 13280877 Procuring Entity NATIONAL POWER CORPORATION - MINDANAO GENERATION Title TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE (A7) Area of Delivery Lanao Del Norte Printable Version Solicitation Number: MG-A7M26-141 Trade Agreement: Implementing Rules and Regulations Procurement Mode: Negotiated Procurement - Small Value Procurement (Sec. 34) Classification: Goods Category: General Engineering Services Approved Budget for the Contract: PHP 412,000.00 Delivery Period: 12 Day/s Client Agency: Contact Person: Rey R. Fausto Materials Management Specialist Maria Cristina, Iligan City Lanao Del Norte Philippines 9200 63-63-2219033 63-63-2213988 reyfausto2013@gmail.com Status Active Associated Components Order Bid Supplements 0 Document Request List 0 Date Published 10/10/2026 Last Updated / Time 10/10/2026 12:00 AM Closing Date / Time 14/10/2026 9:00 AM Description TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE SCOPE OF WORKS: ACTIVITY 1: 1. PREPARATION FO MATERIALS AND EQUIPMENT ON SITE. 2.CORRECTION OF SAG CONDUCTOR 3. CLEANING OF SUSPENSION TOWER POSTS AND SUSPENSION INSULATORS, PHOTOGRAPHS SHALL BE TAKEN BEFORE AND AFTER CLEANING 4. RETIGHTHENING OF TOWER CONNECTORS 5. AGUS 7 UNITS 1 AND 2 SHALL BE SHUT DOWN DURING THE ACTIVITIES 6. SAFETY HARNESS AND OTHER EQUIPMENT FOR TRANSMISSION LINE ACTIVITIES SHOULD BE PROVIDED BY THE CONTRACTOR. ACTIVITY 2: 1. PREPARATION OF MATERIALS/RESOURCES ON SITE AND SITE EVALUATION. 2. CLEANING OF PORCELAIN SUSPENSION INSULATORS ON THE AGUS 7 SWYD, INCLUDING TAKE-OFF TRANSFORMERS, REMOVE THE EXISTING HVIC COMPOUND 3. CONDUCT TIGHTHENING OF CONNECTORS IF HOTSPOTS ARE IDENTIFIED DURING THERMAL SCANNING FROM AGUS 7 SWYD UP TO THE LAST TOWER. 4. AGUS 7 UNITS 1 AND 2 SHALL BE SHUT DOWN TO CONDUCT THE ACTIVITIES. 5. SAFETY HARNESS AND OTHER EQUIPMENT FOR TRANSMISSION LINE ACTIVITIES SHOULD BE PROVIDED BY THE CONTRACTOR. TERMS AND CONDITIONS: 1. All line works must be completed within TWELVE (12) DAYS, consisting of SIX (6) DAYS for insulator replacement and days (6) days for semi-annual PMS. The line works shall be conducted during the shutdown of Agus 7 Units 1 and 2. 2. The interested bidder shall comply the following: a. Eligibility Requirements * Mayor's Permit (Valid Product line) * Philgeps (Platinum/Red/Blue) Certificate * Omnibus Sworn Statement * Latest Audited Annual Financial Sworn Statement b. Techincal Requirements * Certificate of Site Inspection/Notarized Affidavit of Site Inspection * Cost Estimate and Bill of Materials * Brochure/Technical Data sheet: HVIC Compound * Must have three years experience in T/L maintenance 3. The winning bidder shall comply with the following: a. Technical Requirements: * BOSH and COSH Training Certificate for the designated Safety Officer/s * Certificate of Mandatory 8-hour OSH Seminar for workers * Job Hazard Analysis/ Risk Assessment * Company OSH Program/Emergency Plan * Lineman should have a certificate of lineman's training certificate from a reputable training center such as TESDA & NGCP. b. Administrative Requirements: * Sworn Statement that his/ her worker conforms with the following requirements: - At least 18 years old above - Has not involved from any liability, case, crime or no record covered by PNP/NBI and its affiliates. * Safety and Environmental Orientation to be conducted by the Plant Safety Officer and PCO; * Briefing and Security Check by the Plant Security Officer. * Complete and appropriate PPE's shall be provided and used. * Coordinate first with the End-User for further details of the Job * All materials as stipulated in the submitted bill of materials shall be delivered first to Agus 6&7 Warehouse for inspection prior to start of any work activities. Excess materials after the completion of work activities shall be returned to the said warehouse; * Photographs shall be taken before, during, and after completion of the project, with corresponding dates. * All solid and hazardous wastes shall be properly segregated and disposed * All scrap/waste/junk materials shall be turned-over to Agus 6&7 HPPC Warehouse for documentation purposes; * NPC shall not be held liable to any untoward incident that may happen during the course of the job. * The company's work permitting and HSE procedures and policies shall be strictly observed during the conduct of work. 4. The following shall be provided the following prior to acceptance: * Accomplishment report - 2 copies for warehouse and QA/Safety 5. All works shall be subject for final inspection by End-User and Plant QA prior to issuance of Certificate of Acceptance and Completion. 6. Other requirements may be determined by the End-User but still subject for TWG Evaluation. 7. The number of manpower & corresponding rates reflected in the cost estimate/ bill materials for the labor are fixed. Interested bidders are instructed to follow the said number of manpower and corresponding rates. Offer of bidders below the minimum daily rate will be declared non-complying. However, daily rates above the NPC minimum rates are acceptable. Other Information SITE INSPECTION AND AFFIDAVIT OF SITE INSPECTION COST ESTIMATE AND BILL OF MATERIALS BROCHURE/TECHNICAL DATA SHEET FOR HVIC COMPOUND MUST HAVE AT LEAST THREE(3) YEARS EXPERIENCE IN TRANSMISSION LINE MAINTENANCE

October 12, 2026 · Version 1

Published

TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE (A7)

Bid Notice Abstract Invitation to Bid (ITB) Reference Number 13280877 Procuring Entity NATIONAL POWER CORPORATION - MINDANAO GENERATION Title TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE (A7) Area of Delivery Lanao Del Norte Printable Version Solicitation Number: MG-A7M26-141 Trade Agreement: Implementing Rules and Regulations Procurement Mode: Negotiated Procurement - Small Value Procurement (Sec. 34) Classification: Goods Category: General Engineering Services Approved Budget for the Contract: PHP 412,000.00 Delivery Period: 12 Day/s Client Agency: Contact Person: Rey R. Fausto Materials Management Specialist Maria Cristina, Iligan City Lanao Del Norte Philippines 9200 63-63-2219033 63-63-2213988 reyfausto2013@gmail.com Status Active Associated Components Order Bid Supplements 0 Document Request List 0 Date Published 10/10/2026 Last Updated / Time 10/10/2026 12:00 AM Closing Date / Time 14/10/2026 9:00 AM Description TIE LINE & SWITCHYARD OVERHEAD MAINTENANCE SCOPE OF WORKS: ACTIVITY 1: 1. PREPARATION FO MATERIALS AND EQUIPMENT ON SITE. 2.CORRECTION OF SAG CONDUCTOR 3. CLEANING OF SUSPENSION TOWER POSTS AND SUSPENSION INSULATORS, PHOTOGRAPHS SHALL BE TAKEN BEFORE AND AFTER CLEANING 4. RETIGHTHENING OF TOWER CONNECTORS 5. AGUS 7 UNITS 1 AND 2 SHALL BE SHUT DOWN DURING THE ACTIVITIES 6. SAFETY HARNESS AND OTHER EQUIPMENT FOR TRANSMISSION LINE ACTIVITIES SHOULD BE PROVIDED BY THE CONTRACTOR. ACTIVITY 2: 1. PREPARATION OF MATERIALS/RESOURCES ON SITE AND SITE EVALUATION. 2. CLEANING OF PORCELAIN SUSPENSION INSULATORS ON THE AGUS 7 SWYD, INCLUDING TAKE-OFF TRANSFORMERS, REMOVE THE EXISTING HVIC COMPOUND 3. CONDUCT TIGHTHENING OF CONNECTORS IF HOTSPOTS ARE IDENTIFIED DURING THERMAL SCANNING FROM AGUS 7 SWYD UP TO THE LAST TOWER. 4. AGUS 7 UNITS 1 AND 2 SHALL BE SHUT DOWN TO CONDUCT THE ACTIVITIES. 5. SAFETY HARNESS AND OTHER EQUIPMENT FOR TRANSMISSION LINE ACTIVITIES SHOULD BE PROVIDED BY THE CONTRACTOR. TERMS AND CONDITIONS: 1. All line works must be completed within TWELVE (12) DAYS, consisting of SIX (6) DAYS for insulator replacement and days (6) days for semi-annual PMS. The line works shall be conducted during the shutdown of Agus 7 Units 1 and 2. 2. The interested bidder shall comply the following: a. Eligibility Requirements * Mayor's Permit (Valid Product line) * Philgeps (Platinum/Red/Blue) Certificate * Omnibus Sworn Statement * Latest Audited Annual Financial Sworn Statement b. Techincal Requirements * Certificate of Site Inspection/Notarized Affidavit of Site Inspection * Cost Estimate and Bill of Materials * Brochure/Technical Data sheet: HVIC Compound * Must have three years experience in T/L maintenance 3. The winning bidder shall comply with the following: a. Technical Requirements: * BOSH and COSH Training Certificate for the designated Safety Officer/s * Certificate of Mandatory 8-hour OSH Seminar for workers * Job Hazard Analysis/ Risk Assessment * Company OSH Program/Emergency Plan * Lineman should have a certificate of lineman's training certificate from a reputable training center such as TESDA & NGCP. b. Administrative Requirements: * Sworn Statement that his/ her worker conforms with the following requirements: - At least 18 years old above - Has not involved from any liability, case, crime or no record covered by PNP/NBI and its affiliates. * Safety and Environmental Orientation to be conducted by the Plant Safety Officer and PCO; * Briefing and Security Check by the Plant Security Officer. * Complete and appropriate PPE's shall be provided and used. * Coordinate first with the End-User for further details of the Job * All materials as stipulated in the submitted bill of materials shall be delivered first to Agus 6&7 Warehouse for inspection prior to start of any work activities. Excess materials after the completion of work activities shall be returned to the said warehouse; * Photographs shall be taken before, during, and after completion of the project, with corresponding dates. * All solid and hazardous wastes shall be properly segregated and disposed * All scrap/waste/junk materials shall be turned-over to Agus 6&7 HPPC Warehouse for documentation purposes; * NPC shall not be held liable to any untoward incident that may happen during the course of the job. * The company's work permitting and HSE procedures and policies shall be strictly observed during the conduct of work. 4. The following shall be provided the following prior to acceptance: * Accomplishment report - 2 copies for warehouse and QA/Safety 5. All works shall be subject for final inspection by End-User and Plant QA prior to issuance of Certificate of Acceptance and Completion. 6. Other requirements may be determined by the End-User but still subject for TWG Evaluation. 7. The number of manpower & corresponding rates reflected in the cost estimate/ bill materials for the labor are fixed. Interested bidders are instructed to follow the said number of manpower and corresponding rates. Offer of bidders below the minimum daily rate will be declared non-complying. However, daily rates above the NPC minimum rates are acceptable. Other Information SITE INSPECTION AND AFFIDAVIT OF SITE INSPECTION COST ESTIMATE AND BILL OF MATERIALS BROCHURE/TECHNICAL DATA SHEET FOR HVIC COMPOUND MUST HAVE AT LEAST THREE(3) YEARS EXPERIENCE IN TRANSMISSION LINE MAINTENANCE