Track renewal between Martigny and Martigny-Bourg and on the Simplon Bridge

Outcome

Submissions closed on 23 November 2026. No award has been published yet. Open tenders like this one are listed below.

Place
Martigny, canton of Valais
2026-11-23 at 10:00:00 (UTC+01:00)
09:00 AM · UTC
Contract value
Not stated in the notice
Contract period
Execution is planned from 28 June to 3 August 2027.
Published
September 21, 2026
SIMAP

Overview

TMR tenders renewal of the standard-gauge track superstructure over 1,694 m between Martigny and Martigny-Bourg and 270 m on the Simplon Bridge. French-language offers must be signed, complete and delivered in paper form with the required electronic files by 23 November 2026 at 10:00 (UTC+01:00); the postmark does not count. Work is planned from 28 June to 3 August 2027. Partial offers are not allowed; variants, consortia and subcontractors are allowed, with subcontracting capped at 30%.

Information based on the public notice

What the buyer needs

Renew the track superstructure on 1,694 m between Martigny and Martigny-Bourg and on 270 m of the Simplon Bridge.

  • Offers must be in French, complete, signed and submitted as one paper copy with the required digital description and full PDF on USB. No partial offers are allowed. Variants are allowed only with the base offer and must meet the technical conditions. Consortia and subcontractors are allowed; subcontracting is capped at 30%. No site visit is planned.

Tender details

Buyer
TMR – Transports de Martigny & Régions SA, Infrastructure
Country
Switzerland
Procedure
open
Classification
Construction and civil works · CPV 45000000
Notice reference
44594 · 44594-01
Scope
Renew 1,694 m of track between Martigny and Martigny-Bourg and 270 m on the Simplon Bridge.
Offer deadline
23 November 2026, 10:00 (UTC+01:00)
Execution period
28 June–3 August 2027
Submission
One signed paper copy plus required electronic files; postmark does not count

What to check in the tender documents

  • The notice does not state an estimated contract value or an award amount.
Get started with Ziva

Original notice

Read the original description

Réfection superstructure voie courante Martigny – Martigny Bourg [Km1+059 au Km2+806] sur 1694m Pont du Simplon [Km0+599 au Km0+870] sur 270m

Title Réfection superstructure voie courante Martigny – Martigny Bourg [Km1+059 au Km2+806] sur 1694m Pont du Simplon [Km0+599 au Km0+870] sur 270m Description Ligne à voie normale entre les gares de Martigny et Martigny Bourg : « VN 22.40 Réfection de voie sur le Pont du Simplon (270ml) & VN30.05 Réfection de voie entre Martigny Martigny Bourg (1694ml). Publication date 2026-09-22 Offer deadline 2026-11-23T10:00:00+01:00 Questions deadline 2026-10-12 Place of performance Ligne à voie normale entre les gares de Martigny et Martigny Bourg. CPV classification 45000000 — Travaux de construction Contract/execution period 2027-06-28–2027-08-03 Offer languages fr Variants yes Partial offers no Consortium bids yes Subcontractors yes

Official source: SIMAP ↗

Notice updates

October 23, 2026 · Version 2

Buyer updated · Classification updated · Contract period updated · Summary and analysis updated · Tender facts updated · Deadline updated · Source notice details updated · Source references updated

Réfection superstructure voie courante Martigny – Martigny Bourg [Km1+059 au Km2+806] sur 1694m Pont du Simplon [Km0+599 au Km0+870] sur 270m

Title Réfection superstructure voie courante Martigny – Martigny Bourg [Km1+059 au Km2+806] sur 1694m Pont du Simplon [Km0+599 au Km0+870] sur 270m Description Ligne à voie normale entre les gares de Martigny et Martigny Bourg : « VN 22.40 Réfection de voie sur le Pont du Simplon (270ml) & VN30.05 Réfection de voie entre Martigny Martigny Bourg (1694ml). Publication date 2026-09-22 Offer deadline 2026-11-23T10:00:00+01:00 Questions deadline 2026-10-12 Place of performance Ligne à voie normale entre les gares de Martigny et Martigny Bourg. CPV classification 45000000 — Travaux de construction Contract/execution period 2027-06-28–2027-08-03 Offer languages fr Variants yes Partial offers no Consortium bids yes Subcontractors yes

October 11, 2026 · Version 1

Published

Réfection superstructure voie courante Martigny – Martigny Bourg [Km1+059 au Km2+806] sur 1694m Pont du Simplon [Km0+599 au Km0+870] sur 270m

Title Réfection superstructure voie courante Martigny – Martigny Bourg [Km1+059 au Km2+806] sur 1694m Pont du Simplon [Km0+599 au Km0+870] sur 270m Description Ligne à voie normale entre les gares de Martigny et Martigny Bourg : « VN 22.40 Réfection de voie sur le Pont du Simplon (270ml) & VN30.05 Réfection de voie entre Martigny Martigny Bourg (1694ml). Publication date 2026-09-22 Offer deadline 2026-11-23T10:00:00+01:00 Questions deadline 2026-10-12 Place of performance Ligne à voie normale entre les gares de Martigny et Martigny Bourg. CPV classification 45000000 — Travaux de construction Contract/execution period 2027-06-28–2027-08-03 Offer languages fr Variants yes Partial offers no Consortium bids yes Subcontractors yes