Health and safety coordination for the district heating and boiler house renewal in Aachen

Place
Linterstraße 71, 52076 Aachen, Germany (Theodor-Körner-Kaserne)
Submission deadline (German local time, UTC+01:00)
09:00 AM · UTC
Contract value
Not stated in the notice
Lots
1 lot
Contract period
Planned period from 15 December 2026 to 31 January 2031, covering the construction of the district heating network (from December 2026) and the boiler house (from July 2027).
Published
November 2, 2026
TED (Tenders Electronic Daily), official eForms contract notice 761789-2026, read from the official notice XML

Overview

Bau- und Liegenschaftbetrieb NRW Bundesbau is tendering health and safety coordination (SiGeKo) for the renewal of the district heating network and the boiler house at the Theodor-Körner-Kaserne in Aachen. The works are phased: the heating network starts in December 2026, the boiler house in July 2027, and the overall construction period runs to January 2031, about four years. The contract covers service levels 1 and 2 of the SiGeKo services, with the concrete service components set out in the specific service obligations that the notice refers to. This open procedure requires electronic submission through the BLB NRW evergabe portal. Bidders must provide a trade register extract, a company profile, liability insurance confirmation, and declarations on exclusion grounds and subcontracting. The notice does not state an estimated value or award criteria.

Information based on the public notice

What the buyer needs

Open procedure for health and safety coordination (SiGeKo) during the renewal of the district heating network and boiler house at the Theodor-Körner-Kaserne in Aachen. The notice describes phased construction: the district heating network from December 2026 and the boiler house from July 2027, with an overall construction period of about 212 weeks. The services cover service levels 1 and 2 of the SiGeKo services.

  • Trade register extract or register of professions as a copy with the offer, confirming the current status of registration.
  • A short company profile (generally not more than two A4 pages) covering the main activities and organisation.
  • Declaration that all trade-law requirements for performing the service are met.
  • Current professional and business liability insurance, with the insurer's declaration of cover. The notice prints the minimum cover amounts as placeholders.
  • Declarations on exclusion grounds under section 124 GWB and the statutes the notice lists, including the Posted Workers Act, the Residence Act, the Minimum Wage Act and the Undeclared Work Act.
  • Subcontractor and capacity-borrowing declarations (EU forms 533a, 533b, 534a and 534b) where relevant.
  • Newcomers may rely on a shorter company history, and the experience of the persons who will perform the contract may replace company references.

Lots

LOT-0001 ·BLB NRW BB (Bund)/Aachen/KöKa/Neubau ZVA/SiGeKo

Tender details

Buyer
Bau- und Liegenschaftbetrieb NRW Bundesbau
Country
Germany
Procedure
Open procedure, electronic submission via evergabe.blb.nrw.de
Classification
Consulting and business services · CPV 71317200
Notice reference
761789-2026
Submission deadline
3 December 2026, 10:00 (German local time, UTC+01:00)
Questions deadline
20 November 2026, 23:59:59 (UTC+01:00)
Scope
Health and safety coordinator services (SiGeKo), service levels 1 and 2
Planned period
15 December 2026 to 31 January 2031
Contact mailbox
BLBVergabe@blb.nrw.de

What to check in the tender documents

  • The notice does not state an estimated contract value.
  • The notice does not state award criteria.
  • The minimum insurance cover is printed as placeholder amounts ("xx Mio. Euro"), so no cover amount is stated.
  • The tender documents on evergabe.blb.nrw.de are out of scope and were not read; this record uses the official notice only.
Get started with Ziva

Original notice

Read the original description

BLB NRW BB (Bund)/Aachen/KöKa/Neubau ZVA/SiGeKo

In der Theodor-Körner-Kaserne in Aachen wird das Nahwärmenetz und die Heizzentrale der Liegenschaft erneuert. Es gibt eine bauzeitliche Trennung zwischen der Erneuerung des Nahwärmenetzes und der Heizzentrale, da die Liegenschaft während der Gesamtbaumaßnahme weiterhin über das alte Netz und die alte Heizzentrale beheizt werden muss. Der Baubeginn des Nahwärmenetzes ist für Dezember 2026 vorgesehen. Der Baubeginn der Heizzentrale ist für Juli 2027 vorgesehen und soll voraussichtlich bis Januar 2031 andauern. Die gesamte Bauzeit des Projekts beträgt daher etwa 4 Jahre (212 Wochen). Gegenstand der Ausschreibung ist das Leistungsbild des SiGeKo (Sicherheits- und Gesundheitsschutzkoordinator). Gegenstand der Ausschreibung ist das Leistungsbild des SiGeKo (Sicherheits- und Gesundheitsschutzkoordinator). Der Auftragsumfang umfasst die Leistungsstufen 1 und 2 der SiGeKo Leistungen. Die konkreten Leistungsbestandteile sind den spezifischen Leistungspflichten zu entnehmen.