Electricity supply for CERN, 2027–2033
CERN forthcoming tendering procedures
Overview
CERN plans two electricity-supply contracts through the French transmission network: one for 2027–2028 during accelerator shutdown and another for 2029–2031, with two optional years. The stated volumes are 0.5 TWh per year during shutdown and 1.5 TWh per year when the accelerator complex is running. The supplier should have experience with comparable long-term energy contracts for large industrial sites. Estimated costs exceed CHF 10 million. An invitation to tender was estimated for January 2027.
Information based on the public notice
Ask about this tender
What the buyer needs
Supply of electricity via the French transmission network to CERN’s accelerators, experiments, technical infrastructure and facilities, under two contract periods.
- Experience in long-term electricity supply contracts for large industrial plants with comparable quality and quantity requirements.
Tender details
- Buyer
- CERN
- Country
Switzerland
- Procedure
- Invitation to Tender
- Classification
- Energy and utilities · CERN-PROCUREMENT-CODE 14020100
- Notice reference
- MS-5116/ATS
- Scope
- CERN plans two electricity-supply contracts through the French transmission network: one for 2027–2028 during accelerator shutdown and another for 2029–2031, with two optional years. The stated volumes are 0.5 TWh per year during shutdown and 1.5 TWh per year when the accelerator complex is running. The supplier should have experience with comparable long-term energy contracts for large industrial sites. Estimated costs exceed CHF 10 million. An invitation to tender was estimated for January 2027.
- Key fact
- Electricity supply via the French transmission network for CERN accelerators, experiments, technical infrastructure and facilities. · Comparable long-term electricity supply to large industrial sites. · Annual volume: 0.5 TWh during shutdown and 1.5 TWh when the accelerator complex runs. · Two contracts: 2027–2028 and 2029–2031, with two optional years; estimated cost above CHF 10 million.
What to check in the tender documents
- No submission deadline, evaluation criteria or detailed contractual terms are stated in the available notice text.
Original notice
Read the original description
Framework Market Survey concerning the electricity supply for CERN: one contract to cover 2027-2028 and a second contract to cover 2029-2031 (optional 2032-33)
Official source: CERN forthcoming tendering procedures ↗
https://forthcoming-ms.app.cern.ch/?id=MS-5116/ATS/#!/
Source retrieved: 2026-10-17T22:31:02Z