Overview

The Ministry of Works, Housing and Water Resources of Ghana invites eligible contractors to bid for reconstruction of the Abbosey Okai Bridge under the Greater Accra Resilient and Integrated Development Project. The notice describes demolition and replacement with a 47.5-metre single-span bridge, new abutments and pile foundations, approach-road reinstatement, jet-grouting, drainage and traffic management. The contract is planned for nine months. Sealed bids are due 17 November 2026 at 10:00 GMT; electronic bidding is not permitted. Bid security is GHS 1,500,000 and an SEA/SH declaration is required.

Information based on the public notice

What the buyer needs

  • Bids must be sealed and submitted by the deadline; electronic bidding is not permitted. Eligibility is governed by the cited World Bank Procurement Regulations.

Tender details

Buyer
Ministry of Works, Housing and Water Resources
Country
Ghana
Procedure
Request for Bids
Classification
Bridge reconstruction works · WORLD_BANK P164330
Notice reference
OP00473668
Contract scope
Reconstruction of Abbosey Okai Bridge
Execution period
9 months
Bid deadline
17 November 2026, 10:00 GMT
Bid security
GHS 1,500,000
Submission requirements
SEA/SH declaration required; electronic bidding not permitted

What to check in the tender documents

  • No estimated contract value is stated. Bidding documents are described as available from the buyer but were not retrieved.
Get started with Ziva

Original notice

Read the original description

Reconstruction of Abbosey Okai Bridge

SPECIFIC PROCUREMENT NOTICE Invitation for Bids (IFB) Project: Greater Accra Resilient and Integrated Development Project Contract title: Reconstruction of Abbosey Okai Bridge Country: Ghana Credit No.: IDA-64100 RFB No: GH-MWH-219663-CW-RFB Issued on: October 14, 2026 The Government of Ghana has received financing from the World Bank toward the cost of the Greater Accra Resilient and Integrated Development Project and intends to apply part of the proceeds toward payments under the contract for Reconstruction of Abbosey Okai bridge . For this contract, the Borrower shall process the payments using the Direct Payment disbursement method, as defined in the World Bank’s Disbursement Guidelines for Investment Project Financing. The Ministry of Works, Housing and Water Resources invites sealed bids from eligible contractors for the Reconstruction of the Abbosey Okai Bridge . The project involves the demolition of the existing concrete arch bridge, approximately 47.5m long and 15.0m wide, which currently spans over the Odaw River. The existing structure is in a deteriorated condition, with visible concrete cover detachment, oxidized reinforcing steel bars, and vertical misalignment of the paving surface. The new bridge structure to be constructed consists of a 47.5m single-span deck , made of COR-TEN steel beams and reinforced concrete slabs , supported by reinforced concrete abutments with pile foundations . The bridge will have sixteen HL 1100 M (S460) steel beams, spaced at 0.95m, with a reinforced concrete slab (C40/50) placed on top. The abutments will be 6.50m high, 16.20m long, and 2.20m thick, with 24 reinforced concrete piles (diameter 1.20m, depth 25m) ensuring structural stability. The project also includes the elevation and reinstatement of the approach roads and surrounding areas affected by the bridge replacement. The existing vertical clearance of the bridge will be increased, preventing frequent submergence during floods. The bridge deck width will be maintained at 15m to guarantee continuity with the existing roadway. Additional works involve jet grouting consolidation at the abutments, with 130 jet grouting columns per abutment, extending 15m below the foundation slab, to mitigate soil liquefaction risks. Drainage modifications include DIA150mm pipes discharging rainwater directly into the river and covered side drains connecting to the existing drainage system. Traffic management and road diversions during construction will be a very critical aspect of works, considering the highly congested area where the new bridge has to be located. The contract shall be executed within 9 months . Bidding will be conducted through National Competitive Procurement using Request for Bids (RFB) as specified in the World Bank’s “Procurement Regulations for IPF Borrowers” 7th Edition September, 2025 (Procurement Regulations), and is open to all eligible Bidders as defined in the Procurement Regulations. Interested eligible Bidders may obtain further information from the Ministry of Works and Housing, Mr. Daniel Kusi, email: dkojokusi@gmail.com and inspect the Bidding document during office hours (9:00 Hrs GMT-16:00 Hrs GMT) at the address (2) given below. The Bidding document in English may be purchased by interested eligible Bidders upon the submission of a written application to the address (1) below and upon payment of a nonrefundable fee of GH¢ 2,000.00 (Two Thousand Ghana Cedis) or in a freely convertible currency . The method of payment will be cash. The document will be sent by Courier at an additional cost of GHC 100.00 . Bids must be delivered to the address (3) below on or before 10:00 HRS GMT on November 17, 2026. Electronic Bidding will not be permitted. Late Bids will be rejected. Bids will be publicly opened in the presence of the Bidders’ designated representatives and anyone who chooses to attend at the address (3) below on on November 17, 2026 at 10:00 HRS GMT . All bids must be accompanied by a bid security of GH¢ 1,500,000.00 from a reputable bank. All Bids must be accompanied by a Sexual Exploitation and Abuse (SEA) and/or Sexual Harassment (SH) Declaration. Attention is drawn to the Procurement Regulations requiring the Borrower to disclose information on the successful bidder’s beneficial ownership, as part of the Contract Award Notice, using the Beneficial Ownership Disclosure Form as included in the bidding document. The addresses referred to above are: Address (1): inspection and purchase: Name of Office : Ministry of Works, Housing and Water Resources Street Address : Ministries, Accra Floor/Room Number : Ground Floor, Procurement Unit, Room G09, City : Accra Region : Greater Accra Country : Ghana Email Address : dkojokusi@gmail.com Attention : Senior Procurement Manager, GARID Address (2): For Clarifications: Name of Office : Ministry of Works, Housing and Water Resources Street Address : Ministries, Accra. P.O. Box M43, Accra. Floor/Room Number : 2nd Floor / R.202 City : Accra Region : Greater Accra Country : Ghana Email Address : tenders@garid-accra.com Address (3): For bid submission and opening: Name of Office : Ministry of Works, Housing and Water Resources Street Address : No. 3 Valco Drive, Ministries, Accra Floor/Room Number : 3rd Floor / R.308 Conference Room City : Accra Region : Greater Accra Country : Ghana

Official source: World Bank Procurement ↗