I/45 Nové Heřminovy-Zátor, Stage I
Estimated procurement value reported by TED; no award amount is reported.
Tenders Electronic Daily (TED)
Overview
The Czech Road and Motorway Directorate and Povodí Odry are procuring the first stage of relocating about 5 km of the I/45 road between Nové Heřminovy and Zátor. The official notice explains that the realignment is needed because the existing road will lie within the planned Nové Heřminovy reservoir flood area. The works include junctions and roundabouts, bridges, retaining and cut-slope walls, noise barriers near homes, and changes to affected lower-class roads. TED reports an estimated value of CZK 2,433,000,000 and a 47-month period. Award criteria are construction bid price excluding VAT and warranty duration. The deadline is 10 November 2026 at 23:00 UTC; bid validity is 10 months.
Information based on the public notice
Ask about this tender
What the buyer needs
Construction of the first-stage I/45 realignment between Nové Heřminovy and Zátor, with connected junction, bridge, retaining-wall, noise-protection and road-connection works.
Tender details
- Buyer
- Ředitelství silnic a dálnic s. p.
- Country
Czechia
- Procedure
- open
- Classification
- CPV 45233120
- Notice reference
- 687514-2026
- Contracting authorities
- Ředitelství silnic a dálnic s. p.; Povodí Odry, státní podnik
- Estimated value
- CZK 2,433,000,000
- Road section
- About 5.0 km; category S 11.5/90
- Contract period
- 47 months
- Award criteria
- Construction bid price without VAT; warranty duration in months
- Tender validity
- 10 months
- Submission deadline
- 10 November 2026, 23:00 UTC
What to check in the tender documents
- The retrieved notice does not provide a detailed work schedule or award outcome.
Original notice
Read the original description
I/45 Nové Heřminovy - Zátor, I. etapa
Official source: Tenders Electronic Daily (TED) ↗
https://ted.europa.eu/en/notice/-/detail/687514-2026
Source retrieved: 2026-10-13T11:54:01.680319Z