S18 Bodensee Schnellstraße electrical and tunnel ventilation planning

Outcome

Submissions closed on 22 October 2026. No award has been published yet. Open tenders like this one are listed below.

Place
Vorarlberg, Austria
22 October 2026, 15:00 CEST
01:00 PM · UTC
Contract value
Not stated in the notice
Lots
1 lot
Contract period
2026-11-16 to 2030-12-31
Published
October 13, 2026
ted-europa

Overview

ASFINAG is seeking specialist engineering planning for electrical systems, BuS (operational and safety equipment) and tunnel ventilation for the S18 Bodensee Schnellstraße. The stated objective is to complete the submission design phase and obtain approval of the preliminary tunnel design under §7 STSG. The contract period is planned from 16 November 2026 through 31 December 2030. This is an open procedure with one lot and a 22 October 2026, 15:00 CEST deadline. The notice says quality is assessed according to the procurement documents; it gives no estimated value.

Information based on the public notice

What the buyer needs

Specialist planning for electrical engineering, operational and safety equipment, and tunnel ventilation for the S18 project, through approved preliminary tunnel design.

Lots

LOT-0001 ·S18 Bodensee Schnellstraße electrical, BuS and tunnel ventilation planning

Tender details

Buyer
Autobahnen- und Schnellstraßen-Finanzierungs-Aktiengesellschaft
Country
Austria
Procedure
Open procedure; one lot
Classification
Engineering services · CPV 71334000
Notice reference
710499-2026
Deadline
22 October 2026, 15:00 CEST
Contract period
16 November 2026 to 31 December 2030
Objective
Approved preliminary tunnel design at end of submission design phase

What to check in the tender documents

  • The notice refers to tender documents for quality assessment; those supporting documents were not read. No estimated value is stated.
Get started with Ziva

Original notice

Read the original description

S18 Bodensee Schnellstraße - Planung EM inkl. BuS und Tunnellüftung

ba471b07-c861-47a2-a61c-a16db3fbe5b3-01 cor-pub 16 ORG-0002 ASFINAG Bau Management GmbH Schnirchgasse 17 Wien 1030 AT130 AUT 255631d ATU61282533 ASFINAG Bau Management GmbH ORG-0001 Autobahnen- und Schnellstraßen-Finanzierungs-Aktiengesellschaft Schnirchgasse 17 Wien 1030 AT130 AUT FN92191a ATU43143200 Autobahnen- und Schnellstraßen-Finanzierungs-Aktiengesellschaft +43 800 40012400 info@asfinag.at ORG-0003 Bundesverwaltungsgericht Wien 1030 AT130 AUT 9110008059823 Bundesverwaltungsgericht +43 171123-8891541 einlaufstelle@bvwg.gv.at 00710499-2026 199/2026 2026-10-14+02:00 2.3 eforms-sdk-1.14 27e73733-bb60-4682-8b72-f3af57a2f58b 43b80a5d-aa0d-45c5-ab95-d8d8c7084415 2026-10-12+02:00 16:02:17+02:00 01 32014L0024 cn-standard DEU body-pl econ-aff ORG-0001 epo-procurement-document open false 160657 S18 Bodensee Schnellstraße - Planung EM inkl. BuS und Tunnellüftung Leistungsumfang gegenständlicher Dienstleistung ist die Leistung "Fachplaner EM inkl. BuS und Tunnellüftung" für das Projekt S 18 Bodensee Schnellstraße. Leistungsziel ist der Abschluss der Leistungen mit der Phase Einreichprojekt mit Genehmigung des Tunnel-Vorentwurf (§7 STSG). services 71334000 ATZZZ AUT LOT-0001 not-allowed no-eu-funds false epo-procurement-document none no required not-allowed quality Bewertet wird die angebotene Qualität gemäß Unterlagen. ORG-0002 ORG-0001 www.provia.at 3 gem. den entsprechenden gesetzlichen Vorgaben ORG-0003 ORG-0003 DEU true true required true 2026-10-22+02:00 15:00:00+02:00 false none none 160657 S18 Bodensee Schnellstraße - Planung EM inkl. BuS und Tunnellüftung Leistungsumfang gegenständlicher Dienstleistung ist die Leistung "Fachplaner EM inkl. BuS und Tunnellüftung" für das Projekt S 18 Bodensee Schnellstraße. Leistungsziel ist der Abschluss der Leistungen mit der Phase Einreichprojekt mit Genehmigung des Tunnel-Vorentwurf (§7 STSG). services 71334000 ATZZZ AUT 2026-11-16+01:00 2030-12-31+01:00 Option 0