Electrical switchgear assemblies for the Beringen photovoltaic project, phase 2

The latest SIMAP detail adds a question round through 18 November 2026 and moves the answers to 20 November after an Outlook outage. The mandatory site visit took place on 11 November.

Place
Schaffhausen, canton of Schaffhausen
Deadline for receipt of offers
11:00 AM · UTC
Contract value
Not stated in the notice
Lots
1 lot
Contract period
The public notice does not state a contract period.
Published
November 16, 2026
SIMAP

Overview

The Elektrizitätswerk des Kantons Schaffhausen seeks supply and installation of electrical switchgear assemblies for phase 2 of the Beringen Syntegon Packaging Systems photovoltaic project. The notice identifies one lot under cost group BKP 231.2. A mandatory project briefing and site visit took place on 11 November 2026 at 08:00, with a safety briefing for all trades. The notice provides another question round through 18 November, with answers shifted to 20 November. Offers are due on 14 December 2026 at 12:00 CET. Consortia and subcontractors are permitted; detailed technical and qualification requirements are in the tender documents.

Information based on the public notice

What the buyer needs

Supply or installation of BKP 231.2 electrical switchgear assemblies for phase 2 of the Beringen photovoltaic project. The notice states that technical scope is detailed in the tender documents.

  • Attendance at the project briefing and site visit on 11 November 2026 at 08:00 is mandatory. A safety briefing is planned for all trades. Detailed technical and qualification requirements are in the tender documents.

Lots

1 ·BKP231.2 Schaltgerätekombinationen

Tender details

Buyer
Elektrizitätswerk des Kanton Schaffhausens AG
Country
Switzerland
Procedure
open
Classification
Electrical and electronic equipment · CPV 31200000
Notice reference
46555 · 46555-02
Lot
One lot for BKP 231.2 switchgear assemblies
Mandatory briefing and site visit
11 November 2026, 08:00
Offer deadline
14 December 2026 at 12:00 CET (UTC+01:00)
Additional question round
Questions through 18 November; answers 20 November 2026

What to check in the tender documents

  • The public notice does not state an estimated value or award result.
  • Detailed technical specifications are in the tender documents.
Get started with Ziva

Original notice

Read the original description

BKP231.2 Schaltgerätekombinationen- Beringen, Syntegon Packaging Systems – Etappe 2 (PV)

Bauauftrag: BKP231.2 Schaltgerätekombinationen [project-info.title.de] BKP231.2 Schaltgerätekombinationen- Beringen, Syntegon Packaging Systems – Etappe 2 (PV) [project-info.offerAddress.postalCode] 8201 [project-info.offerAddress.countryId] CH [project-info.offerAddress.id] e8960412-bb95-4912-82d2-c33f9b6136e7 [project-info.offerAddress.reference] Ausschreibung Beringen, Syntegon (PV) [procurement.orderDescription.de] Bauauftrag: BKP231.2 Schaltgerätekombinationen [project-info.procOfficeAddress.name.de] Elektrizitätswerk des Kanton Schaffhausens AG [project-info.procOfficeAddress.street.de] Rheinstrasse 37 [project-info.procOfficeAddress.postalCode] 8201 [project-info.procOfficeAddress.city.de] Schaffhausen [Personal contact channel omitted from the public extract.] +41526335253 [project-info.procOfficeAddress.email] [Contact email omitted from the public extract.] [dates.offerDeadline] 2026-12-14T12:00:00+01:00 [dates.questionDeadline] 2026-11-13 {'de': None, 'en': None, 'fr': None, 'it': None} [terms.consortiumAllowed] yes [terms.subContractorAllowed] yes [terms.subContractorNote.de] Subunternehmer müssen in den Offerten Unterlagen genannt werden. [terms.otherRequirements.de] siehe Bedingungen in den Dokumenten [terms.remediesNotice.de] [Personal contact channel omitted from the public extract.] [lots.1.title.de] BKP231.2 Schaltgerätekombinationen

Official source: SIMAP ↗

Notice updates

November 16, 2026 · Version 2

Deadline information updated · Summary and analysis updated · Tender facts updated · Original notice updated · Deadline updated · Source notice details updated · Source references updated · Notice update added

BKP231.2 Schaltgerätekombinationen- Beringen, Syntegon Packaging Systems – Etappe 2 (PV)

Bauauftrag: BKP231.2 Schaltgerätekombinationen [project-info.title.de] BKP231.2 Schaltgerätekombinationen- Beringen, Syntegon Packaging Systems – Etappe 2 (PV) [project-info.offerAddress.postalCode] 8201 [project-info.offerAddress.countryId] CH [project-info.offerAddress.id] e8960412-bb95-4912-82d2-c33f9b6136e7 [project-info.offerAddress.reference] Ausschreibung Beringen, Syntegon (PV) [procurement.orderDescription.de] Bauauftrag: BKP231.2 Schaltgerätekombinationen [project-info.procOfficeAddress.name.de] Elektrizitätswerk des Kanton Schaffhausens AG [project-info.procOfficeAddress.street.de] Rheinstrasse 37 [project-info.procOfficeAddress.postalCode] 8201 [project-info.procOfficeAddress.city.de] Schaffhausen [Personal contact channel omitted from the public extract.] +41526335253 [project-info.procOfficeAddress.email] [Contact email omitted from the public extract.] [dates.offerDeadline] 2026-12-14T12:00:00+01:00 [dates.questionDeadline] 2026-11-13 {'de': None, 'en': None, 'fr': None, 'it': None} [terms.consortiumAllowed] yes [terms.subContractorAllowed] yes [terms.subContractorNote.de] Subunternehmer müssen in den Offerten Unterlagen genannt werden. [terms.otherRequirements.de] siehe Bedingungen in den Dokumenten [terms.remediesNotice.de] [Personal contact channel omitted from the public extract.] [lots.1.title.de] BKP231.2 Schaltgerätekombinationen

November 5, 2026 · Version 1

Published

BKP231.2 Schaltgerätekombinationen- Beringen, Syntegon Packaging Systems – Etappe 2 (PV)

Bauauftrag: BKP231.2 Schaltgerätekombinationen [project-info.title.de] BKP231.2 Schaltgerätekombinationen- Beringen, Syntegon Packaging Systems – Etappe 2 (PV) [project-info.offerAddress.postalCode] 8201 [project-info.offerAddress.countryId] CH [project-info.offerAddress.id] e8960412-bb95-4912-82d2-c33f9b6136e7 [project-info.offerAddress.reference] Ausschreibung Beringen, Syntegon (PV) [procurement.orderDescription.de] Bauauftrag: BKP231.2 Schaltgerätekombinationen [project-info.procOfficeAddress.name.de] Elektrizitätswerk des Kanton Schaffhausens AG [project-info.procOfficeAddress.street.de] Rheinstrasse 37 [project-info.procOfficeAddress.postalCode] 8201 [project-info.procOfficeAddress.city.de] Schaffhausen [project-info.procOfficeAddress.phone] +41526335253 [project-info.procOfficeAddress.email] patrick.sixta@eks.ch [dates.offerDeadline] 2026-12-14T12:00:00+01:00 [dates.questionDeadline] 2026-11-13 {'de': None, 'en': None, 'fr': None, 'it': None} [terms.consortiumAllowed] yes [terms.subContractorAllowed] yes [terms.subContractorNote.de] Subunternehmer müssen in den Offerten Unterlagen genannt werden. [terms.otherRequirements.de] siehe Bedingungen in den Dokumenten [terms.remediesNotice.de] Gegen diese Ausschreibung kann innert 20 Tagen, von der Publikation an gerechnet, beim Obergericht des Kantons Schaffhausen, Frauengasse 17, 8200 Schaffhausen, schriftlich Beschwerde erhoben werden. Die Beschwerdeschrift muss einen Antrag und eine Begründung enthalten und ist im Doppel einzureichen. Die angefochtene Verfügung und vorhandene Beweismittel sind beizulegen. [lots.1.title.de] BKP231.2 Schaltgerätekombinationen