Construction design for the Castellón Port southern rail-access electrical substation, Phase 0 access conduits

Outcome

Awarded to BECSA, S.A. on 21 May 2021 for €33,692.52. Open tenders like this one are listed below.

The Port Authority transparency table reports the award amount without stating its VAT basis.

Place
Spain
Submission deadline
Not available
Award amount
€33,692.52
Award details
BECSA, S.A.
May 21, 2021
Classification
Works
Published
December 4, 2023
Autoridad Portuaria de Castellón

Overview

Constructive design for the electrical substation serving the southern rail access to Castellón Port, Phase 0, including access conduits on port land. The Port Authority’s 2021 Q2 transparency register lists BECSA, S.A. as contractor, an award of €33,692.52 (VAT basis not specified), and 21 May 2021 as the award date.

Information based on the public notice

What the buyer needs

Constructive design for the electrical substation serving the southern rail access to Castellón Port, Phase 0, including access conduits on port land.

Award details

Supplier
BECSA, S.A.
Award date
May 21, 2021
Award amount
€33,692.52

Tender details

Buyer
Presidencia de la Autoridad Portuaria de Castellón
Country
Spain
Procedure
Minor contract
Classification
Works · CPV 45232000 · NUTS ES522
Notice reference
8711822
Contractor
BECSA, S.A.
Award amount; VAT basis not stated
€33,692.52
Award date
2021-05-21

What to check in the tender documents

  • The transparency register supplies no additional technical design scope or delivery requirements.
Get started with Ziva

Original notice

Read the original description

Proyecto Constructivo de la Subestación Eléctrica del acceso Ferroviario Sur al Puerto de Castellón. Fase 0. Canalizaciones de acceso en terrenos del Puerto de Castellón

Proyecto Constructivo de la Subestación Eléctrica del acceso Ferroviario Sur al Puerto de Castellón. Fase 0. Canalizaciones de acceso en terrenos del Puerto de Castellón

Official source: Autoridad Portuaria de Castellón ↗

Official notice PDF ↗