KSS Energia electrode boiler project for district heating

KSS Energia OyFinlandStatus unconfirmed
Place
Kouvola, Finland (buyer address in canonical record; project site not specified).
8 April 2027 at 03:05:01.064 UTC as recorded; source schedule conflicts with earlier milestones.
03:05 AM · UTC
Contract value
Not stated in the notice
Classification
District heating boiler plant
Published
October 8, 2026
Hilma, Finnish public procurement notice service

Overview

KSS Energia Oy is planning an approximately 40 MW electrode boiler plant for district heating, including the equipment and systems needed for a functioning installation. The notice description identifies 10 kV IT-grid constraints, a short-circuit withstand requirement of 28 kA for one second, and ability to participate in frequency containment reserves. It says the procurement depends on an approved investment decision. The official Hilma page returned a shell without the assigned reference or title. The preliminary schedule in the source includes 2026 milestones that predate the record’s 8 October 2026 publication, while its deadline is 8 April 2027. The current process stage is therefore unconfirmed; the source text ends mid-sentence.

Information based on the public notice

What the buyer needs

Planned procurement of an approximately 40 MW electrode boiler plant for district heating, with associated equipment and systems. The description also states electrical-grid, short-circuit and FCR requirements.

  • Design, supply and erection must meet applicable Finnish laws, regulations, norms and authority requirements.
  • The boiler must meet the KJV2026 grid-code requirements expected to apply at delivery.
  • The plant must withstand at least 28 kA short-circuit current for one second and be capable of FCR participation.
  • Procurement is conditional on approval of an investment decision.

Tender details

Buyer
KSS Energia Oy
Country
Finland
Procedure
neg-w-call
Classification
District heating boiler plant · CPV 45251000 42160000 42161000
Notice reference
EF-58574
Project
Electrode boiler plant for district heating; approximately 40 MW output.
Included scope
Boiler plant and equipment/systems required for a functional installation; water-treatment equipment is included if needed.
Grid constraints
10 kV IT supply; no neutral point available.
Electrical requirement
Withstand at least 28 kA short-circuit current for one second.
System capability
Must be capable of participating in Frequency Containment Reserves (FCR).
Investment condition
Procurement is subject to an approved investment decision.
Deadline
8 April 2027 at 03:05:01.064 UTC, as stored in the assigned source.
Schedule caveat
The preliminary schedule lists 2026 milestones earlier than the recorded 8 October 2026 publication; current stage is unconfirmed.

What to check in the tender documents

  • The official detail page did not expose content matching the assigned reference; value, final participation procedure and current milestone status are not confirmed.
  • The preliminary schedule contains 2026 milestones that predate the record’s 8 October 2026 publication, conflicting with the 8 April 2027 deadline.
  • The available source description ends mid-sentence after referring to Fingrid materials.
  • No award or supplier is stated.
Get started with Ziva

Original notice

Read the original description

Hinkismäki Electrode boiler procurement

Hinkismäki Electrode boiler procurement KSS Energia Oy (later "KSS" or "Procurement Unit") is planning the purchase of an electrode boiler to produce district heat. It is initially estimated that the electrode boiler plant will produce district heating with an output of approx. 40 MW. The procurement will cover also any relevant equipment, systems and procurements needed for fully functional and operational electrode boiler. Candidates should also note that, if higher quality water treatment system is needed by the electrode boiler, this water treatment system, including make-up water tank, pumps and all other necessary equipment to produce make-up water for the boiler is included in the scope of the Supplier . Any party participating in the procurement must note that the KSS 's electricity grid is subject to the following constraints: Supply voltage 10 kV IT, no neutral point available. The electrode boiler must withstand, at minimum, a short circuit current of 28 kA for 1 second (Ith). Fimpec Engineering Oy, a part of Sweco, is a consulting engineering company that provides qualified consulting services with a high knowledge content in Finland. Fimpec is working together with KSS to advance the project to a maturity level where investment decision can be made. PRELIMINARY PROJECT SCHEDULE Submission of Applications, April 2026 Selection of Tenderers, April 2026 Submission of Preliminary Request for Quotation, May 2026 Negotiations, May to July 2026 Submission of Final Request for Quotation, August 2026 Contract award, September 2026 The delivery must be ready for commissioning no later than the 2027–2028 heating season. The procurement is subject to an approved investment decision. The candidate shall ensure that the design, supply and erection of the electrode boiler shall fulfil the mandatory laws, regulations, norms and authority requirements which are applicable in Finland at the time of the delivery. In particular, the candidate should note that the electrode boiler must meet the requirements of the grid code specifications for demand connections (KJV2026), which are estimated to be in force at the time of delivery. The electrode boiler must be capable of participating in the Frequency Containment Reserves (FCR). The technical specifications for FCR and KJV2026 are available on the website of Finland’s transmission system operator (www.fingrid.fi/en),

Official source: Hilma, Finnish public procurement notice service ↗