Innlandet County is seeking bridge maintenance and repair under a framework agreement for 2027–2028. Work may include joint and bearing repairs, concrete and asphalt repairs, waterproofing, corrosion protection, railings, drainage and other bridge works on county roads. The county has about 1,250 bridges, with specific sites to be prioritised after annual inspections. The estimated overall amount is NOK 200 million; the framework is planned for two years with up to two one-year extensions. Price is weighted at 100%, while the climate and environment criterion is listed at 0%. The notice also sets extensive environmental management and site requirements. Offers are due 30 October 2026 at 12:00 UTC+01:00.
Framework agreement for maintenance and repair work on county road bridges in Innlandet during 2027–2028, with up to two one-year extensions. Specific bridges will be selected following annual inspections.
Tenderers must hold an ISO 14001-certified environmental management system or equivalent. Monthly greenhouse-gas reports and documented routines for environmental substances are required. Machines must meet at least EURO 6 or Stage IV emission requirements; project managers and administrative staff must use zero-emission vehicles for contract-related site visits and meetings.
Waste must be managed with at least 80% sorting, and results reported. A mass-disposal plan is required. Liquid fossil fuels may not be used to heat formwork or structures in or near waterways. Machines must be washed when moving between watercourses and carry absorbents for spills.
2027–2028, with up to two one-year extensions (2+1+1)
Award weights
Price 100%; climate and environment 0% as structured
Tender deadline
30 October 2026, 12:00 (UTC+01:00)
What to check in the tender documents
The framework sets no specific bridge locations or quantities in advance; sites will be prioritised after annual inspections and reported damage. The notice refers to tender documents for detailed qualification and rejection criteria. The environmental award criterion is described in detail but its structured weight is 0%, alongside a 100% price weight.
Framework agreement Bruvedlikehold 2027-2028
Background and purpose
The aim of the procurement is to enter into a framework agreement that covers the Contracting Authority's need for delivery and execution of work connected to bridge maintenance.
The total number of busy bridges on county roads in Innlandet County is approx. 1,250.
The work will take place on county road bridges in Innlandet.
The work mainly concerns minor maintenance work. If there is a need for more comprehensive maintenance work on individual bridges, this will be announced as separate contracts.
The assignments will vary in extent and comprise bridge maintenance of various nature, including joint repairs, replacement of asphalt joints, repair of joints, repairs of bearings, concrete repairs, cover repairs, cover maintenance, asphalt and membrane work, corrosion protection, replacement and repair of railings, edge binders, water sewage, major concrete works due to flood damage, repairs due to under-excavation, stream alterations etc.
Award criteria:
The price form will be assessed under this criteria.
Climate and environment:
The contract is for the maintenance and renovation of existing bridges, which in itself is an important climate and environmental measure. Repairing and extending the lifetime of the existing structures reduces the need for demolition and new construction, with the accompanying resource consumption, transport and greenhouse gas emissions.
In order to ensure that the contract is implemented in an environmentally responsible manner, the contractor has a number of climate and environmental requirements. Tenderers shall have an environmental management system certified in accordance with ISO 14001 or equivalent. Monthly reports of greenhouse gas emissions are required throughout the contract period, so that the builder can follow-up on the environmental performance of the project.
Furthermore there are requirements for handling noise, dust, emissions to the outer environment and the spreading of foreign species. Tenderers shall ensure good waste management with a minimum of 80% sorting degree and results shall be reported to the builder. A mass disposal plan is also required to ensure effective and environmentally correct handling of matter.
In order to reduce emissions from the site implementation, the machines and vehicles used in the contract must as a minimum fulfil the emission requirements EURO 6 or Steg IV. Project managers and administrative personnel shall use emission free vehicles for site inspections and meetings connected to the contract.
The assignments include measures on bridges distributed throughout The Hinterland. As of now, it has not yet been decided which bridges shall be improved. This will be prioritised after annual inspections and reported injuries. Several of the relevant premises are located in pig-branched areas with limited network capacity and insufficient electrical infrastructure. This leads to considerable practical challenges connected to the establishment of any emission free site and the use of electrical site equipment.
Liquid fossile fuel is not allowed to be used for heating the form/structures in or close to waterways. All machines shall be washed when moved from one watercourse to another.
In order to prevent environmental damage, all machines shall be equipped with absorption agents for handling any spills and leaks. Tenderers shall also have documented routines for substitutes and proper handling of health and environmentally damaging substances.
In addition to climate and environmental considerations in the contract requirements and the requirement specifications, climate and environmental considerations are included as an award criterion. The tenders will be evaluated based on documented environmental performance through environmental declarations (EPDs) for central materials, transport and processes. Climate gas emissions connected to concrete, steel and railings will be weighted in the evaluation. This shall contribute to stimulating the choice of materials and systems that give the lowest possible climate footprint throughout the execution of the contract.
Combined this means that a combination of requirements and criteria gives a better climate and environmental effect than weighting climate and environmental considerations with a minimum of 30%, cf. The Public Procurement Act §5b (2).
Price carries a weight of 100%; the climate and environment criterion is listed with a weight of 0%. Tender submission deadline: 30 October 2026, 12:00 (UTC+01:00). The framework is for 2027–2028, with options to extend by one year at a time up to twice (2+1+1).