Solar plant acquisition and installation framework agreement for Ukraine

East Europe FoundationSwitzerlandClosed

Outcome

Submissions closed on 9 November 2026. No award has been published yet. Open tenders like this one are listed below.

The offer deadline of 9 November 2026 at 23:59 (UTC+01:00) has passed, so the tender is now closed.

Place
Ukraine (installation on the territory of Ukraine, contracting office in Kyiv)
9 November 2026 at 23:59 (UTC+01:00)
10:59 PM · UTC
Contract value
Not stated in the notice
Contract period
Framework term of eighteen (18) months; contract term 550 days after signature, as stated in the SIMAP contract deadline field
Published
September 28, 2026
Official SIMAP publication 44702-01 (simap.ch)

Overview

East Europe Foundation is tendering a framework agreement for the purchase and installation of solar power plants in Ukraine. The notice describes a supply contract under an open procedure, with an 18-month framework term and a contract term of 550 days after signature, as stated in the SIMAP contract field. The specifications set a hybrid inverter of at least 5 kW, panels of at least 400 W and a battery of at least 2 kWh, with warranties of 5 years for panels, 2 years for inverters and 1 year for installation. Bids must be in Ukrainian and are submitted electronically through SIMAP. The offer deadline was 9 November 2026 at 23:59 (UTC+01:00), and the opening was set for 10 November 2026 at 10:00 (UTC+01:00). The tender is now closed.

Information based on the public notice

What the buyer needs

Supply and installation of solar power plants on the territory of Ukraine under a framework agreement, procured as an open supply contract with electronic submission through SIMAP. The notice sets technical minimums for the equipment, qualification requirements and six weighted evaluation criteria.

  • Bids must be in Ukrainian; foreign-language documents need an identical Ukrainian translation, and the Ukrainian text prevails.
  • Bidders need at least three years of experience in the solar energy market, official registration, and the relevant licences and certificates.
  • Warranties: at least 5 years for panels, 2 years for inverters and other units, and 1 year for installation.

Tender details

Buyer
East Europe Foundation
Country
Switzerland
Procedure
open
Classification
Energy and utilities · CPV 09331000 solar panels; additional CPV 09332000 solar installation and 45261215 solar panel roof-covering work
Notice reference
44702 · 44702-01
Offer deadline
9 November 2026 at 23:59 (UTC+01:00)
Question deadline
13 October 2026
Offer opening
10 November 2026 at 10:00 (UTC+01:00)
Bid language
Ukrainian; foreign-language documents need an identical Ukrainian translation, and the Ukrainian text prevails
Offer validity
90 days
Prices
VAT not included

What to check in the tender documents

  • The notice does not state an estimated value or budget.
  • The notice does not state the quantities of systems or the individual installation sites.
  • Payment terms follow Ukrainian legislation as stated; the notice does not give further payment milestones.
Get started with Ziva

Original notice

Read the original description

Solar Plant Acquisition and Installation_Framework_Agreement_Ukraine

Title: Solar Plant Acquisition and Installation_Framework_Agreement_Ukraine Publication number: 44702-01 Publication date: 2026-09-29 Procedure type: Open procedure Contract type: Supply contract Contracting authority: East Europe Foundation Address: 96 Saksahanskoho str., office 508 (5th floor), 01032 Kyiv Telephone: +380504437258 Functional email: tender@egap.in.ua Website: https://www.eef.org.ua Description: Framework agreement on solar plant acquisition and installation on the territory of Ukraine. CPV code: 09331000 Solar panels Additional CPV codes: 09332000 Solar installation; 45261215 Solar panel roof-covering work Execution note: Term of framework: eighteen (18) months. Contract period: 550 days after contract signature (source contract deadline type days_after) Document languages: en Offer languages: en Offer form: Electronic submission via SIMAP Documents available: Documents available on SIMAP Question deadline: 2026-10-13 Offer deadline: 2026-11-09T23:59:00+01:00 Offer validity: 90 days Offer opening: 2026-11-10T10:00:00+01:00 Qualification note: 1. Previous experience (20%): - Experience in the implementation of projects of similar complexity for 3 years (confirmation of the project's implementation related to SPP installation (at least 3 projects) or with the total equivalent cost of completed projects not less than USD 50 thousand); 2. Availability of equipment and resources (15%): - Own or subcontracted organization to supply and/or install equipment; - Infrastructure availability (logistics and transportation, warehouses, technical means, and machinery for equipment installation); 3. Human resources (15%) The company staffing level The number of certified personnel (relevant training and certification, namely, in such areas as electrical safety,installation of solar systems, and operations with similar equipment, availability of professionals with electrical safetycertificates authorizing to work with electrical installations of up to 1,000 V or higher); 4. Cost (price criterion) (25%) Evaluation of price offers under the summary table in the tender application; 5. Qualitative equipment characteristics (15%) Evaluation of the proposed equipment models under the set equipment requirements and comparison of the quality characteristics of the proposed models; 6. Order fulfillment term (10%) Starting with the facility survey to assembly according to the SPP installation calendar plan as set in the application. Comments: every bid shall be evaluated according to the mentioned award criteria and relevant weightings. Payment terms: Payments shall be done according to Ukrainian legislation. Included costs: VAT not included. Site visit: n/a Terms: General requirements • Supplier qualification: the supplier shall have at least 3 years of experience in the solar energy market, be officially registered, and have the relevant licenses and certificates. • Warranties: the supplier shall provide a warranty for the equipment (at least 5 years for the panel and 2 years for inverters and other units). Installation warranty — at least 1 year. Equipment requirements all proposed equipment for SPP sets shall be compatible and operate as a single system. • Hybrid inverter: power (nominal) – not less than 5 kW; output signal – pure sine wave; option to automatically switch (mix) network/solar panels/battery power with variable priority included; battery charge controller type: MPPT, the desired quantity of MPPT trackers is at least 2; inverter efficiency coefficient – at least 92%; option to control settings and view status/statistics remotely via WiFi is optional; option to install several devices and unite them into a single system to build a higher capacity SPP. • Solar panels: the minimum nominal power of one panel is 400 W; the conversion factor should be more than 21%; panels must be resistant to extreme temperatures, wind, rain, snow, etc. • Storage battery: capacity: from 2 kWh; technology: LiFePo4 (priority). Installation requirements Design and installation: the supplier shall provide a system design and detailed engineering calculations that account for the proposed panel location, tilt angle, orientation, roof or ground conditions, and electrical connection diagrams for the solar panels, inverters, and batteries. • Installation work: installation of solar panels, inverters, and other equipment shall be carried out by qualified professionals in compliance with all safety requirements and standards. Maintenance and service • Post-installation service: the supplier shall ensure system maintenance and repair services during the warranty period. • Technical support: access to technical support shall be granted during the system's lifetime. Documentation and licenses • Documentation: the supplier shall submit all necessary documentation for the equipment, including certificates of conformity/quality, operating guidelines, and data sheets. • Licenses and certifications: equipment shall meet local standards and licensing requirements, and shall be certified to international standards (ISO, IEC, etc.). Legal remedies: In accordance with Article 56 paragraph 1 of the Public Procurement Act (PPA), a written appeal against this decision can be lodged with the Federal Administrative Court, P.O. Box, 9023 St. Gallen, Switzerland, within 20 days of notification. Any appeal is to be submitted in duplicate and must include what is being sought, the grounds for appeal, evidence and the signature of the person lodging the appeal or his or her representative. A copy of this decision and available evidence must be included. The provisions of the Administrative Procedure Act (APA) on legal holidays do not apply in accordance with Article 56 paragraph 2 of the PPA. Based on Article 52 paragraph 2 of the PPA, the appeal can be used only to establish that this decision violates federal law, but not to apply for its cancellation. Foreign providers are permitted to appeal only to the extent that the state in which they are domiciled grants reciprocal rights.

Official source: Official SIMAP publication 44702-01 (simap.ch) ↗

Notice updates

November 11, 2026 · Version 3

Classification updated · Contract period updated · Deadline information updated · Summary and analysis updated · Tender facts updated · Original notice updated · Deadline updated · Location updated · Source updated · Source notice details updated · Source references updated · Status changed · Notice update added

Solar Plant Acquisition and Installation_Framework_Agreement_Ukraine

Title: Solar Plant Acquisition and Installation_Framework_Agreement_Ukraine Publication number: 44702-01 Publication date: 2026-09-29 Procedure type: Open procedure Contract type: Supply contract Contracting authority: East Europe Foundation Address: 96 Saksahanskoho str., office 508 (5th floor), 01032 Kyiv Telephone: +380504437258 Functional email: tender@egap.in.ua Website: https://www.eef.org.ua Description: Framework agreement on solar plant acquisition and installation on the territory of Ukraine. CPV code: 09331000 Solar panels Additional CPV codes: 09332000 Solar installation; 45261215 Solar panel roof-covering work Execution note: Term of framework: eighteen (18) months. Contract period: 550 days after contract signature (source contract deadline type days_after) Document languages: en Offer languages: en Offer form: Electronic submission via SIMAP Documents available: Documents available on SIMAP Question deadline: 2026-10-13 Offer deadline: 2026-11-09T23:59:00+01:00 Offer validity: 90 days Offer opening: 2026-11-10T10:00:00+01:00 Qualification note: 1. Previous experience (20%): - Experience in the implementation of projects of similar complexity for 3 years (confirmation of the project's implementation related to SPP installation (at least 3 projects) or with the total equivalent cost of completed projects not less than USD 50 thousand); 2. Availability of equipment and resources (15%): - Own or subcontracted organization to supply and/or install equipment; - Infrastructure availability (logistics and transportation, warehouses, technical means, and machinery for equipment installation); 3. Human resources (15%) The company staffing level The number of certified personnel (relevant training and certification, namely, in such areas as electrical safety,installation of solar systems, and operations with similar equipment, availability of professionals with electrical safetycertificates authorizing to work with electrical installations of up to 1,000 V or higher); 4. Cost (price criterion) (25%) Evaluation of price offers under the summary table in the tender application; 5. Qualitative equipment characteristics (15%) Evaluation of the proposed equipment models under the set equipment requirements and comparison of the quality characteristics of the proposed models; 6. Order fulfillment term (10%) Starting with the facility survey to assembly according to the SPP installation calendar plan as set in the application. Comments: every bid shall be evaluated according to the mentioned award criteria and relevant weightings. Payment terms: Payments shall be done according to Ukrainian legislation. Included costs: VAT not included. Site visit: n/a Terms: General requirements • Supplier qualification: the supplier shall have at least 3 years of experience in the solar energy market, be officially registered, and have the relevant licenses and certificates. • Warranties: the supplier shall provide a warranty for the equipment (at least 5 years for the panel and 2 years for inverters and other units). Installation warranty — at least 1 year. Equipment requirements all proposed equipment for SPP sets shall be compatible and operate as a single system. • Hybrid inverter: power (nominal) – not less than 5 kW; output signal – pure sine wave; option to automatically switch (mix) network/solar panels/battery power with variable priority included; battery charge controller type: MPPT, the desired quantity of MPPT trackers is at least 2; inverter efficiency coefficient – at least 92%; option to control settings and view status/statistics remotely via WiFi is optional; option to install several devices and unite them into a single system to build a higher capacity SPP. • Solar panels: the minimum nominal power of one panel is 400 W; the conversion factor should be more than 21%; panels must be resistant to extreme temperatures, wind, rain, snow, etc. • Storage battery: capacity: from 2 kWh; technology: LiFePo4 (priority). Installation requirements Design and installation: the supplier shall provide a system design and detailed engineering calculations that account for the proposed panel location, tilt angle, orientation, roof or ground conditions, and electrical connection diagrams for the solar panels, inverters, and batteries. • Installation work: installation of solar panels, inverters, and other equipment shall be carried out by qualified professionals in compliance with all safety requirements and standards. Maintenance and service • Post-installation service: the supplier shall ensure system maintenance and repair services during the warranty period. • Technical support: access to technical support shall be granted during the system's lifetime. Documentation and licenses • Documentation: the supplier shall submit all necessary documentation for the equipment, including certificates of conformity/quality, operating guidelines, and data sheets. • Licenses and certifications: equipment shall meet local standards and licensing requirements, and shall be certified to international standards (ISO, IEC, etc.). Legal remedies: In accordance with Article 56 paragraph 1 of the Public Procurement Act (PPA), a written appeal against this decision can be lodged with the Federal Administrative Court, P.O. Box, 9023 St. Gallen, Switzerland, within 20 days of notification. Any appeal is to be submitted in duplicate and must include what is being sought, the grounds for appeal, evidence and the signature of the person lodging the appeal or his or her representative. A copy of this decision and available evidence must be included. The provisions of the Administrative Procedure Act (APA) on legal holidays do not apply in accordance with Article 56 paragraph 2 of the PPA. Based on Article 52 paragraph 2 of the PPA, the appeal can be used only to establish that this decision violates federal law, but not to apply for its cancellation. Foreign providers are permitted to appeal only to the extent that the state in which they are domiciled grants reciprocal rights.

October 12, 2026 · Version 2

Deadline information updated · Summary and analysis updated · Tender facts updated · Original notice updated · Location updated · Source references updated

Solar Plant Acquisition and Installation_Framework_Agreement_Ukraine

Solar Plant Acquisition and Installation_Framework_Agreement_Ukraine Framework agreement on solar plant acquisition and installation on the territory of Ukraine. Framework term: eighteen (18) months. Place of performance: Kyiv, Ukraine. Offer deadline: 9 November 2026, 23:59 CET. Questions: 13 October 2026. Offers valid for 90 days. Offer opening: 10 November 2026, 10:00 CET; not public. Offer language: English. Ukrainian-language requirement: Language of the bid: all documents submitted as part of the bid must be in Ukrainian. If the text of the document is written in a foreign language, its Ukrainian translation must be attached. The original and the translation must be identical; the Ukrainian text shall prevail. Offers are submitted electronically via SIMAP. Consortium bids and subcontracting are not allowed. Variants and partial offers are not allowed. Payment is according to Ukrainian legislation. VAT is not included. General requirements General requirements • Supplier qualification: the supplier shall have at least 3 years of experience in the solar energy market, be officially registered, and have the relevant licenses and certificates. • Warranties: the supplier shall provide a warranty for the equipment (at least 5 years for the panel and 2 years for inverters and other units). Installation warranty — at least 1 year. Equipment requirements all proposed equipment for SPP sets shall be compatible and operate as a single system. • Hybrid inverter: power (nominal) – not less than 5 kW; output signal – pure sine wave; option to automatically switch (mix) network/solar panels/battery power with variable priority included; battery charge controller type: MPPT, the desired quantity of MPPT trackers is at least 2; inverter efficiency coefficient – at least 92%; option to control settings and view status/statistics remotely via WiFi is optional; option to install several devices and unite them into a single system to build a higher capacity SPP. • Solar panels: the minimum nominal power of one panel is 400 W; the conversion factor should be more than 21%; panels must be resistant to extreme temperatures, wind, rain, snow, etc. • Storage battery: capacity: from 2 kWh; technology: LiFePo4 (priority). Installation requirements Design and installation: the supplier shall provide a system design and detailed engineering calculations that account for the proposed panel location, tilt angle, orientation, roof or ground conditions, and electrical connection diagrams for the solar panels, inverters, and batteries. • Installation work: installation of solar panels, inverters, and other equipment shall be carried out by qualified professionals in compliance with all safety requirements and standards. Maintenance and service • Post-installation service: the supplier shall ensure system maintenance and repair services during the warranty period. • Technical support: access to technical support shall be granted during the system's lifetime. Documentation and licenses • Documentation: the supplier shall submit all necessary documentation for the equipment, including certificates of conformity/quality, operating guidelines, and data sheets. • Licenses and certifications: equipment shall meet local standards and licensing requirements, and shall be certified to international standards (ISO, IEC, etc.). Evaluation criteria and weightings 1. Previous experience (20%): - Experience in the implementation of projects of similar complexity for 3 years (confirmation of the project's implementation related to SPP installation (at least 3 projects) or with the total equivalent cost of completed projects not less than USD 50 thousand); 2. Availability of equipment and resources (15%): - Own or subcontracted organization to supply and/or install equipment; - Infrastructure availability (logistics and transportation, warehouses, technical means, and machinery for equipment installation); 3. Human resources (15%) The company staffing level The number of certified personnel (relevant training and certification, namely, in such areas as electrical safety,installation of solar systems, and operations with similar equipment, availability of professionals with electrical safetycertificates authorizing to work with electrical installations of up to 1,000 V or higher); 4. Cost (price criterion) (25%) Evaluation of price offers under the summary table in the tender application; 5. Qualitative equipment characteristics (15%) Evaluation of the proposed equipment models under the set equipment requirements and comparison of the quality characteristics of the proposed models; 6. Order fulfillment term (10%) Starting with the facility survey to assembly according to the SPP installation calendar plan as set in the application. Comments: every bid shall be evaluated according to the mentioned award criteria and relevant weightings. Legal remedy In accordance with Article 56 paragraph 1 of the Public Procurement Act (PPA), a written appeal against this decision can be lodged with the Federal Administrative Court, P.O. Box, 9023 St. Gallen, Switzerland, within 20 days of notification. Any appeal is to be submitted in duplicate and must include what is being sought, the grounds for appeal, evidence and the signature of the person lodging the appeal or his or her representative. A copy of this decision and available evidence must be included. The provisions of the Administrative Procedure Act (APA) on legal holidays do not apply in accordance with Article 56 paragraph 2 of the PPA. Based on Article 52 paragraph 2 of the PPA, the appeal can be used only to establish that this decision violates federal law, but not to apply for its cancellation. Foreign providers are permitted to appeal only to the extent that the state in which they are domiciled grants reciprocal rights.

October 11, 2026 · Version 1

Published

Solar Plant Acquisition and Installation_Framework_Agreement_Ukraine

Solar Plant Acquisition and Installation_Framework_Agreement_Ukraine Framework agreement on solar plant acquisition and installation on the territory of Ukraine.