Overview

SBB plans a pedestrian underpass, upgrades to central platform 2/3 and a canopy at Villeneuve station. The current notice sets the offer deadline at 4 January 2027 at 15:00 CET. Offers must be submitted exclusively through SAP Ariba; suppliers request access using the public SIMAP participation form. The stated project period is 1 September 2027 to 31 March 2030. Award criteria are set out in the tender documents, and no estimated value appears in the notice.

Information based on the public notice

What the buyer needs

Rail construction at Villeneuve station for a pedestrian underpass, central platform 2/3 upgrade and platform canopy.

  • Submit the offer exclusively through SAP Ariba and request access through the public SIMAP participation form.
  • The project period in the notice is 1 September 2027 to 31 March 2030.

Tender details

Buyer
Buyer is SBB Infrastructure, Western Region construction procurement
Country
Switzerland
Procedure
open
Classification
Construction and civil works · CPV 45000000
Notice reference
791338-2026
Underpass
Works include a pedestrian underpass
Platform
Central platform 2/3 will be upgraded
Canopy
A canopy is planned for the central platform
Project period
Project period is 1 September 2027 to 31 March 2030
Deadline
Deadline is 4 January 2027 at 15:00 CET
Submission
Offers must be submitted exclusively in SAP Ariba
Access
Access is requested through the public SIMAP participation form
Award criteria
Award criteria are in the tender documents
Value
No estimated value appears in the notice

What to check in the tender documents

  • The notice does not state an estimated contract value.
  • Detailed award criteria are in the procurement documents.
Get started with Ziva

Original notice

Read the original description

Suisse – Travaux de construction – Mise en conformité des quais et renouvellement LC - Gare de Villeneuve

Le contrat consiste en la mise en oeuvre d'un passage inférieur ; de la mise en conformité du quai central 2/3 ainsi que la mise en place d'une marquise sur le quai précité.

Official source: TED ↗

Notice updates

November 22, 2026 · Version 2

Buyer updated · Contract period updated · Deadline information updated · Summary and analysis updated · Tender facts updated · Original notice updated · Deadline updated · Location updated · Source updated · Source notice details updated · Source references updated · Notice update added

Suisse – Travaux de construction – Mise en conformité des quais et renouvellement LC - Gare de Villeneuve

Le contrat consiste en la mise en oeuvre d'un passage inférieur ; de la mise en conformité du quai central 2/3 ainsi que la mise en place d'une marquise sur le quai précité.

November 17, 2026 · Version 1

Published

Швейцария – Строителни и монтажни работи – Mise en conformité des quais et renouvellement LC - Gare de Villeneuve

​​Le contrat consiste en la mise en oeuvre d'un passage inférieur ; de la mise en conformité du quai central 2/3 ainsi que la mise en place d'une marquise sur le quai précité.​