The Canton of Glarus is procuring lead engineering services for phases 31 to 53 of a new approximately 300 metre connection road between the Mitlödi to Glarus cantonal road at Leimen and Holenstein near Holenstein Bridge. The assignment includes phase-specific environmental protection planning and surveying, with environmental and soil construction supervision during delivery. The contract period is 1 April 2027 to 31 December 2031. Questions are due 9 December 2026. Offers remain valid for 183 days. Offers are due 15 January 2027 at 14:00 CET.

Information based on the public notice

What the buyer needs

The Canton of Glarus is procuring lead engineering services for phases 31 to 53 of a new approximately 300 metre connection road between the Mitlödi to Glarus cantonal road at Leimen and Holenstein near Holenstein Bridge. The assignment includes phase-specific environmental protection planning and surveying, with environmental and soil construction supervision during delivery. The contract period is 1 April 2027 to 31 December 2031.

  • Consortiums and subcontractors are permitted. The lead firm must be identified. A consortium member may be in only one team; subplanners may be in multiple teams. escd gmbh is excluded.

Tender details

Buyer
Abteilung Tiefbau
Country
Switzerland
Procedure
open
Classification
Engineering design services · CPV 71300000
Notice reference
47464 · 47464-01
Scope
The Canton of Glarus is procuring lead engineering services for phases 31 to 53 of a new approximately 300 metre connection road between the Mitlödi to Glarus cantonal road at Leimen and Holenstein near Holenstein Bridge. The assignment includes phase-specific environmental protection planning and surveying, with environmental and soil construction supervision during delivery. The contract period is 1 April 2027 to 31 December 2031.
Deadline
15 January 2027 at 14:00 CET
Questions deadline
9 December 2026
Offer validity
183 days
Contract or execution period
1 April 2027 to 31 December 2031

What to check in the tender documents

  • No estimated contract value is stated in the public notice.
  • Detailed participation or award criteria are in tender documents that were not reviewed.
Get started with Ziva

Original notice

Read the original description

Kantonsstrasse; Verbindungsstrasse Leimen-Holenstein, Planerleistungen Phase 31-53

Kantonsstrasse; Verbindungsstrasse Leimen-Holenstein, Planerleistungen Phase 31-53 Das Projekt Verbindungsstrasse Leimen–Holenstein beinhaltet den Neubau einer rund 300 m langen Verbindungsstrasse zwischen der Kantonsstrasse Mitlödi–Glarus im Gebiet Leimen und dem Gebiet Holenstein bei der Holensteinbrücke, inkl. der erforderlichen Anschlüsse an das bestehende Strassennetz. Gegenstand der vorliegenden Ausschreibung sind die Ingenieurleistungen im genannten Projekt in den SIA-Teilphasen 31–53 gemäss SIA 103/2014 des Ingenieurs als Gesamtleiter inkl. der phasenzugehörigen Leistungen zur Sicherstellung der Umwelt (Umweltnotiz) sowie der Vermessung. Als ergänzende Leistung sind die Umweltbaubegleitung und die bodenkundliche Baubegleitung (UBB/BBB) in der Realisierung enthalten. Other requirements: Die mit der Bauherrenunterstützung betraute escd gmbh ist von der Teilnahme ausgeschlossen. Consortium conditions: Die federführende Firma ist genau zu bezeichnen. Der Gesellschafter einer Bietergemeinschaft darf sich nur in einem Bewerbungsteam beteiligen. Weitere Bedingungen gemäss Dokument A. Subcontractor conditions: Subplaner sind zugelassen und dürfen sich in mehreren Bewerbungsteams beteiligen. Die Auftragsteile sind für jede Firma klar zu definieren und anzugeben. Offer deadline: 2027-01-15T14:00:00+01:00 Questions deadline: 2026-12-09 Offer validity: 183 days contractPeriod: 2027-04-01 to 2031-12-31 executionPeriod: 2027-04-01 to 2031-12-31

Official source: SIMAP ↗