A measurable social value bid commitment is a supplier promise tied to the subject matter and performance of a particular contract. It states what additional activity will be delivered, for which defined people or community, in what place and period, by which responsible party, using what funded resources. It also defines the unit, starting position, counting rules, source evidence, reporting frequency and response to shortfall. The record separates a mandatory contract condition from a scored offer and separates both from existing corporate activity. An output such as completed paid placement days can be controlled and counted directly. A later outcome such as sustained employment may be monitored, but should be promised only when the supplier has the authority and evidence needed to control it.
A regional public authority asks how an IT support bidder will create skills opportunities for people facing barriers to work. The draft says the supplier supports local employment, works with colleges and will provide training, mentoring and volunteering. None of those statements identifies a target group, number of places, duration, payment status, recruitment route, supervisor, delivery date or evidence. The same activities also appear in the bidder's annual responsibility report, so the evaluator cannot tell what the contract would add. Delivery has not reserved supervisor time or budget. If the wording enters the contract, the contract manager still has no rule for deciding whether the promise was met.
Begin with the exact criterion, assessment method, contract condition and applicable policy edition. Freeze the tender publication date because policy transitions can change which model applies. Define one commitment at the smallest unit that can be priced, assigned and verified. Keep required performance, existing activity, scored additional value and hoped-for community outcomes in separate fields. Count delivered activity under a written rule and describe longer-term outcomes as follow-up measures unless the supplier can control them. Test capacity with the people who will perform the work and obtain authority from every partner whose contribution appears in the offer. The final answer should show the evaluator a credible method and give the future contract manager the same operational promise.
Control point
Fix the tender date and requirement before designing the promise
Read the social value question beside the notice, evaluation method, definitions, schedules and draft contract. Capture the exact outcome or criterion selected by the buyer, any minimum commitment, the available score, word limit, evidence request and reporting terms. Do not import a familiar social value model when the procurement uses another one. The buyer's documents control the bid. Policy guidance helps interpret them but cannot silently replace them.
Timing matters in the United Kingdom. PPN 026 was published on 5 August 2026 and applies to covered procurements whose tender notices are published on or after 1 January 2027. For earlier procurements under the Procurement Act 2023, covered organizations are encouraged to transition but may use the previous edition in stated circumstances. The detailed PPN 026 guidance was still due in autumn 2026 when this dossier was reviewed. A bidder should therefore record the notice date and model named in the actual tender rather than filling missing future sub-criteria from assumption.
The same discipline applies elsewhere. EU rules permit social award criteria and performance conditions when they are linked to the subject matter and disclosed. German GWB sections 127 and 128 distinguish award criteria from special performance conditions. French rules changed in August 2026 for covered procurements. These regimes provide boundaries, not a universal answer template. Route legal interpretation to the authorized reviewer and preserve the decision with its date.
| Field | Record | Why it matters |
|---|---|---|
| Tender basis | Notice, question, criterion, definitions and lot | Prevents answering a different requirement |
| Time basis | Notice date, clarification date and policy edition | Controls transition rules and versions |
| Evaluation | Weight, score bands and requested evidence | Shows what the evaluator will judge |
| Contract route | Condition, KPI, schedule or accepted method | Shows how the promise can be managed |
Classification
Separate required performance, existing activity and added value
Create separate rows for four kinds of proposition. The first is core delivery that every compliant bidder must provide, such as an insertion-hours condition. The second is an existing organizational practice that establishes capability. The third is a contract-specific enhancement offered for score. The fourth is a community outcome that the activity may contribute to. Mixing them exaggerates the offer and makes delivery control impossible.
Additional value needs a comparison point. State what would happen under the minimum compliant delivery or under the supplier's already funded business-as-usual plan, then identify what this contract adds. Do not claim the full reach of a national apprenticeship programme because one contract funds a small number of places. Conversely, do not strip out a required activity simply because it already aligns with company policy. Keep the mandatory delivery in the contract plan and keep the claimed increment honest.
Use status labels that survive review: buyer minimum, current capability, existing funded activity, proposed additional commitment, dependent commitment and monitored outcome. The label determines the evidence and approval needed. A current capability needs present proof. A future offer needs authority, cost and a delivery plan. A monitored outcome needs a method and a clear statement that observation is not a guarantee.
Commitment
Write the commitment as an operable delivery record
A useful commitment names the actor, activity, beneficiary, quantity, unit, quality threshold, place, start, finish and evidence. It also names the delivery owner, performing party, cost source, dependencies, reporting cycle and response to variance. Leave an unknown field visible until the responsible person decides it. A polished sentence with missing mechanics is weaker than a record that shows one open dependency.
Keep the beneficiary definition close to the commitment. If the buyer names care leavers, disabled people or people not in employment, education or training, preserve that wording and the buyer's eligibility process. If the buyer leaves the cohort open, state how it will be agreed through an authorized referral body. Avoid inventing a geographic preference, age limit or protected-characteristic condition. Eligibility data should be confirmed by the permitted party and reported at the least personal level the contract needs.
The delivery owner must have authority over the resources. A social value lead may coordinate the record while an operations manager controls supervisor capacity, HR controls recruitment and a college controls course places. Name those responsibilities separately. When a subcontractor delivers activity, obtain its written agreement and retain the prime supplier's accountability to the buyer.
| Element | Required entry | Acceptance evidence |
|---|---|---|
| Activity | Defined task and quality threshold | Attendance, completion or service record |
| Beneficiary | Cohort, location and eligibility route | Authorized aggregate confirmation |
| Quantity | Number, unit and delivery window | Reconciled controlled register |
| Authority | Owner, performer and partner agreement | Approval and named responsibility |
| Resources | Budget, paid time, supervision and facilities | Cost and capacity approval |
| Control | Report, variance trigger and correction | Accepted report and action log |
Measurement
Decide what counts before selecting the target
The number is meaningful only after the unit is defined. A placement may mean an accepted offer, a first day, a minimum number of attended days or completion of the planned period. Training hours may mean scheduled learner hours, attended learner hours or instructor time. Jobs may mean vacancies, offers, starts or retained roles. Choose the unit named by the buyer. Where the documents are silent, propose a rule that can be inspected and ask for clarification if the difference could affect evaluation.
Count starts, completions and withdrawals separately. Record unique people as well as activity volume so repeated sessions do not look like wider reach. State whether paid time, training time, travel, preparation and remote attendance qualify. Define cut-off dates and evidence. Where participant privacy matters, the contract manager may need an eligibility confirmation and aggregate count rather than personal case files.
Outputs and outcomes need different claims. Completed placement days are an output. A qualification, sustained job or increase in earnings is an outcome that follows later and may depend on decisions outside the supplier's control. Promise the output when capacity is approved. Monitor the outcome at a stated interval, disclose loss to follow-up and avoid attributing the whole change to the contract without an evaluation design that supports that conclusion.
Claim boundary
Make the baseline and supplier contribution visible
Use the baseline required by the tender. It may be a contract workforce count, a current level of activity, a buyer minimum or zero contract-funded places before award. Name its date, entity and boundary. A company-wide total from last year cannot become the baseline for one regional contract without explanation. If there is no measured starting value, state the mobilization method and date for establishing it instead of inventing one.
Keep gross activity, additional activity and attributable effect separate. The supplier can report that it funded and delivered eight completed placements. It may also report how many participants later entered work. It should not claim that the contract caused every job unless the comparison and follow-up support that finding. The Magenta Book distinguishes operational monitoring from evaluation and explains why outcomes can have several influences. Use that distinction to set the strength of the tender statement.
Credit must also reconcile across organizations. If a college recruits participants, a charity provides coaching and the supplier funds placement supervision, record each contribution. Agree whether the buyer metric credits the combined activity once or assigns units by performer. Never let a prime and subcontractor both count the same participant, hour or outcome as separate contract value.
Worked case
Test an IT support skills promise before it reaches the bid
Consider a four-year regional IT support procurement that scores access to paid work experience for a buyer-defined cohort facing barriers to employment. The draft promise offers eight placements of twenty working days within the first two contract years. A place counts as completed after the participant attends at least eighteen days, including paid induction and supervised service tasks. Starts, completed places and early exits are reported separately. Later employment at three and six months is follow-up information, not a guaranteed result.
The workforce lead confirms the recruitment route with the buyer's named community partner. The service owner reserves two supervisors and defines tasks that do not expose live customer credentials or personal support tickets. Finance includes wages, equipment, access checks and supervisor time. If security clearance delays live access, the accepted design uses a segregated training environment and approved service simulations without lowering the paid duration or quality standard. Legal and data reviewers approve the limited reporting fields.
This is a worked design, not a recommended target. The bid team must test its own volumes, workforce plan, security model and buyer wording. A smaller promise with approved resources is stronger than a larger number that assumes unconfirmed referrals or spare operational capacity. Record the capacity evidence beside the offer so an ambitious edit cannot detach the target from the delivery basis.
| Test | Evidence before submission | Failure response |
|---|---|---|
| Participant route | Partner confirms eligible referral capacity | Reduce or phase the target before approval |
| Work content | Service owner approves safe supervised tasks | Use an approved training environment |
| People | Supervisors and HR dates are reserved | Move dates within the offered window |
| Cost | Wages, checks, devices and supervision are priced | Reconcile the commercial model |
| Evidence | Attendance and completion records have owners | Repair the process before promising the metric |
Response
Give the evaluator a method and the contract manager a promise
Open the response with the commitment in one bounded sentence. Follow it with the buyer need, delivery mechanism, cohort route, timetable, resources, measurement, governance and correction. Use the evaluation headings and word limit. Evidence should establish the proposed method and delivery capacity, not merely show that the company has supported similar causes before. Existing examples can demonstrate competence, but they are not the offered quantity.
Map the accepted promise into the implementation plan, price, resource schedule, subcontract and proposed KPI or performance schedule. Preserve the same unit and definition. A response that promises eight completed placements while the schedule tracks eight advertised places contains a material mismatch. State buyer dependencies beside the affected promise and describe what the supplier will do if they are delayed.
Only an authorized route can make the offer contractual. Submission does not by itself prove how every statement will be incorporated, and award does not settle document precedence. After contract finalization, the contract team must identify the controlling schedule, accepted changes, target, reporting recipient and remedy. Until then, use proposed and submitted status accurately.
Delivery control
Report delivery, shortfall and change under the accepted rule
At mobilization, transfer each confirmed obligation into a delivery register with its source, owner, performing parties, baseline, period, unit, evidence, reporting date and acceptance authority. Keep participant-level information in the approved system and give the buyer only the detail authorized by the contract and data rules. Reconcile partner submissions before the report is issued.
Report planned, started, completed and accepted values separately. Explain variance with evidence. A referral shortage, site closure or buyer access delay may justify recovery action, but it does not erase the original promise. Record the cause, owner, corrective step, forecast and decision. Change the commitment only through the contract's authorized mechanism, with a dated link from the old version to the new one.
Close the period with both delivery and learning. Confirm what was accepted, what remained unverified, what outcomes were observed and what should change in the next cycle. Do not turn a positive participant story into proof of the full target. The retained register should allow another reviewer to reproduce the reported count from the agreed evidence.
What good looks like
Useful outcomes from measurable social value tender commitments
- Each social value proposition is linked to the exact criterion, lot, policy edition, scoring method and contract destination.
- Mandatory delivery is separated from the extra value offered for evaluation.
- The beneficiary group, eligibility decision, location and access route are defined without inventing a buyer preference.
- Every numerical promise has a unit, quantity, period, completion rule and treatment for cancellations or duplicates.
- Outputs controlled by the supplier are separated from outcomes affected by other people and conditions.
- Supervision, partner capacity, safeguarding, access, cost and delivery time are approved before submission.
- The response, price, implementation plan, subcontract and draft contract carry compatible commitments.
- Contract reporting uses retained records that establish who delivered what and when without unnecessary personal data.
- Shortfalls trigger an owned recovery decision rather than retrospective changes to the counting rule.
Operating model
How to run the work
- 01
Fix the buyer requirement
Record the wording, definitions, lot, score, policy edition, publication date, mandatory minimum, response format and proposed contract route.
- 02
Classify the promise
Mark each proposition as required delivery, current capability, existing activity, additional offer, dependency or uncommitted outcome.
- 03
Define the beneficiary
Use the buyer's cohort and geography where supplied; otherwise describe the permitted identification and referral process without adding a restriction.
- 04
Write the counting rule
Set the unit, target, delivery window, completion threshold, evidence, duplicate treatment, exclusions and outcome follow-up.
- 05
Prove delivery capacity
Confirm budget, roles, supervisor time, sites, systems, partner authority, safeguarding and alternatives for known delivery constraints.
- 06
Approve the offer
Obtain workforce, delivery, commercial, legal, data and partner decisions at the strength of commitment being proposed.
- 07
Align response and contract
Use the same quantity, definition, owner, timing and evidence in the method statement, project plan, price and contractual schedule.
- 08
Control delivery evidence
Baseline the accepted promise after award, report under the agreed rule and record correction, buyer-approved change or unmet performance without rewriting history.
Evaluation
Questions that change the decision
- Which tender document, date and policy edition govern the social value response?
- Is the proposition a minimum condition, an award criterion, an offered enhancement or a reporting duty?
- What contract activity makes the commitment relevant to the purchase?
- Who qualifies as a beneficiary and who is authorized to confirm eligibility?
- What location or community definition does the buyer actually use?
- Which unit can be counted without relying on a future interpretation?
- When does one placement, hour, person, qualification or job count as complete?
- How are repeat participants, cancelled sessions and subcontractor activity treated?
- Which output can the supplier promise and which outcome can it only monitor?
- What staff time, cost, facilities, access and partner agreement support the target?
- Where will the commitment appear in the contract and who will accept the evidence?
- What recovery action is possible if referrals, demand or delivery fall below plan?
Failure modes
Where teams lose control
A corporate volunteering programme is presented as new value created by the contract.
A bidder adds a local residency restriction that the buyer did not publish.
A mandatory contract condition is relabelled as scored additional value.
Training places are counted when advertised rather than when attended or completed.
One participant is counted as several people across sessions without disclosure.
Hours delivered by a subcontractor are counted by both subcontractor and prime.
An employment outcome is guaranteed even though the participant and employer make later decisions.
An output target has no quality threshold, so token activity satisfies the number.
A partner is named before agreeing the cohort, volume, evidence or delivery period.
Supervision and paid participant time are absent from the cost model.
Sensitive beneficiary records are collected when aggregate evidence would meet the contract need.
The method statement, project plan and KPI schedule use different targets.
A missed target is hidden by changing the denominator or counting rule after delivery.
Measurement
Measure the finished job
Measure the completed workflow, including review effort and exceptions. Output volume on its own is not evidence of a better process.
- commitments with a controlling criterion, tender date and policy edition
- promises with an approved owner, funded resource and contract destination
- beneficiaries whose eligibility was confirmed through the agreed route
- places started, completed and withdrawn, reported as separate counts
- paid placement days or training hours completed under the stated quality rule
- unique people served, with repeat participation reported separately
- supplier and subcontractor contributions reconciled without duplicate credit
- outcomes followed at the agreed interval and labelled separately from outputs
- evidence records accepted by the contract manager on first review
- forecast shortfalls with an owner, cause, recovery action and decision date
Questions
Common questions
Can an existing corporate programme count as contract social value?
It may establish capability or form part of delivery if the tender permits it. State what is already funded and identify the contract-specific quantity, access or activity being offered. Do not present the whole corporate programme as additional contract value.
Should we promise jobs or training places?
Use the buyer's metric and promise only what the delivery owners can control. A supplier can often control funded places, supervised hours and completed training. A sustained job may depend on later vacancies and individual choices, so it may be better as a monitored outcome.
What is a suitable baseline for social value?
Use the baseline specified by the tender. Otherwise define the relevant contract, entity, location, population, measure and date. If the starting value is unknown, commit to an approved baseline exercise rather than inventing a figure.
Can subcontractor delivery be included in the target?
Yes when the tender permits it and the subcontractor has agreed the activity, evidence and timing. Reconcile the count once and retain the prime supplier's responsibility to the buyer.
How should repeat participants be counted?
Report unique people separately from sessions, hours or interventions. Follow the buyer's metric and state the repeat rule before delivery so several activities for one person do not imply several beneficiaries.
Does PPN 026 replace PPN 002 immediately?
No. PPN 026 states that covered procurements with tender notices published on or after 1 January 2027 should use the new model. Earlier Procurement Act procurements have a transition position. Check the tender notice date, scope and model named by the buyer.
What if a partner has not confirmed capacity before submission?
Do not write its contribution as committed. Obtain authority, reduce the target, use a separately approved delivery route or state the dependency where the procurement permits it.
Can the counting method change after award?
Only through the contract's authorized decision route. Preserve the original method, reason, approval date and effect on prior reports. Never change a denominator or completion rule merely to remove a shortfall.
Sources
Primary references
- PPN 026, the Social Value Model, including timing and contract monitoring UK Cabinet Office
- PPN 002 Social Value Model and standard reporting metrics UK Cabinet Office
- Guide to using the PPN 002 Social Value Model UK Cabinet Office
- Procurement Act 2023 guidance on key performance indicators UK Cabinet Office
- Procurement Act 2023, section 23, award criteria The National Archives
- Procurement Act 2023, section 52, contract performance indicators The National Archives
- Magenta Book guidance on outputs, outcomes, monitoring and attribution HM Treasury and Evaluation Task Force
- Social procurement resources and Buying Social guide European Commission
- Directive 2014/24/EU, Articles 67 and 70 EUR-Lex
- German Act against Restraints of Competition, section 127 German Federal Ministry of Justice and Federal Office of Justice
- German Act against Restraints of Competition, section 128 German Federal Ministry of Justice and Federal Office of Justice
- German Procurement Ordinance, section 58, award criteria German Federal Ministry of Justice and Federal Office of Justice
- German Procurement Ordinance, section 61, performance conditions German Federal Ministry of Justice and Federal Office of Justice
- Federal overview of sustainable public procurement in Germany German Federal Ministry for Economic Cooperation and Development
- French Public Procurement Code, Article L2112-2 Légifrance
- French Public Procurement Code, Article L2112-2-1, effective August 2026 Légifrance
- French Public Procurement Code, Article R2152-7, current criteria Légifrance
- French guide to social considerations in public procurement French Directorate for Legal Affairs
- French guide sheet 6 on social inclusion clauses French Directorate for Legal Affairs and OECP
- French guide sheet 7 on social inclusion performance criteria French Directorate for Legal Affairs and OECP
Ziva
Proposal software for source-grounded RFP, RFI, DDQ and questionnaire response work.
Bid, proposal, presales, security and compliance teams. Start with the workflow, constraints and evidence you already have.