Maintenance of an environmental facility
The anonymous printable bid notice supplies the scope, location, 45-day delivery period and PHP 800,000 approved budget; the accessible former-opportunity page had concealed these details.
Approved Budget for the Contract (tax basis not stated).
PhilGEPS official printable bid notice
Overview
PhilGEPS describes a 45-day, small-value procurement by National Power Corporation - Mindanao Generation to maintain the spill-boom system at Agus HE Plant in Lanao del Norte. The notice calls for a 3-ton manual hand winch and integration with the existing block, reinforcement of the boom-reel frame, heavy-duty marine-suitable ropes or cables, a reinforced foundation and anchor bolts with pull-out testing, and A-frame support work. The approved budget is PHP 800,000. The supervisor may also serve as safety officer if holding a valid BOSH or COSH certificate. The notice is closed; the printed cutoff was 14 October 2026 at 01:00, with no time zone stated.
Information based on the public notice
Ask about this tender
What the buyer needs
Maintenance of the environmental facility’s spill-boom deployment system at Agus HE Plant, including winch, rope/cable, anchor, foundation and frame work.
- The accessible former-opportunity page does not expose technical or participation requirements.
Tender details
- Buyer
- National Power Corporation - Mindanao Generation
- Country
Philippines
- Procedure
- Not stated in the notice
- Classification
- Environmental facility maintenance
- Notice reference
- 13280733 · 13280733 / MG-A7T26-056
- Location
- Agus HE Plant, Lanao del Norte
- Approved budget
- PHP 800,000; tax basis not stated
- Delivery period
- 45 days
- Procurement mode
- Negotiated procurement, small-value procurement under Sec. 34
- Closing
- 14 October 2026, 01:00; time zone not stated
What to check in the tender documents
- The notice does not report an award result or a delivery period.
Original notice
Read the original description
MAINTENANCE OF ENVIRONMENTAL FACILITY
Official source: PhilGEPS official printable bid notice ↗
Notice updates
October 16, 2026 · Version 3
Contract period updated · Deadline information updated · Summary and analysis updated · Tender facts updated · Original notice updated · Deadline updated · Location updated · Source updated · Source references updated · Notice update added
MAINTENANCE OF ENVIRONMENTAL FACILITY
Bid Notice Abstract Invitation to Bid (ITB) Reference Number 13280733 Procuring Entity NATIONAL POWER CORPORATION - MINDANAO GENERATION Title MAINTENANCE OF ENVIRONMENTAL FACILITY Area of Delivery Lanao Del Norte Solicitation Number: MG-A7T26-056 Trade Agreement: Implementing Rules and Regulations Procurement Mode: Negotiated Procurement - Small Value Procurement (Sec. 34) Classification: Goods Category: Environmental Health/Safety Equipment Approved Budget for the Contract: PHP 800,000.00 Delivery Period: 45 Day/s Client Agency: Status Closed Associated Components 1 Bid Supplements 0 Document Request List 1 Date Published 10/10/2026 Last Updated / Time 10/10/2026 00:00 AM Closing Date / Time 14/10/2026 01:00 AM Description SCOPE OF WORKS: THE WINNING BIDDER SHALL PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, TOOLS, TRANSPORTATION, SUPERVISION, PERMITS (IF APPLICABLE) AND OTHER INCINDENTIALS NECESSARY TO COMPLETE THE PROJECT, INCLUDING BUT NOT LIMITED TO THE FOLLOWING: MOBILIZATION AND SITE PREPARATION * DELIVERY OF EQUIPMENT, MATERIALS, TOOLS, AND CONSUMABLE ITEMS AT AGUS HE PLANT. * CONDUCT TOOL BOX MEETING WITH THE AGUS 6/7 HEP SAFETY OFFICER AND MAINTENANCE PERSONEL FOR THE SAFETY PROTOCOL AND OTHER CONCERNS. * SECURE WORK PERMITS TO THE SAFETY OFFICER AND CHIEF SECURITY OFFICER OF AGUS 6/7 HEPC BEFORE PROCEED. 1. MECHANICAL LIFTING & SYSTEMS A. SUPPLY AND INSTALL 3 TONS OF MANUAL HAND WINCH TO AUTOMATE THE INSTALLATION/LAYING OF SPILL BOOM ACROSS TAIL RACE, WATER WAYS B. INTERGRATE THE HANDWINCH WITH THE EXISTING CONCRETE BLOCK. C. REINFORCEMENT OF THE FRAME HOLDING BOOM REEL TO WITHSTAND THE DRAG INDUCED BY WATER CURRENT. 2. ROPE AND CABLE INSTALLATION A. SUPPLY AND INSTALL NEW HEAVY-DUTY WIRE ROPES OR STAINLESS CABLES SUITABLE FOR MARINE ENVIRONMENTS B. ENSURE PROPER WINDING ON THE REEL TO PREVENT OVERLAPPING OR JAMMING. 3. FOUNDATION FOR CABLE CONNECTOR A. EXCAVATE AND POUR A REINFORCED CONCRETE FOUNDATION TO SUPPORT A FIXED CABLE CONNECTOR OR ANCHOR B. ENSURE THE FOUNDATION IS DESIGNED TO WITHSTAND THE MAXIMUM TENSION OF THE BOOM DURING DEPLOMENT IS STRONG CURRENTS. 4. ANCHOR BOLT INSTALLATION A. INSTALL HEAVY- DUTY CHEMICAL OR MECHANICAL ANCHOR BOLTS TO SECURE THE REEL FRAME EXISTING FLOOR B. PERFORM PULL-OUT TEST TO VERIFY ANCHOR INTEGRITY. 5. FABRICATION & METAL WORKS FRAME REINFORCEMENT A. FABRICATE AND WELD ADDITIONAL SUPPORT STRUTS FOR THE A-FRAME TO ACCOMMODATE THE NEW MOTORIZED COMPONENTS. 6. FINAL INSPECTION A. CONDUCT A FINAL INSPECTION TO ENSURE ALL WORK IS COMPLETED TO THE REQUIRED STANDARDS AND IS FREE TO DEFECTS 7. MANPOWER REQUIREMENTS * THE PROJECT SUPERVISOR MAY ALSO SERVE AS THE SAFETY OFFICER, PROVIDED THE HE/SHE POSSESSES A VALID BOSH OR COSH * CERTIFICATE AND PERFORMS ALL DUTIES AND RESPONSIBILITIES REQUIRED OF SAFETY OFFICER UNDER APPLICABLE OCCUPATIONAL SAFETY AND HEALTH REGULATIONS Other Information SITE INSPECTION
October 16, 2026 · Version 2
Buyer updated · Classification updated · Deadline information updated · Summary and analysis updated · Tender facts updated · Original notice updated · Deadline updated · Source updated · Source notice details updated · Status changed · Notice update added
MAINTENANCE OF ENVIRONMENTAL FACILITY
MAINTENANCE OF ENVIRONMENTAL FACILITY
October 12, 2026 · Version 1
Published
MAINTENANCE OF ENVIRONMENTAL FACILITY
Bid Notice Abstract Invitation to Bid (ITB) Reference Number 13280733 Procuring Entity NATIONAL POWER CORPORATION - MINDANAO GENERATION Title MAINTENANCE OF ENVIRONMENTAL FACILITY Area of Delivery Lanao Del Norte Solicitation Number: MG-A7T26-056 Trade Agreement: Implementing Rules and Regulations Procurement Mode: Negotiated Procurement - Small Value Procurement (Sec. 34) Classification: Goods Category: Environmental Health/Safety Equipment Approved Budget for the Contract: PHP 800,000.00 Delivery Period: 45 Day/s Status Active Associated Components Order Bid Supplements 0 Document Request List 1 Date Published 10/10/2026 Last Updated / Time 10/10/2026 12:00 AM Closing Date / Time 14/10/2026 1:00 AM Description SCOPE OF WORKS: THE WINNING BIDDER SHALL PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, TOOLS, TRANSPORTATION, SUPERVISION, PERMITS (IF APPLICABLE) AND OTHER INCINDENTIALS NECESSARY TO COMPLETE THE PROJECT, INCLUDING BUT NOT LIMITED TO THE FOLLOWING: MOBILIZATION AND SITE PREPARATION * DELIVERY OF EQUIPMENT, MATERIALS, TOOLS, AND CONSUMABLE ITEMS AT AGUS HE PLANT. * CONDUCT TOOL BOX MEETING WITH THE AGUS 6/7 HEP SAFETY OFFICER AND MAINTENANCE PERSONEL FOR THE SAFETY PROTOCOL AND OTHER CONCERNS. * SECURE WORK PERMITS TO THE SAFETY OFFICER AND CHIEF SECURITY OFFICER OF AGUS 6/7 HEPC BEFORE PROCEED. 1. MECHANICAL LIFTING & SYSTEMS A. SUPPLY AND INSTALL 3 TONS OF MANUAL HAND WINCH TO AUTOMATE THE INSTALLATION/LAYING OF SPILL BOOM ACROSS TAIL RACE, WATER WAYS B. INTERGRATE THE HANDWINCH WITH THE EXISTING CONCRETE BLOCK. C. REINFORCEMENT OF THE FRAME HOLDING BOOM REEL TO WITHSTAND THE DRAG INDUCED BY WATER CURRENT. 2. ROPE AND CABLE INSTALLATION A. SUPPLY AND INSTALL NEW HEAVY-DUTY WIRE ROPES OR STAINLESS CABLES SUITABLE FOR MARINE ENVIRONMENTS B. ENSURE PROPER WINDING ON THE REEL TO PREVENT OVERLAPPING OR JAMMING. 3. FOUNDATION FOR CABLE CONNECTOR A. EXCAVATE AND POUR A REINFORCED CONCRETE FOUNDATION TO SUPPORT A FIXED CABLE CONNECTOR OR ANCHOR B. ENSURE THE FOUNDATION IS DESIGNED TO WITHSTAND THE MAXIMUM TENSION OF THE BOOM DURING DEPLOMENT IS STRONG CURRENTS. 4. ANCHOR BOLT INSTALLATION A. INSTALL HEAVY- DUTY CHEMICAL OR MECHANICAL ANCHOR BOLTS TO SECURE THE REEL FRAME EXISTING FLOOR B. PERFORM PULL-OUT TEST TO VERIFY ANCHOR INTEGRITY. 5. FABRICATION & METAL WORKS FRAME REINFORCEMENT A. FABRICATE AND WELD ADDITIONAL SUPPORT STRUTS FOR THE A-FRAME TO ACCOMMODATE THE NEW MOTORIZED COMPONENTS. 6. FINAL INSPECTION A. CONDUCT A FINAL INSPECTION TO ENSURE ALL WORK IS COMPLETED TO THE REQUIRED STANDARDS AND IS FREE TO DEFECTS 7. MANPOWER REQUIREMENTS * THE PROJECT SUPERVISOR MAY ALSO SERVE AS THE SAFETY OFFICER, PROVIDED THE HE/SHE POSSESSES A VALID BOSH OR COSH * CERTIFICATE AND PERFORMS ALL DUTIES AND RESPONSIBILITIES REQUIRED OF SAFETY OFFICER UNDER APPLICABLE OCCUPATIONAL SAFETY AND HEALTH REGULATIONS Other Information SITE INSPECTION
https://notices.philgeps.gov.ph/GEPSNONPILOT/Tender/SplashBidNoticeAbstractUI.aspx?menuIndex=3&refID=13280733&DirectFrom=OpenOpp&Type=category&BusCatID=74
Source retrieved: 2026-10-16T05:30:23.078701Z