title: "ROKS TP7: Turbine lot"
canonical: "https://zephior.com/tenders/7d0e3ba6-7d98-40e3-af42-e53747b9d720/ova-spin-roks-tp7-turbine-overhaul"
last-updated: "2026-10-11T16:15:51.109506+00:00"
language: "en"
---

[Tenders](https://zephior.com/tenders) › [Switzerland](https://zephior.com/tenders/countries/ch) › [Engadiner Kraftwerke AG](https://zephior.com/tenders/buyers/engadiner-kraftwerke-ag)

# ROKS TP7: Turbine lot

Engadiner Kraftwerke AG · Switzerland · Open

- **Buyer:** Engadiner Kraftwerke AG
- **Place:** Switzerland
- **Submission deadline:** December 14, 2026 at 1:00 PM UTC
- **Contract value:** Not stated in the notice
- **Contract period:** 2027-10-11 to 2028-05-12
- **Published:** October 7, 2026

## Overview

Engadiner Kraftwerke AG is tendering the complete overhaul of the horizontal Francis dosing turbine at the Ova Spin plant. Work includes renewing corrosion protection, reusing the existing spare runner and guide vanes, removing and disposing of PCB-containing coatings, replacing old instrumentation, and possibly installing a bearing-oil heat exchanger. Generator overhaul is explicitly outside this lot. The execution period is 11 October 2027 to 12 May 2028. Bids must be submitted both electronically through SIMAP and in one paper copy. The deadline is 14 December 2026 at 14:00 CET.

Information based on the public notice

## What the buyer needs

Complete turbine overhaul, with the generator overhaul excluded and tendered separately; 500 kW horizontal Francis turbine.

- Submit documents electronically through SIMAP and provide one paper copy. Questions must be submitted in writing through SIMAP by 27 November 2026.

## Tender details

- Buyer: Engadiner Kraftwerke AG
- Country: Switzerland
- Procedure: open
- Classification: Hydraulic turbines · CPV 42112200
- Notice reference: 45150 · 45150-01 · 45150, 45150-01
- Official submission deadline: 14 Dec 2026, 14:00 CET
- Execution period: 2027-10-11 to 2028-05-12

## What to check in the tender documents

- Detailed qualification and award criteria are in the tender documents.

[Get started with Ziva](https://agent.zephior.ai/onboarding/initiate)

## Original notice

**ROKS TP7: Los Turbine**

Im Rahmen des Projekts "ROKS- TP7 Dotierkraftwerk Ova Spin" wird die Dotieranlage, bestehend aus einer Maschinengruppe mit Turbine, Generator, Kugelschieber, Leitungssystem und Steuerungseinheiten aus der Erstausrüstung von 1968, nach über 50 Betriebsjahren total revidiert.
Zweck der vorgesehenen Totalrevision der Dotierturbine ist es, diese Maschine auf den heutigen Stand der Technik und mechanisch wieder in einen einwandfreien Zustand zu bringen.
Die Dotierturbine wurde letztes Mal 2002 teilrevidiert.
Dabei sind zusammenfassend die folgenden wichtigsten Arbeiten vorgesehen:
- Totalüberholung des vorhandenen Generators. Dieser Punkt ist nicht Bestandteil dieser Aus­schreibung, sondern wird als separates Los ausgeschrieben
- Total-Revision der Turbine mit komplett Erneuerung des Korrosionsschutzes
- Verwendung des vorhandenen Ersatzlaufrades und der Ersatzleitschaufeln sowie weitere vorhandener Ersatzteile
- Entfernung und Entsorgung PCB haltiger Anstriche
- Eventuell neuer Lagerölwärmetauscher für das Turbinenführungslager
- Ersatz der alten Instrumentierung
Technische Daten zur Dotierturbine:
Francisturbine horizontal
Fabrikat/Typ: Bell
Wassermenge: 0.9 m³/s
Fallhöhe: 57.64 m
Leistung: 500 kW
Inbetriebnahme: Dezember 1968
Letzte Revision: 2002
Drehzahl: 750 U/min

Siehe Ausschreibungsunterlagen. Die Unterlagen sind elektronisch auf SIMAP und 1x auf Papier einzureichen.

- Official source: [simap](https://www.simap.ch/de/project-detail/ab03f175-e76c-4b87-890e-9f4b4fd4d3dc)

## Notice updates

### October 11, 2026 · Version 2 (Contract period updated, Summary and analysis updated, Tender facts updated, Original notice updated, Source references updated)

ROKS TP7: Los Turbine

Im Rahmen des Projekts "ROKS- TP7 Dotierkraftwerk Ova Spin" wird die Dotieranlage, bestehend aus einer Maschinengruppe mit Turbine, Generator, Kugelschieber, Leitungssystem und Steuerungseinheiten aus der Erstausrüstung von 1968, nach über 50 Betriebsjahren total revidiert.
Zweck der vorgesehenen Totalrevision der Dotierturbine ist es, diese Maschine auf den heutigen Stand der Technik und mechanisch wieder in einen einwandfreien Zustand zu bringen.
Die Dotierturbine wurde letztes Mal 2002 teilrevidiert.
Dabei sind zusammenfassend die folgenden wichtigsten Arbeiten vorgesehen:
- Totalüberholung des vorhandenen Generators. Dieser Punkt ist nicht Bestandteil dieser Aus­schreibung, sondern wird als separates Los ausgeschrieben
- Total-Revision der Turbine mit komplett Erneuerung des Korrosionsschutzes
- Verwendung des vorhandenen Ersatzlaufrades und der Ersatzleitschaufeln sowie weitere vorhandener Ersatzteile
- Entfernung und Entsorgung PCB haltiger Anstriche
- Eventuell neuer Lagerölwärmetauscher für das Turbinenführungslager
- Ersatz der alten Instrumentierung
Technische Daten zur Dotierturbine:
Francisturbine horizontal
Fabrikat/Typ: Bell
Wassermenge: 0.9 m³/s
Fallhöhe: 57.64 m
Leistung: 500 kW
Inbetriebnahme: Dezember 1968
Letzte Revision: 2002
Drehzahl: 750 U/min

Siehe Ausschreibungsunterlagen. Die Unterlagen sind elektronisch auf SIMAP und 1x auf Papier einzureichen.

### October 11, 2026 · Version 1 (Published)

ROKS TP7: Los Turbine

Im Rahmen des Projekts "ROKS- TP7 Dotierkraftwerk Ova Spin" wird die Dotieranlage, bestehend aus einer Maschinengruppe mit Turbine, Generator, Kugelschieber, Leitungssystem und Steuerungseinheiten aus der Erstausrüstung von 1968, nach über 50 Betriebsjahren total revidiert. Zweck der vorgesehenen Totalrevision der Dotierturbine ist es, diese Maschine auf den heutigen Stand der Technik und mechanisch wieder in einen einwandfreien Zustand zu bringen. Die Dotierturbine wurde letztes Mal 2002 teilrevidiert. Dabei sind zusammenfassend die folgenden wichtigsten Arbeiten vorgesehen: - Totalüberholung des vorhandenen Generators. Dieser Punkt ist nicht Bestandteil dieser Aus­schreibung, sondern wird als separates Los ausgeschrieben - Total-Revision der Turbine mit komplett Erneuerung des Korrosionsschutzes - Verwendung des vorhandenen Ersatzlaufrades und der Ersatzleitschaufeln sowie weitere vorhandener Ersatzteile - Entfernung und Entsorgung PCB haltiger Anstriche - Eventuell neuer Lagerölwärmetauscher für das Turbinenführungslager - Ersatz der alten Instrumentierung Technische Daten zur Dotierturbine: Francisturbine horizontal Fabrikat/Typ: Bell Wassermenge: 0.9 m³/s Fallhöhe: 57.64 m Leistung: 500 kW Inbetriebnahme: Dezember 1968 Letzte Revision: 2002 Drehzahl: 750 U/min

## Turn this opportunity into a response.

Analyze the tender documents and build your response with Ziva.

- Understand the requirements
- Find the evidence you need
- Prepare your response

[Get started with Ziva](https://agent.zephior.ai/onboarding/initiate) · [View official notice](https://www.simap.ch/de/project-detail/ab03f175-e76c-4b87-890e-9f4b4fd4d3dc)

## About this notice

- Official source: simap
- Source retrieved: October 11, 2026
- Page updated: October 11, 2026
- Notice reference: 45150 · 45150-01

## Open tenders from Engadiner Kraftwerke AG

- [Hydraulic control systems for the Pradella power station](https://zephior.com/tenders/33e16633-3542-400c-a350-7cec3b531323/pradella-hydraulic-control-and-distribution-systems) ([Markdown](https://zephior.com/tenders/33e16633-3542-400c-a350-7cec3b531323/pradella-hydraulic-control-and-distribution-systems.md)), Engadiner Kraftwerke AG
- [Relocation of the north low-voltage distribution equipment at Munt la Schera tunnel](https://zephior.com/tenders/b53badda-e164-409c-94db-82266408e766/relocation-of-the-north-low-voltage-distribution-equipment-at-munt-la-schera-tunnel) ([Markdown](https://zephior.com/tenders/b53badda-e164-409c-94db-82266408e766/relocation-of-the-north-low-voltage-distribution-equipment-at-munt-la-schera-tunnel.md)), Engadiner Kraftwerke AG
- [Hydraulic control and distribution systems for Pradella power station, lot 1](https://zephior.com/tenders/e8a7d7cd-ee89-49d2-ae4b-2d95798c7a4e/hydraulic-control-renewal-at-pradella-power-station-lot-1) ([Markdown](https://zephior.com/tenders/e8a7d7cd-ee89-49d2-ae4b-2d95798c7a4e/hydraulic-control-renewal-at-pradella-power-station-lot-1.md)), Engadiner Kraftwerke AG

## Similar tenders

- [COSAHL orientation school: composite screeds](https://zephior.com/tenders/49a2c5e3-eeaa-498d-85fc-e1645d661f23/cosahl-school-screeds-composite-underlayers) ([Markdown](https://zephior.com/tenders/49a2c5e3-eeaa-498d-85fc-e1645d661f23/cosahl-school-screeds-composite-underlayers.md)), COSAHL - Association du cycle d’orientation de la Sarine-Campagne et du Haut-Lac français
- [Bremgarten community centre: pollutant remediation](https://zephior.com/tenders/53c7c9f6-b244-4b92-ab66-af3245385e6d/bremgarten-community-centre-pollutant-remediation) ([Markdown](https://zephior.com/tenders/53c7c9f6-b244-4b92-ab66-af3245385e6d/bremgarten-community-centre-pollutant-remediation.md)), Einwohnergemeinde Bremgarten b. Bern
- [Four-year HVAC maintenance in District VII](https://zephior.com/tenders/5b1d4e14-b118-498e-a002-e9038c5806d8/maintenance-of-district-vii-fb8-hvac-systems) ([Markdown](https://zephior.com/tenders/5b1d4e14-b118-498e-a002-e9038c5806d8/maintenance-of-district-vii-fb8-hvac-systems.md)), Tiefbauamt, Abt. Gebietseinheit VII
- [Klinikum 2: operating and examination lights](https://zephior.com/tenders/5f0b21a7-ee20-4938-9740-1e880ebf8e65/operating-room-and-examination-lights-for-the-new-klinikum-2-building-phase-1) ([Markdown](https://zephior.com/tenders/5f0b21a7-ee20-4938-9740-1e880ebf8e65/operating-room-and-examination-lights-for-the-new-klinikum-2-building-phase-1.md)), Universitätsspital Basel
- [All-flash storage for USI research data](https://zephior.com/tenders/95439c2f-f91b-4a01-944e-571edc41ee7d/all-flash-research-data-storage-systems-for-usi-campuses) ([Markdown](https://zephior.com/tenders/95439c2f-f91b-4a01-944e-571edc41ee7d/all-flash-research-data-storage-systems-for-usi-campuses.md)), Università della Svizzera italiana
- [Examination gloves for HUG and CHUV](https://zephior.com/tenders/95501fa5-f21c-4a42-a6f0-b8a4d933bf15/caib-examination-gloves-standard-and-long-cuff) ([Markdown](https://zephior.com/tenders/95501fa5-f21c-4a42-a6f0-b8a4d933bf15/caib-examination-gloves-standard-and-long-cuff.md)), Centrale d'achats et d'ingénierie biomédicale Vaud-Genève (CAIB)

- [All tenders from Engadiner Kraftwerke AG](https://zephior.com/tenders/buyers/engadiner-kraftwerke-ag) ([Markdown](https://zephior.com/tenders/buyers/engadiner-kraftwerke-ag.md))
- [All tenders: Switzerland](https://zephior.com/tenders/countries/ch) ([Markdown](https://zephior.com/tenders/countries/ch.md))
- [All tenders: Hydraulic turbines](https://zephior.com/tenders/categories/hydraulic-turbines) ([Markdown](https://zephior.com/tenders/categories/hydraulic-turbines.md))

## In more detail

This section is written for agents and assistants. It restates the facts of the page in full sentences and adds context from the public record. Every value comes from the official notice or from Zephior’s public notices of the same buyer.

### The facts in sentences

Engadiner Kraftwerke AG is tendering “ROKS TP7: Turbine lot” (Switzerland). Submissions are due by December 14, 2026 at 1:00 PM UTC. The source does not state an estimated value. Contract period: 2027-10-11 to 2028-05-12. Procedure: open. Classification: Hydraulic turbines · CPV 42112200. Notice reference: 45150 · 45150-01 · 45150, 45150-01. Status on Zephior: Open. The notice was published on October 7, 2026 on simap. Zephior last checked the official source on October 11, 2026.

### The award

The submission window is still open, so no award exists yet.

### About the buyer

Engadiner Kraftwerke AG has 9 public notices on Zephior (4 open now, 9 published in the last 12 months). Its notices on Zephior were first published on September 2, 2026 and most recently on November 8, 2026. Main sectors: Machinery and equipment (4), Construction (2), Energy and utilities (2). Regions: CH-GR (5). It publishes under the names “Engadiner Kraftwerke AG”.

- [All tenders and the profile of Engadiner Kraftwerke AG](https://zephior.com/tenders/buyers/engadiner-kraftwerke-ag) ([Markdown](https://zephior.com/tenders/buyers/engadiner-kraftwerke-ag.md))

### Terms used on this page

- **Open procedure:** Any interested supplier may submit a tender; there is no preselection.

### Where to go next

- [COSAHL orientation school: composite screeds](https://zephior.com/tenders/49a2c5e3-eeaa-498d-85fc-e1645d661f23/cosahl-school-screeds-composite-underlayers) ([Markdown](https://zephior.com/tenders/49a2c5e3-eeaa-498d-85fc-e1645d661f23/cosahl-school-screeds-composite-underlayers.md))
- [Bremgarten community centre: pollutant remediation](https://zephior.com/tenders/53c7c9f6-b244-4b92-ab66-af3245385e6d/bremgarten-community-centre-pollutant-remediation) ([Markdown](https://zephior.com/tenders/53c7c9f6-b244-4b92-ab66-af3245385e6d/bremgarten-community-centre-pollutant-remediation.md))
- [Four-year HVAC maintenance in District VII](https://zephior.com/tenders/5b1d4e14-b118-498e-a002-e9038c5806d8/maintenance-of-district-vii-fb8-hvac-systems) ([Markdown](https://zephior.com/tenders/5b1d4e14-b118-498e-a002-e9038c5806d8/maintenance-of-district-vii-fb8-hvac-systems.md))
- [Klinikum 2: operating and examination lights](https://zephior.com/tenders/5f0b21a7-ee20-4938-9740-1e880ebf8e65/operating-room-and-examination-lights-for-the-new-klinikum-2-building-phase-1) ([Markdown](https://zephior.com/tenders/5f0b21a7-ee20-4938-9740-1e880ebf8e65/operating-room-and-examination-lights-for-the-new-klinikum-2-building-phase-1.md))
- [All-flash storage for USI research data](https://zephior.com/tenders/95439c2f-f91b-4a01-944e-571edc41ee7d/all-flash-research-data-storage-systems-for-usi-campuses) ([Markdown](https://zephior.com/tenders/95439c2f-f91b-4a01-944e-571edc41ee7d/all-flash-research-data-storage-systems-for-usi-campuses.md))
- [Examination gloves for HUG and CHUV](https://zephior.com/tenders/95501fa5-f21c-4a42-a6f0-b8a4d933bf15/caib-examination-gloves-standard-and-long-cuff) ([Markdown](https://zephior.com/tenders/95501fa5-f21c-4a42-a6f0-b8a4d933bf15/caib-examination-gloves-standard-and-long-cuff.md))
- [Hydraulic control systems for the Pradella power station](https://zephior.com/tenders/33e16633-3542-400c-a350-7cec3b531323/pradella-hydraulic-control-and-distribution-systems) ([Markdown](https://zephior.com/tenders/33e16633-3542-400c-a350-7cec3b531323/pradella-hydraulic-control-and-distribution-systems.md))
- [Relocation of the north low-voltage distribution equipment at Munt la Schera tunnel](https://zephior.com/tenders/b53badda-e164-409c-94db-82266408e766/relocation-of-the-north-low-voltage-distribution-equipment-at-munt-la-schera-tunnel) ([Markdown](https://zephior.com/tenders/b53badda-e164-409c-94db-82266408e766/relocation-of-the-north-low-voltage-distribution-equipment-at-munt-la-schera-tunnel.md))
- [Hydraulic control and distribution systems for Pradella power station, lot 1](https://zephior.com/tenders/e8a7d7cd-ee89-49d2-ae4b-2d95798c7a4e/hydraulic-control-renewal-at-pradella-power-station-lot-1) ([Markdown](https://zephior.com/tenders/e8a7d7cd-ee89-49d2-ae4b-2d95798c7a4e/hydraulic-control-renewal-at-pradella-power-station-lot-1.md))
- [All tenders from Engadiner Kraftwerke AG](https://zephior.com/tenders/buyers/engadiner-kraftwerke-ag) ([Markdown](https://zephior.com/tenders/buyers/engadiner-kraftwerke-ag.md))
- [All tenders: Switzerland](https://zephior.com/tenders/countries/ch) ([Markdown](https://zephior.com/tenders/countries/ch.md))
- [All tenders: Hydraulic turbines](https://zephior.com/tenders/categories/hydraulic-turbines) ([Markdown](https://zephior.com/tenders/categories/hydraulic-turbines.md))

### Source-backed public record

```json
{
  "id": "7d0e3ba6-7d98-40e3-af42-e53747b9d720",
  "revision": 2,
  "modifiedAt": "2026-10-11T16:15:51.109506+00:00",
  "url": "https://zephior.com/tenders/7d0e3ba6-7d98-40e3-af42-e53747b9d720/ova-spin-roks-tp7-turbine-overhaul",
  "status": "open",
  "recordedStatus": "open",
  "buyer": {
    "id": "engadiner-kraftwerke-ag",
    "name": "Engadiner Kraftwerke AG"
  },
  "category": {
    "de": "Wasserturbinen",
    "en": "Hydraulic turbines",
    "fr": "Turbines hydrauliques",
    "id": "hydraulic-turbines"
  },
  "deadline": {
    "at": "2026-12-14T13:00:00+00:00",
    "date": null
  },
  "award": null,
  "estimatedValue": null,
  "contractPeriod": "2027-10-11 to 2028-05-12",
  "region": null,
  "originalSource": {
    "url": "https://www.simap.ch/de/project-detail/ab03f175-e76c-4b87-890e-9f4b4fd4d3dc",
    "title": "ROKS TP7: Los Turbine",
    "issuer": "Engadiner Kraftwerke AG",
    "status": "open",
    "language": "de",
    "location": "CH",
    "deadline_at": "2026-12-14T13:00:00+00:00",
    "description": "Im Rahmen des Projekts \"ROKS- TP7 Dotierkraftwerk Ova Spin\" wird die Dotieranlage, bestehend aus einer Maschinengruppe mit Turbine, Generator, Kugelschieber, Leitungssystem und Steuerungseinheiten aus der Erstausrüstung von 1968, nach über 50 Betriebsjahren total revidiert. Zweck der vorgesehenen Totalrevision der Dotierturbine ist es, diese Maschine auf den heutigen Stand der Technik und mechanisch wieder in einen einwandfreien Zustand zu bringen. Die Dotierturbine wurde letztes Mal 2002 teilrevidiert. Dabei sind zusammenfassend die folgenden wichtigsten Arbeiten vorgesehen: - Totalüberholung des vorhandenen Generators. Dieser Punkt ist nicht Bestandteil dieser Aus­schreibung, sondern wird als separates Los ausgeschrieben - Total-Revision der Turbine mit komplett Erneuerung des Korrosionsschutzes - Verwendung des vorhandenen Ersatzlaufrades und der Ersatzleitschaufeln sowie weitere vorhandener Ersatzteile - Entfernung und Entsorgung PCB haltiger Anstriche - Eventuell neuer Lagerölwärmetauscher für das Turbinenführungslager - Ersatz der alten Instrumentierung Technische Daten zur Dotierturbine: Francisturbine horizontal Fabrikat/Typ: Bell Wassermenge: 0.9 m³/s Fallhöhe: 57.64 m Leistung: 500 kW Inbetriebnahme: Dezember 1968 Letzte Revision: 2002 Drehzahl: 750 U/min",
    "country_code": "CH",
    "published_at": "2026-10-07T22:00:00+00:00",
    "contract_type": "supply",
    "deadline_date": null,
    "procedure_type": "open",
    "reference_numbers": [
      "45150",
      "45150-01"
    ],
    "classification_codes": [
      {
        "code": "42112200",
        "system": "CPV",
        "provenance": "source_declared"
      }
    ]
  },
  "sources": [
    {
      "ref": "canonical_snapshot",
      "url": "https://www.simap.ch/de/project-detail/ab03f175-e76c-4b87-890e-9f4b4fd4d3dc",
      "kind": "canonical_snapshot",
      "retrieved_at": "2026-10-11T16:06:39Z"
    },
    {
      "ref": "official_notice_html",
      "url": "https://www.simap.ch/de/project-detail/ab03f175-e76c-4b87-890e-9f4b4fd4d3dc",
      "kind": "official_notice_html",
      "retrieved_at": "2026-10-11T16:06:39Z"
    },
    {
      "ref": "official_notice_api",
      "url": "https://www.simap.ch/api/publications/v1/project/ab03f175-e76c-4b87-890e-9f4b4fd4d3dc/publication-details/530f3d0c-243f-40b6-9c3b-97f6b89892d0",
      "kind": "official_notice_api",
      "retrieved_at": "2026-10-11T16:15:04Z"
    }
  ],
  "keyFacts": [
    {
      "label": "Reference",
      "value": "45150, 45150-01",
      "source_ref": "canonical_snapshot#/reference_numbers"
    },
    {
      "label": "Official submission deadline",
      "value": "14 Dec 2026, 14:00 CET",
      "source_ref": "official_notice_api#dates.offerDeadline"
    },
    {
      "label": "Execution period",
      "value": "2027-10-11 to 2028-05-12",
      "source_ref": "official_notice_api#procurement.executionPeriod"
    }
  ],
  "noticeFacts": {
    "lots": [],
    "schedule": [
      {
        "event": "Questions deadline",
        "value": "2026-11-27",
        "source_ref": "official_notice_api#dates"
      },
      {
        "event": "Answers published by",
        "value": "2026-12-04",
        "source_ref": "official_notice_api#dates"
      },
      {
        "event": "Public offer opening",
        "value": "2026-12-15T08:00:00+01:00",
        "source_ref": "official_notice_api#dates"
      }
    ],
    "requirements": [
      {
        "text": "Elektronische Einreichung über SIMAP und ein Papierexemplar sind erforderlich.",
        "source_ref": "official_notice_api#terms+project-info.offerSpecificNote"
      },
      {
        "text": "Die Generatorrevision ist nicht Bestandteil dieses Loses.",
        "source_ref": "official_notice_api#terms+project-info.offerSpecificNote"
      }
    ],
    "award_criteria": [
      {
        "text": "The generator overhaul is not part of this lot and is tendered separately.",
        "source_ref": "canonical_snapshot#/description"
      }
    ],
    "estimated_value": null
  },
  "historyTotal": 2
}
```