[Tenders](https://zephior.com/tenders) › [Switzerland](https://zephior.com/tenders/countries/ch) › [St. Gallen](https://zephior.com/tenders/countries/ch/regions/sg) › [Politische Gemeinde Goldach, vertreten durch die Technischen Betriebe Goldach](https://zephior.com/tenders/buyers/politische-gemeinde-goldach-vertreten-durch-die-technischen-betriebe-goldach)

# Goldach energy network distribution grid, general planner mandate

Politische Gemeinde Goldach, represented by Technische Betriebe Goldach · Switzerland · Open

- **Buyer:** Politische Gemeinde Goldach, represented by Technische Betriebe Goldach
- **Place:** Goldach, canton of St. Gallen
- **Offer deadline:** December 23, 2026 at 10:59 PM UTC
- **Contract value:** Not stated in the notice
- **Contract period:** The contract runs from 1 April 2027 to 31 December 2030.
- **Published:** November 11, 2026

## Overview

The municipality of Goldach, through its technical utilities, is seeking a general planner for the distribution network of a lake-water district energy network. The network draws on the new Riet II lake-water intake of the Regional Water Supply St. Gallen (RWSG) and uses large heat pumps to supply heating for households, public buildings and businesses, with a cooling network as an option. The basic contract covers SIA sub-phase 31 (preliminary design) for the distribution network. The option covers SIA sub-phases 32 to 53 for zone 1 and the cooling network. Three firms that prepared the preliminary design are admitted to the procedure as bidders. The offer deadline is 23 December 2026 at 23:59 CET (UTC+01:00).

Information based on the public notice

## What the buyer needs

General planner services for the distribution network of a lake-water district energy network in Goldach. The basic contract covers SIA sub-phase 31 (preliminary design) for the distribution network. The option covers SIA sub-phases 32 to 53 for zone 1 and the cooling network. Services include overall management and coordination, civil engineering, pipeline construction and private connections.

- Qualification EK 1.1 to EK 1.4 requires a project reference for each area (overall coordination, civil engineering, heat and cooling pipeline construction, house connections) covering SIA sub-phases 31 to 53, completed or largely implemented, within the last 10 years.
- Qualification EK 2: the annual contract volume must not exceed 30% of the annual turnover of the relevant business unit, supported by a declaration of turnover for the last three years.
- Qualification EK 3: organisational and financial capacity, supported by a signed self-declaration C1.
- Consortia are permitted. Subplanners are permitted, and the majority of services must be provided by the bidder.
- Offers are submitted in German, digitally through SIMAP.
- Three firms that prepared the preliminary design (HOLINGER AG, Contegra AG Integrale Planung and RKL AG) are admitted to the procedure as bidders under Art. 14 IVöB.

## Tender details

- Buyer: Politische Gemeinde Goldach, represented by Technische Betriebe Goldach
- Country: Switzerland
- Procedure: Open procedure
- Classification: Architecture and engineering services · CPV 71000000
- Notice reference: 47407 · 47407-01
- Offer deadline: 23 December 2026, 23:59 CET (UTC+01:00)
- Questions: Submitted through the SIMAP forum by 27 November 2026; answers by 4 December 2026
- Contract period: 1 April 2027 to 31 December 2030, with the option for zone 1 and the cooling network
- Fee basis: Total fee for the basic contract and options, including expenses and discount, excluding VAT
- Offer validity: Until 30 July 2027
- Payment: In Swiss francs, payment term 30 days
- Contact: Technische Betriebe Goldach, Marmorstrasse 3, 9403 Goldach; +41 58 228 78 78; https://tb-goldach.ch/
- Location: Goldach, canton of St. Gallen

## What to check in the tender documents

- The public notice does not state an estimated fee or budget, so the scale of the mandate cannot be judged from the notice.
- The notice does not give a fee estimate for the option, separate from the basic contract.

[Get started with Ziva](https://agent.zephior.ai/onboarding/initiate)

## Original notice

**Energieverbund Goldach: Verteilnetz**

Energieverbund Goldach: Verteilnetz

Die Regionale Wasserversorgung St.Gallen (RWSG) baut derzeit das neue Seewasserwerk Riet II. Im Zuge dieses Projekts bietet sich für die Gemeinde Goldach die Möglichkeit, die neue Seewasserfassung parallel zu nutzen und damit ein nachhaltiges Energiesystem für die Fernwärme und Fernkälte aufzubauen. Durch den Einsatz von Grosswärmepumpen kann Seewasser als erneuerbare Energiequelle genutzt werden, um umweltfreundliche Wärme für Haushalte, öffentliche Gebäude und Gewerbebetriebe bereitzustellen.
Das Projekt ist in zwei Teilprojekte unterteilt:
Teilprojekt 1 – Energiezentrale
Teilprojekt 2 – Verteilnetz
Der Grundauftrag umfasst die SIA-Teilphase 31 (Vorprojekt) - Verteilnetz.
Die Option umfasst die SIA-Teilphasen 32-53 für die Zone 1 und das Kältenetz.
Das Generalplanermandat umfasst folgende Leistungen resp. Fachbereiche:
- Gesamtleitung und Koordination
- Tiefbau
- Rohrleitungsbau
- Hausanschlüsse

Die Option umfasst die SIA-Teilphasen 32-53 für die Zone 1 und das Kältenetz.

Die Firmen HOLINGER AG, Luzern, Contegra AG Integrale Planung, St. Gallen und RKL AG, St. Gallen haben mit der Erstellung des Vorprojekts ihren Auftrag abgeschlossen. Die von den obigen Firmen wesentlich erarbeiteten Projektunterlagen sind den Ausschreibungsunterlagen beigelegt.
Gestützt auf obige Massnahmen werden die HOLINGER AG, Luzern, Contegra AG Integrale Planung, St. Gallen und RKL AG, St. Gallen im Verfahren als Anbieter zugelassen (vgl. Art. 14 IVöB).

Subplaner sind zugelassen. Die Mehrheit der Leistungen ist vom Anbieter zu erbringen.
Mehrfachbewerbungen von Subplanern sind zulässig.

Zahlungen erfolgen ausschliesslich in Schweizer Franken [CHF].
Zahlungsfrist: 30 Tage

Gegen diese Verfügung kann innert 20 Tagen seit Publikation auf www.simap.ch beim Verwaltungsgericht des Kantons St.Gallen, Webergasse 8, 9001 St.Gallen, schriftlich Beschwerde erhoben werden (Art. 52 Abs. 1 i.V.m. Art. 56 der Interkantonalen Vereinbarung über das öffentliche Beschaffungswesen [sGS 841.51]). Die Frist ist eingehalten, wenn die Beschwerde spätestens am letzten Tag der Frist beim Gericht eingereicht oder zu dessen Handen der Schweizerischen Post oder einer schweizerischen diplomatischen oder konsularischen Vertretung übergeben wird (Art. 143 Abs. 1 der Schweizerischen Zivilprozessordnung [SR 272] i.V.m. Art. 30 Abs. 1 des Gesetzes über die Verwaltungsrechtspflege [sGS 951.1]). Die Beschwerde muss einen Antrag sowie eine Darstellung des Sachverhaltes und eine Begründung enthalten. Sie ist zu unterzeichnen und im Doppel einzureichen. Diese Verfügung ist beizulegen. Es gelten keine Gerichtsferien.

Zu jedem Eignungskriterium (EK 1.1 bis EK1.4) ist eine entsprechende Referenz des Anbieters einzureichen. Mehrere Eignungskriterien können dabei durch ein einziges Projekt nachgewiesen werden, sofern die jeweiligen Anforderungen klar ersichtlich sind. Alternativ können auch separate Referenzprojekte für einzelne Eignungskriterien eingereicht werden.
Es gelten die folgenden Mindestanforderungen:
- Die Referenzprojekte müssen die SIA-Teilphasen 31 «Vorprojekt» bis 53 «Inbetriebnahme» abdecken. Kann der Nachweis über die verlangten Phasen nicht mit einem Referenzprojekt erbracht werden, kann ein zweites Referenzprojekt ergänzend beigebracht werden. In diesem zweiten Referenzprojekt müssen die restlichen Anforderungen (Art, Grösse, Komplexität etc.) ebenfalls erfüllt werden.
- Die Referenzprojekte müssen abgeschlossen bzw. zu einem wesentlichen Teil realisiert sein.
- Die Referenzenprojekte müssen in den letzten 10 Jahren durch den Anbieter bearbeitet worden sein (Abschluss der Bearbeitung nicht vor 2016).
- Die eingereichten Referenzprojekte müssen hinsichtlich Aufgabenstellung, Stand der Technik und Komplexität mit dem ausgeschriebenen Projekt vergleichbare Leistungen belegen.
Die Nachweise sind für die folgenden Bereiche zu erbringen:
- EK1.1 Gesamtleitung / Gesamtkoordination
- EK1.2 Tiefbau
- EK1.3 Rohrleitungsbau (Wärme / Kälte)
- EK1.4 Hausanschlüsse
Die Firmenreferenzen EK1.2 bis EK1.4 dürfen von einem Subplaner stammen. In diesem Fall hat der Anbieter eine Bestätigung des Subplaners beizulegen, dass dieser im Auftragsfall die Arbeit ausführen wird.

Deklaration des Umsatzes der letzten drei Jahre in der (den) massgebenden Unternehmenseinheit(en). (Bei Planergemeinschaften sind die addierten Umsätze der beteiligten Unternehmenseinheiten massgebend.)

Unterzeichnete Selbstdeklaration C1.

Gesamthonorar (Grundauftrag und Optionen) inkl. Nebenkosten und Rabatt, exkl. MWST; das tiefste Angebot erhält die Maximalnote; Angebote, die 100 % oder mehr über dem tiefsten Preis liegen, erhalten 0 Punkte; dazwischen wird linear bewertet.

- Projektherausforderungen und Chancen: Aufzeigen der 5 wesentlichsten projektspezifischen Herausforderungen sowie möglicher Massnahmen zu deren Beherrschung sowie der 2 grössten Chancen inkl. deren Auswirkung auf das Projekt (max. 1 DIN-A4-Seiten). (10%)
- Vorgehensplanung und Organisation: Aufzeigen des geplanten Vorgehens, der Terminrisiken und möglicher Massnahmen zu deren Beschränkung sowie der geplanten Organisation inkl. erwarteter Schnittstellen (max. 1 DIN-A4-Seite + Terminplan + Organigramm). (5%)
- Massnahmen zur Förderung der Nachhaltigkeit und Kreislaufwirtschaft: Erkennen der wichtigsten ökologischen Aspekte im Projekt und Aufzeigen von innovativen Massnahmen zu deren Umsetzung (max. 1 A4-Seiten). (5%)

Angaben zur Ausbildung und Berufserfahrung der vorgesehenen Schlüsselpersonen:
1 Projektreferenz mit vergleichbarer Komplexität und Aufgabenstellung der am Vorhaben beteiligten Schlüsselperson. Die angegebenen Referenzen sollen im Wesentlichen die Funktion, die Aufgabenschwerpunkte und die gemachten Erfahrungen aufzeigen. Die (Teil-) Phasen, welche durch die Schlüsselperson bearbeitet wurden und als Referenz angegeben werden, müssen abgeschlossen sein.
Die Referenzen der Schlüsselpersonen ZK3.2 - ZK3.4 dürfen von einem Subplaner stammen. In diesem Fall hat der Anbieter eine Bestätigung des Subplaners beizulegen, dass er im Auftragsfall die Arbeit ausführen wird.
Sprachkenntnisse Deutsch (Muttersprache oder mind. Sprachkompetenz Level C1)
Die Referenzen sind für folgende Schlüsselpersonen anzugeben:
- ZK3.1 Gesamtleitung / Koordination (10%)
- ZK3.2 Fachprojektleiter /-in Tiefbau (10%)
- ZK3.3 Fachprojektleiter /-in Rohrleitungsbau (10%)
- ZK3.4 Fachprojektleiter /-in Hausanschlüsse (10%)
Personalunionen sind für max. 2 Schlüsselpersonen erlaubt.

Die Anbieter präsentieren mit den vorgesehenen Schlüsselpersonen ihre Auftrags- und Projektanalyse. Sie erläutern zudem ihre Referenzprojekte und beantworten offene Fragen der Bauherrschaft.
Falls nach der Auswertung der eingereichten Offerten für Anbietende keine Aussicht auf einen Zuschlag besteht, behält sich der Auftraggeber vor, diese Anbietenden nicht für die Präsentationen einzuladen. Es besteht somit kein Anrecht auf eine Angebotspräsentation.

Fragen sind unter www.simap.ch im "Forum" der entsprechenden Ausschreibung zu stellen. Sie werden bis am 04.12.2026 allen Bezügern der Ausschreibungsunterlagen gleichlautend unter www.simap.ch im "Forum" beantwortet. Nach dem 27.11.2026 eintreffende Fragen werden nicht mehr beantwortet.

- Official source: [SIMAP](https://www.simap.ch/de/project-detail/f78ef787-22ba-4034-b4e9-b76f80de11ad)

## Turn this opportunity into a response.

Analyze the tender documents and build your response with Ziva.

- Understand the requirements
- Find the evidence you need
- Prepare your response

[Get started with Ziva](https://agent.zephior.ai/onboarding/initiate) · [View official notice](https://www.simap.ch/de/project-detail/f78ef787-22ba-4034-b4e9-b76f80de11ad)

## About this notice

- Official source: SIMAP
- Source retrieved: November 12, 2026
- Page updated: November 12, 2026
- Notice reference: 47407 · 47407-01

## Similar tenders

- [110 kV GIS switchgear for three substations](https://zephior.com/tenders/70ec4982-7d80-47f4-a2bf-58a5ff264582/three-110-kv-gis-switchgear-installations-70ec4982) ([Markdown](https://zephior.com/tenders/70ec4982-7d80-47f4-a2bf-58a5ff264582/three-110-kv-gis-switchgear-installations-70ec4982.md)), St. Gallisch Appenzellische Kraftwerke AG (SAK)
- [University of St. Gallen heat and cooling plant renewal: heat pump supply](https://zephior.com/tenders/3b8a2d5f-ade0-4260-bcb0-586218bc27ed/university-of-st-gallen-heat-and-cooling-plant-renewal-heat-pump-supply) ([Markdown](https://zephior.com/tenders/3b8a2d5f-ade0-4260-bcb0-586218bc27ed/university-of-st-gallen-heat-and-cooling-plant-renewal-heat-pump-supply.md)), Kanton St.Gallen, Bau- und Umweltdepartement, Hochbauamt
- [District heating distribution and external connections, Lot 516 Konkordiastrasse West](https://zephior.com/tenders/a9c05714-40b9-42e4-b201-52960f6eeb7c/lucerne-konkordiastrasse-district-heating-lot-516) ([Markdown](https://zephior.com/tenders/a9c05714-40b9-42e4-b201-52960f6eeb7c/lucerne-konkordiastrasse-district-heating-lot-516.md)), St.Galler Stadtwerke
- [Compact fire engine for the Eastern Switzerland fire training centre](https://zephior.com/tenders/e370ee46-8a74-4c3a-aabe-99319d4f089c/compact-fire-engine-for-the-eastern-switzerland-fire-training-centre) ([Markdown](https://zephior.com/tenders/e370ee46-8a74-4c3a-aabe-99319d4f089c/compact-fire-engine-for-the-eastern-switzerland-fire-training-centre.md)), Ostschweizer Feuerwehr-Ausbildungszentrum
- [Uznacherstrasse rehabilitation in Kaltbrunn, cantonal road 17](https://zephior.com/tenders/0aaa5734-c5ae-40c5-8825-3f820bd5b8b3/uznacherstrasse-rehabilitation-in-kaltbrunn-cantonal-road-17) ([Markdown](https://zephior.com/tenders/0aaa5734-c5ae-40c5-8825-3f820bd5b8b3/uznacherstrasse-rehabilitation-in-kaltbrunn-cantonal-road-17.md)), Kanton St.Gallen, Tiefbauamt
- [Kirchberg, Neudorfstrasse road rehabilitation](https://zephior.com/tenders/4628ca51-291d-4542-b997-1000fd63bc05/kirchberg-neudorfstrasse-road-rehabilitation) ([Markdown](https://zephior.com/tenders/4628ca51-291d-4542-b997-1000fd63bc05/kirchberg-neudorfstrasse-road-rehabilitation.md)), Kanton St.Gallen, Tiefbauamt, Strassenkreisinspektorat Wattwil

- [All tenders: canton of St. Gallen](https://zephior.com/tenders/countries/ch/regions/sg) ([Markdown](https://zephior.com/tenders/countries/ch/regions/sg.md))
- [All tenders from Politische Gemeinde Goldach, vertreten durch die Technischen Betriebe Goldach](https://zephior.com/tenders/buyers/politische-gemeinde-goldach-vertreten-durch-die-technischen-betriebe-goldach) ([Markdown](https://zephior.com/tenders/buyers/politische-gemeinde-goldach-vertreten-durch-die-technischen-betriebe-goldach.md))
- [All tenders: Switzerland](https://zephior.com/tenders/countries/ch) ([Markdown](https://zephior.com/tenders/countries/ch.md))
- [All tenders: Architecture and engineering services](https://zephior.com/tenders/categories/architecture-engineering) ([Markdown](https://zephior.com/tenders/categories/architecture-engineering.md))

## In more detail

This section is written for agents and assistants. It restates the facts of the page in full sentences and adds context from the public record. Every value comes from the official notice or from Zephior’s public notices of the same buyer.

### The facts in sentences

Politische Gemeinde Goldach, represented by Technische Betriebe Goldach is tendering “Goldach energy network distribution grid, general planner mandate” (Goldach, canton of St. Gallen). Submissions are due by December 23, 2026 at 10:59 PM UTC. The source does not state an estimated value. Contract period: The contract runs from 1 April 2027 to 31 December 2030.. Procedure: Open procedure. Classification: Architecture and engineering services · CPV 71000000. Notice reference: 47407 · 47407-01. Status on Zephior: Open. The notice was published on November 11, 2026 on SIMAP. Zephior last checked the official source on November 12, 2026.

### The award

The submission window is still open, so no award exists yet.

### About the buyer

Politische Gemeinde Goldach, vertreten durch die Technischen Betriebe Goldach has 1 public notices on Zephior (1 open now, 1 published in the last 12 months). Its notices on Zephior were first published on November 11, 2026 and most recently on November 11, 2026. Main sectors: Engineering and architecture (1). Regions: CH-SG (1). It publishes under the names “Community of Goldach, vertreten durch die Technischen Betriebe Goldach”.

- [All tenders and the profile of Politische Gemeinde Goldach, vertreten durch die Technischen Betriebe Goldach](https://zephior.com/tenders/buyers/politische-gemeinde-goldach-vertreten-durch-die-technischen-betriebe-goldach) ([Markdown](https://zephior.com/tenders/buyers/politische-gemeinde-goldach-vertreten-durch-die-technischen-betriebe-goldach.md))

### Terms used on this page

- **Open procedure:** Any interested supplier may submit a tender; there is no preselection.

### Where to go next

- [110 kV GIS switchgear for three substations](https://zephior.com/tenders/70ec4982-7d80-47f4-a2bf-58a5ff264582/three-110-kv-gis-switchgear-installations-70ec4982) ([Markdown](https://zephior.com/tenders/70ec4982-7d80-47f4-a2bf-58a5ff264582/three-110-kv-gis-switchgear-installations-70ec4982.md))
- [University of St. Gallen heat and cooling plant renewal: heat pump supply](https://zephior.com/tenders/3b8a2d5f-ade0-4260-bcb0-586218bc27ed/university-of-st-gallen-heat-and-cooling-plant-renewal-heat-pump-supply) ([Markdown](https://zephior.com/tenders/3b8a2d5f-ade0-4260-bcb0-586218bc27ed/university-of-st-gallen-heat-and-cooling-plant-renewal-heat-pump-supply.md))
- [District heating distribution and external connections, Lot 516 Konkordiastrasse West](https://zephior.com/tenders/a9c05714-40b9-42e4-b201-52960f6eeb7c/lucerne-konkordiastrasse-district-heating-lot-516) ([Markdown](https://zephior.com/tenders/a9c05714-40b9-42e4-b201-52960f6eeb7c/lucerne-konkordiastrasse-district-heating-lot-516.md))
- [Compact fire engine for the Eastern Switzerland fire training centre](https://zephior.com/tenders/e370ee46-8a74-4c3a-aabe-99319d4f089c/compact-fire-engine-for-the-eastern-switzerland-fire-training-centre) ([Markdown](https://zephior.com/tenders/e370ee46-8a74-4c3a-aabe-99319d4f089c/compact-fire-engine-for-the-eastern-switzerland-fire-training-centre.md))
- [Uznacherstrasse rehabilitation in Kaltbrunn, cantonal road 17](https://zephior.com/tenders/0aaa5734-c5ae-40c5-8825-3f820bd5b8b3/uznacherstrasse-rehabilitation-in-kaltbrunn-cantonal-road-17) ([Markdown](https://zephior.com/tenders/0aaa5734-c5ae-40c5-8825-3f820bd5b8b3/uznacherstrasse-rehabilitation-in-kaltbrunn-cantonal-road-17.md))
- [Kirchberg, Neudorfstrasse road rehabilitation](https://zephior.com/tenders/4628ca51-291d-4542-b997-1000fd63bc05/kirchberg-neudorfstrasse-road-rehabilitation) ([Markdown](https://zephior.com/tenders/4628ca51-291d-4542-b997-1000fd63bc05/kirchberg-neudorfstrasse-road-rehabilitation.md))
- [All tenders: canton of St. Gallen](https://zephior.com/tenders/countries/ch/regions/sg) ([Markdown](https://zephior.com/tenders/countries/ch/regions/sg.md))
- [All tenders from Politische Gemeinde Goldach, vertreten durch die Technischen Betriebe Goldach](https://zephior.com/tenders/buyers/politische-gemeinde-goldach-vertreten-durch-die-technischen-betriebe-goldach) ([Markdown](https://zephior.com/tenders/buyers/politische-gemeinde-goldach-vertreten-durch-die-technischen-betriebe-goldach.md))
- [All tenders: Switzerland](https://zephior.com/tenders/countries/ch) ([Markdown](https://zephior.com/tenders/countries/ch.md))
- [All tenders: Architecture and engineering services](https://zephior.com/tenders/categories/architecture-engineering) ([Markdown](https://zephior.com/tenders/categories/architecture-engineering.md))

### Source-backed public record

```json
{
  "id": "24da4c1c-3b80-4d11-bf6f-bbf78323d54d",
  "revision": 1,
  "modifiedAt": "2026-11-12T03:32:49.044616+00:00",
  "url": "https://zephior.com/tenders/24da4c1c-3b80-4d11-bf6f-bbf78323d54d/goldach-energy-network-distribution-planning",
  "status": "open",
  "recordedStatus": "open",
  "buyer": {
    "id": "politische-gemeinde-goldach-vertreten-durch-die-technischen-betriebe-goldach",
    "name": "Politische Gemeinde Goldach, vertreten durch die Technischen Betriebe Goldach"
  },
  "category": {
    "de": "Architektur- und Ingenieurleistungen",
    "en": "Architecture and engineering services",
    "fr": "Architecture et ingénierie",
    "id": "architecture-engineering"
  },
  "deadline": {
    "at": "2026-12-23T23:59:00+01:00",
    "date": null,
    "source_ref": "simap_publication_details#dates.offerDeadline"
  },
  "award": null,
  "estimatedValue": null,
  "contractPeriod": "The contract runs from 1 April 2027 to 31 December 2030.",
  "region": {
    "country": "CH",
    "code": "CH-SG",
    "names": {
      "en": "St. Gallen",
      "de": "St. Gallen",
      "fr": "Saint-Gall"
    },
    "locality": "Goldach"
  },
  "originalSource": {
    "url": "https://www.simap.ch/de/project-detail/f78ef787-22ba-4034-b4e9-b76f80de11ad",
    "title": "Energieverbund Goldach: Verteilnetz",
    "issuer": "Community of Goldach, vertreten durch die Technischen Betriebe Goldach",
    "status": "open",
    "language": "en",
    "location": "9403 Goldach, SG, CH",
    "deadline_at": "2026-12-23T22:59:00+00:00",
    "description": "The Regional Water Supply St. Gallen (RWSG) is currently constructing the new Riet II lakewater plant. As part of this project, the municipality of Goldach has the opportunity to make use of the new lake water intake and thereby establish a thermal network. Using large-scale heat pumps, lake water can be utilized as a renewable energy source to provide environmentally friendly heating for households, public buildings and commercial premises. The project is divided into two sub-projects: Sub-project 1 – Energy centre Sub-project 2 – Distribution network The basic contract covers SIA sub-phase 31 (preliminary design) – distribution network. The option covers SIA sub-phases 32–53 for Zone 1 and the district cooling. The general planner’s mandate covers the following services and specialist areas: - Overall management and coordination - Civil engineering - Pipeline construction - private connections",
    "country_code": "CH",
    "published_at": "2026-11-11T23:00:00+00:00",
    "contract_type": "service",
    "deadline_date": null,
    "procedure_type": "open",
    "reference_numbers": [
      "47407",
      "47407-01"
    ],
    "classification_codes": [
      {
        "code": "71000000",
        "system": "CPV",
        "provenance": "source_declared"
      }
    ]
  },
  "sources": [
    {
      "ref": "canonical_snapshot",
      "url": "https://www.simap.ch/de/project-detail/f78ef787-22ba-4034-b4e9-b76f80de11ad",
      "kind": "canonical_snapshot",
      "retrieved_at": "2026-11-11T23:22:15.423950Z"
    },
    {
      "ref": "simap_project_header",
      "url": "https://www.simap.ch/api/publications/v2/project/f78ef787-22ba-4034-b4e9-b76f80de11ad/project-header",
      "kind": "official_notice_api",
      "retrieved_at": "2026-11-12T03:23:14Z"
    },
    {
      "ref": "simap_publication_details",
      "url": "https://www.simap.ch/api/publications/v1/project/f78ef787-22ba-4034-b4e9-b76f80de11ad/publication-details/cf781b7b-3e25-4c6c-b727-8c595dd700cc",
      "kind": "official_notice_api",
      "retrieved_at": "2026-11-12T03:23:15Z"
    }
  ],
  "keyFacts": [
    {
      "label": "Buyer",
      "value": "Politische Gemeinde Goldach, represented by Technische Betriebe Goldach",
      "source_ref": "canonical_snapshot#/issuer"
    },
    {
      "label": "Procedure",
      "value": "Open procedure",
      "source_ref": "canonical_snapshot#/procedure_type"
    },
    {
      "label": "Offer deadline",
      "value": "23 December 2026, 23:59 CET (UTC+01:00)",
      "source_ref": "simap_publication_details#dates.offerDeadline"
    },
    {
      "label": "Questions",
      "value": "Submitted through the SIMAP forum by 27 November 2026; answers by 4 December 2026",
      "source_ref": "simap_publication_details#dates.qnas"
    },
    {
      "label": "Contract period",
      "value": "1 April 2027 to 31 December 2030, with the option for zone 1 and the cooling network",
      "source_ref": "simap_publication_details#procurement.contractPeriod"
    },
    {
      "label": "Fee basis",
      "value": "Total fee for the basic contract and options, including expenses and discount, excluding VAT",
      "source_ref": "simap_publication_details#criteria.awardCriteria"
    },
    {
      "label": "Offer validity",
      "value": "Until 30 July 2027",
      "source_ref": "simap_publication_details#dates.offerValidityDeadlineDate"
    },
    {
      "label": "Payment",
      "value": "In Swiss francs, payment term 30 days",
      "source_ref": "simap_publication_details#terms.termsOfPayment"
    },
    {
      "label": "Contact",
      "value": "Technische Betriebe Goldach, Marmorstrasse 3, 9403 Goldach; +41 58 228 78 78; https://tb-goldach.ch/",
      "source_ref": "simap_publication_details#project-info.procOfficeAddress"
    },
    {
      "label": "Location",
      "value": "Goldach, canton of St. Gallen",
      "source_ref": "canonical_snapshot#/location"
    }
  ],
  "noticeFacts": {
    "lots": [],
    "schedule": [
      {
        "event": "Question deadline",
        "value": "27 November 2026, through the SIMAP forum",
        "source_ref": "simap_publication_details#dates.qnas"
      },
      {
        "event": "Answers to questions",
        "value": "4 December 2026",
        "source_ref": "simap_publication_details#dates.qnas"
      },
      {
        "event": "Offer deadline",
        "value": "23 December 2026, 23:59 CET (UTC+01:00)",
        "source_ref": "simap_publication_details#dates.offerDeadline"
      },
      {
        "event": "Contract period",
        "value": "1 April 2027 to 31 December 2030",
        "source_ref": "simap_publication_details#procurement.contractPeriod"
      },
      {
        "event": "Offer validity",
        "value": "Until 30 July 2027",
        "source_ref": "simap_publication_details#dates.offerValidityDeadlineDate"
      }
    ],
    "requirements": [
      {
        "text": "Offers in German, digitally through SIMAP.",
        "source_ref": "simap_publication_details#project-info.offerTypes"
      },
      {
        "text": "Consortia are permitted; subplanners are permitted, and the majority of services must be provided by the bidder.",
        "source_ref": "simap_publication_details#terms.subContractorNote"
      },
      {
        "text": "Qualification EK 1.1 to EK 1.4: one project reference per area covering SIA sub-phases 31 to 53, within the last 10 years.",
        "source_ref": "simap_publication_details#criteria.qualificationCriteria"
      },
      {
        "text": "Qualification EK 2: annual contract volume not above 30% of the annual turnover of the relevant business unit, with a three-year turnover declaration.",
        "source_ref": "simap_publication_details#criteria.qualificationCriteria"
      },
      {
        "text": "Qualification EK 3: organisational and financial capacity, with signed self-declaration C1.",
        "source_ref": "simap_publication_details#criteria.qualificationCriteria"
      },
      {
        "text": "HOLINGER AG, Contegra AG Integrale Planung and RKL AG, which prepared the preliminary design, are admitted as bidders under Art. 14 IVöB.",
        "source_ref": "simap_publication_details#terms.preInvolvedVendor"
      },
      {
        "text": "Payment in Swiss francs with a payment term of 30 days.",
        "source_ref": "simap_publication_details#terms.termsOfPayment"
      }
    ],
    "award_criteria": [
      {
        "text": "Total fee for the basic contract and options, including expenses and discount, excluding VAT, 30%; the lowest offer receives the maximum mark.",
        "source_ref": "simap_publication_details#criteria.awardCriteria"
      },
      {
        "text": "Order and project analysis, project challenges and opportunities, 20%.",
        "source_ref": "simap_publication_details#criteria.awardCriteria"
      },
      {
        "text": "Competence of key persons, including one comparable project reference per key person, 40%.",
        "source_ref": "simap_publication_details#criteria.awardCriteria"
      },
      {
        "text": "Presentation with the key persons on the order and project analysis and reference projects, 10%.",
        "source_ref": "simap_publication_details#criteria.awardCriteria"
      }
    ],
    "estimated_value": null
  },